Quarterly Activities Report - September 2024
Released
Released
Announcement PDF
ASX Release 23 October 2024
September 2024 Quarterly Report
Ramp-up proceeding to plan as first
production column hits nameplate capacity
Second column now operating and third column under construction, putting Honeymoon on track
to meet FY25 production guidance; Plus, first shipment completed and cash received
Highlights
Honeymoon Uranium Project, South Australia
Operations
•
89,516 lbs of U3O8 drummed during the September quarter (June quarter 28,844 lbs)
•
NIMCIX production column 1 achieved nameplate uranium production; NIMCIX 2 now
operational
•
Construction of NIMCIX 3 proceeding to plan and on target for commissioning in December
quarter, 2024
•
Achieved major milestone of first shipment of 57,000 lbs U308; The U308 met all converter
quality metrics
•
Receipts of $23.4M from sale of 200,000 lbs U308 as part of an existing sales contract
•
Preliminary update on costs to be provided once NIMCIX 3 is commissioned
•
Honeymoon is on track to meet production guidance of 850,000 lbs of U308 in FY25
Alta Mesa Uranium Operation, South Texas (Boss 30%)
•
Official opening on 3 October 2024, featuring George W. Bush, the 43rd President of the US
•
Alta Mesa continues to dry, package and ship uranium yellowcake (U308)
•
Alta Mesa expected to reach full operational capacity of 1.5M lbs of U308 a year by 2026. Boss’
share of Alta Mesa production is 30 per cent (450,000 lbs U308 a year at nameplate capacity)
Corporate
•
As at 30 September 2024, Boss held liquid assets of A$244.9M; Boss has no debt
•
Well-positioned to benefit from rising uranium prices with most of Honeymoon Life of Mine
production and all of Alta Mesa production uncontracted
•
Boss continues to strengthen its senior management team in line with the Company’s growing
status as a global uranium producer with the appointment of experienced COO Matt Dusci
FOR FURTHER INFORMATION PLEASE CONTACT:
Boss Energy Limited
ABN 38 116 834 336
Duncan Craib - Managing Director/ CEO
+61 (08) 6263 4494
ASX: BOE
OTCQX: BQSSF
Level 1, 420 Hay Street, Subiaco
Western Australia 6008
Paul Armstrong – Public Relations
+61 (08) 9388 1474
www.bossenergy.com
@Boss_Energy
Boss Energy Limited (ASX: BOE; OTCQX: BQSSF) is pleased to report on a strong September 2024 quarter,
during which the Company continued to ramp up uranium production at Honeymoon in line with its
targets and saw first production at its 30 per cent-owned Alta Mesa Project in South Texas.
Boss Managing Director Duncan Craib said: “Our strategy is proceeding to plan on all fronts.
Honeymoon’s key metrics are all in line with our targets and we are on track to meet our FY25 production
guidance.
“The first production column hit nameplate capacity, the second column is now operational and the
third is under construction.
“We made our first shipment from Honeymoon and we are generating cashflow from sales. As a result,
we are in an extremely strong financial position with liquid assets of A$245M and no debt.
“The recent start of production at Alta Mesa will also help drive ongoing growth in our production and
cashflow as the project ramps up.
“The combination of this increasing production profile and the fact that most of it is uncontracted means
we are ideally placed to capitalise on the strong outlook for uranium prices.
“The supply-demand fundamentals in the uranium market are increasingly favourable and long-term
contract prices are rising.
“The growing demand for clean energy, particularly stemming from the rapidly expanding AI industry,
further strengthens the outlook for uranium and supports our strategic decision to commit to contracts
in a gradual manner, maximising our ability to capitalise on rising prices while maintaining financial
security”.
Strong Balance Sheet
As at 30 September 2024, Boss has no debt and $244.9M of liquid assets (being cash, liquid investments
and physical uranium). The uranium inventory was valued at A$145.4M, including 200,000lbs uranium
loaned to enCore Energy Corp. ("enCore") (NASDAQ: EU) (TSXV: EU), which is repayable in cash or in
kind.
Unrestricted cash and cash equivalents stood at $66.6M (which excludes a fully cash-backed
environmental bond of $13.5M) and listed investments (including the Company’s investment in enCore)
were valued at $32.9M.
First shipment, sales and cash received
During the quarter, Boss sold 200,000 lbs U308 to a European nuclear utility under an existing sales
contract, receiving cash of AU$23.4M.
Honeymoon also celebrated its milestone first shipment of 57,000 lbs U308 to the Honeywell Uranium
Hexafluoride Processing Facility in Metropolis, Illinois, USA. Feedback from the conversion facility,
based on a representative sample, noted clean, quality U308 product, with approval granted for future
bulk shipments to the facility.
Executive Appointments
During the quarter, Boss announce the appointment of highly experienced resources executive Mr Matt
Dusci as Chief Operating Officer.
Mr Dusci has more than 25 years of experience in all facets of the mining industry, including technical
studies, project development, operations, business development, strategy and executive leadership. His
experience spans a diverse range of commodities, including battery metals.
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
Page 2
For the past 10 years, Mr Dusci has held several executive positions at IGO Limited (ASX: IGO). These
include Acting CEO, Chief Operating Officer and Chief Growth Officer. He has played a major role in the
growth, development and transformation of IGO.
Mr Craib said: “With the ramp up at Honeymoon proceeding so well, we are advancing our strategy to
grow the project’s inventory, production rate and mine life.
“As part of this strategy, we are committed to building a world-class team of highly skilled and experienced
people who can help ensure we maximise our huge opportunities.
“We maximise our ability to generate the best possible results, including consistent reliable production
and ongoing growth, if we have the best possible team.
“Matt’s knowledge and experience at both a project management level and as a senior resource industry
executive will be immensely valuable as we implement our strategy”.
Honeymoon Production Results for the September 2024 Quarter
As expected, and in-line with Feasibility Study forecasts, Honeymoon’s production continues to increase
as set out in the results for the September 2024 quarter.
In August 2024, NIMCIX 1 achieved nameplate capacity.
NIMCIX 2 is now operational as production ramp-up continues to perform inline with expectations, and
construction of NIMCIX 3 is proceeding to plan and on target for commissioning in Q4, 2024.
Table 1: Operational physicals for the September 2024 Quarter as compared to the June Quater 2024
Process
Wellfields online
Wells online
IX Columns operational
IX Flow (total)1
PLS to IX tenor (weighted average)2
IX Recovery (weighted average)2
IX Production (total)1
U3O8 Drummed (total)
Unit
September Q1 FY25
(m3)
(U3O8 mg/l)
(%)
(lbs)
(lbs)
1
16
1
729,299
71
97.2
110,050
89,516
June Q4 FY24
1
16
1
327,066
80
99.7
57,364
28,844
Notes: (1) Conversions: There are 1,000 litres per m3 and 0.0000022 lbs per mg. (2) The weighted average is
calculated based on total flow for the quarter.
Initiatives to optimise plant performance are ongoing as learnings are implemented.
It is important to note that while the tenors being achieved from initial wellfields exceed the average LOM
tenors forecast in the Feasibility Study1, the project is still in the ramp-up phase and therefore these tenors
should not be extrapolated across the LOM.
Given the time taken to ramp-up wellfields in ISR projects, preliminary cost updates will be provided once
NIMCIX 3 is commissioned.
The northern part of South Australia and far west New South Wales experienced an abnormal weather
event on 16 and 17th October that affected power supply to these regions. The power supply to the
Honeymoon project has also been impacted, with power restrictions imposed during the night. These
impacts are being effectively managed with only limited impacts to the ramp-up plan. There is no change
to forecast production of 850,000 lbs of U308 for FY25.
1
Refer to ASX: BOE announcement dated 21 June 2021.
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
Page 3
Honeymoon Construction Activities
NIMCIX 1 is producing at nameplate capacity, NIMCIX 2 has commenced production, and NIMCIX 3 is on
track for completion in December 2024.
Figure 1: From left to right, NIMCIX columns 1, 2 and 3
Columns 4, 5 and 6 will be commissioned in 2025 to enable ramp-up to continue to be in line with
Feasibility Study forecasts, to achieve Honeymoon’s nameplate capacity of 2.45Mlb/annum of U308.
Figure 2: Wellfields 1 and 2 in operation
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
Page 4
Boss Sales
During the quarter Boss secured its third binding sales contract, signing a market-linked deal with a US
power utility. Sales agreements now total circa 3.5Mlbs of U308 from 2024 to 2033, providing Boss with
further financial certainty while enabling it to retain ongoing exposure to increases in the uranium price
The sales agreements for the supply of uranium from its Honeymoon Project in South Australia, is based
on market-related pricing with other terms and conditions of the agreement in line with industry
standards.
Boss’ contracting strategy is to monitor the markets and layer in contracts, predominantly market related
for the uncommitted supply from Honeymoon and Alta Mesa, to optimise future pricing and, in the near
term, to ensure profitability and cash flow as production ramps up.
Alta Mesa
Boss is currently the only multi-asset uranium producer on the ASX with the commencement of
production during the quarter at its 30 per cent-owned Alta Mesa In-Situ Recovery (“ISR”) Central
Processing Uranium Plant and Wellfields (“Alta Mesa Project”) in South Texas.
The Alta Mesa Project continues to dry, package and ship uranium yellowcake with the most recent
shipment in the past week.
On 14 June 2024, Boss advised that Alta Mesa’s uranium production is forecast to ramp up to a steadystate rate of 1,500,000lbs a year by 2026 with additional drying capacity of 500,000lbs a year. Boss owns
the sale and marketing rights over its pro-rata share (450,000lbs at nameplate capacity). Please refer to
enCore’s announcement dated 13 June 2024 for further information.2
On 3 October 2024, the grand opening celebration of Alta Mesa took place on site in South Texas. The
private event, attended by 300 guests, featured George W. Bush, the 43rd President of the United States.
Please refer to enCore’s announcement dated 8 October 2024 for further information.3
Furthermore, on 16 October 2024, Boss reported continued strong drilling results from Alta Mesa. The
results were reported by Alta Mesa’s 70 per cent owner enCore.
The results of the drilling, which was designed to expand the producing wellfield capacity, continue to
significantly exceed the cut-off grade thickness requirements for ISR of uranium. enCore also reported
that production from its first wellfield continues to progress with increases in the number of Alta Mesa
production and injection wells on schedule for 2024 and continuing into 2025.
The Alta Mesa wellfield drilling operations, which commenced in March 2023, are advancing rapidly with
80 holes drilled since the previous update announced on 18 March 20244. In total, 749 drill holes have
been completed through mid-September 2024. At present there are seven (7) drill rigs in full operation at
Alta Mesa, with plans to double that number over the next twelve (12) months.
Please refer to enCore’s announcement dated 15 October 2024 for further information5.
2 enCore Energy Corp. announcement titled ‘enCore Energy Commences Uranium Production at its Second South Texas Project’ dated 13 June 2024
https://www.sedarplus.ca/csa-party/records/document.html?id=b5b37208e04209072f3a850b53c88385cc67adc9220730b1094ad5024299b241
3
enCore Energy Corp. announcement titled ‘enCore Energy Hosts Grand Opening of the Alta Mesa Uranium Plant with George W. Bush, the 43rd
President of the United States’ dated 8 October 2024
https://www.sedarplus.ca/csa-party/records/document.html?id=7ab880664a35ef6b20bec1baf56d27352c9cf8dd3cf9bc437d8568a2065b6587
4 enCore Energy Corp. Announcement titled 'enCore Energy Encounters Highest Grade Drill Results at Alta Mesa Uranium Project; Provides Status
on South Texas Production Operations' dated 18 March 2024
https://www.sedarplus.ca/csa-party/records/document.html?id=ce7cfbfb51537487f6e2afdf08ad57e975b307e414c9229afce2926422a4190f
5 enCore Energy Corp. announcement titled ‘enCore Energy Continues to Encounter High Grade Drill Results from the Alta Mesa Uranium Project.’
dated 15 October 2024
https://www.sedarplus.ca/csa-party/records/document.html?id=744fc68bc7324711050b527b28fee210b7280edc50dc28686e95c17c76bb4c2d
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
Page 5
The Alta Mesa Project, which consists of over 200,000 acres plus the central processing plant and
wellfields, is managed by experienced uranium producer, and partner, enCore.
Boss acquired its 30 per cent interest in the Alta Mesa Project in February 2024 from enCore and its wholly
owned subsidiary, enCore Energy U.S. Corp., a highly credentialed United States uranium developer and
operator, for US$60 million cash (see ASX release dated 27 February 2024).
Uranium Market Analysis
Uranium fundamentals are strengthening as support for nuclear power grows. The long-term price
continued to rise during the quarter, spot prices declined during the same period. Supply and demand
fundamentals are strengthening which should be reflected in upward pressure on pricing in the coming
months.
One of the key messages at the WNA uranium symposium in September was the significant increase in
the demand for electricity. The presence of representatives from Microsoft, and the steel and concrete
industries highlighted the unforeseen interest of these sectors in nuclear power as a viable source of
supply for industrial scale clean reliable electricity capacity. Later in September this message was
reinforced by the deal between Microsoft and Constellation Energy. Microsoft will purchase the entire
electric generating capacity of Three Mile Island Unit 1 over the next 20 years. The trend in restarting
reactors which were closed for economic reasons looks likely to continue as near-term electricity forecasts
are revised upwards.
On the demand side the interest in term contracting by utilities remains high. The restart of shut down
reactors is likely to impact the uranium market in the near term, life extensions and new build increase
demand in the mid and longer term.
Geopolitical and supply chain concerns are shrinking the pool of existing supply available to Western
Utilities. New mines are needed to fill this gap and higher prices are needed to incentivise new mines.
Boss continues to ramp up its production and is well positioned to meet the need for secure and stable
uranium.
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
Page 6
Appendix 5B disclosures
In line with its obligations under ASX Listing Rule 5.3.5, Boss notes that the only payments to related
parties of the Company, as disclosed in the Appendix 5B (Quarterly Cashflow Report) for the period ended
30 September 2024, consist of executive director and chief financial officer salaries and wages (including
superannuation) and payment of non-executive director fees.
During the quarter ended 30 September 2024, the Company spent approximately $6.8M on project and
exploration activities relating to its Honeymoon and Alta Mesa Projects. These activities included:
Technical studies costs
Construction equipment
Wellfield drilling and development costs
Engineering and construction expenses
Mineral exploration and evaluation costs
In addition to these activities the Company continued to incur costs relating to the ongoing maintenance
activities required at Honeymoon. The expenditure represents direct costs associated with these
activities as well as capitalised wages which can be directly attributable to Honeymoon.
This ASX announcement was approved and authorised by the Board of Boss Energy Limited.
For further information, contact:
Duncan Craib
Chief Executive Officer
P: +61 (8) 6263 4494
E: boss@bossenergy.com
For media enquiries, contact:
Paul Armstrong
Read Corporate
P: +61 (8) 9388 1474
E: info@readcorporate.com
Reference to previous ASX announcements
In relation to the results of the Enhanced Feasibility Study announced on 21 June 2021, the Company
confirms that all material assumptions underpinning the production target and forecast financial
information included in that announcement continue to apply and have not materially changed.
The mineral resource estimates in this announcement were reported by the Company in accordance
with listing rule 5.8 on 25 February 2019. The Company confirms it is not aware of any new information
or data that materially affects the information included in the previous announcement and that all
material assumptions and technical parameters underpinning the estimates in the previous
announcement continue to apply and have not materially changed.
Forward-Looking Statements
This announcement includes forward-looking statements. These forward-looking statements are based
on the Company’s expectations and beliefs concerning future events. Forward-looking statements are
necessarily subject to risks, uncertainties, and other factors, many of which are outside the control of
Boss Energy, which could cause actual results to differ materially from such statements. Boss Energy
makes no undertaking to subsequently update or revise the forward-looking statements made in this
announcement, to reflect the circumstances or events after the date of this announcement.
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
Page 7
Appendix One:
Schedule of Mining Tenements
The following information is provided pursuant to Listing Rule 5.3.3 for the quarter ended 30 June 2024.
Tenement Name
Location
Licence Number
Interest
Yarramba
South Australia
EL6510
100%
South Eagle
South Australia
EL6081
100%
Gould’s Dam
South Australia
EL6512
100%
Katchiwilleroo
South Australia
EL6511
100%
Ethiudna
South Australia
EL6020
100%
Gould’s Dam
South Australia
RL83-85
100%
Honeymoon Mine
South Australia
ML6109
100%
Prairie Dam
South Australia
EL6962
75%
Chalker Dam
South Australia
EL6963
75%
Oakvale
South Australia
EL6964
75%
Gairloch
South Australia
EL6965
75%
Venus Bay
South Australia
EL6992
100%
Darke Peak
South Australia
ELA2024_00018
100%
Rudall
South Australia
EL6999
100%
There were no mining tenement acquisitions or divestments during the quarter.
EL6512, 6511, 6020, 6510 and 6081 are subject to an earn-in agreement with First Quantum Minerals in
respect to the base and precious metal rights. Refer ASX release dated 10 February 2022 for further
information.
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
Page 8
Honeymoon Project Mineral Resource
Honeymoon’s Mineral Resource (lower cut-off of 250 ppm U3O8)
Classification
Tonnage
(Million Tonnes)
Average Grade
(ppm U3O8)
Contained Metal
(Mkg, U3O8)
Contained Metal
(Mlb, U3O8)
Measured
3.1
1,100
3.4
7.6
Indicated
18.4
630
12.0
25.5
Inferred
30.9
570
18.0
38.5
Total
52.4
620
32.5
71.6
The global Honeymoon Mineral Resource stands at 71.6 Mlb (52.4Mt) with an average grade of 620ppm
U308, using a cut-off grade of 250ppm.
The current Honeymoon restart feasibility studies utilise only a portion of Honeymoon’s JORC resource,
excluding 36Mlb of JORC resource outside the HRA, which could expand the mine life, and Boss’ defined
exploration target could potentially extend the mine life beyond the initial 11 years and increase the
production profile. Honeymoon’s Federal EPIP Act approvals allow export of more than 3Mlbs/annum
U3O8 equivalent.
In addition to the global Mineral Resource, the Honeymoon Uranium Project also has an Exploration
Target range of 28 Mt to 133 Mt of mineralisation at a grade of 340 ppm to 1,080 ppm U308 for a contained
58Mlbs to 190Mlbs U308 (26,300 to 86,160 tonnes of contained U308), using a cut-off of 250ppm6. Note
the potential quantity and grade of the Exploration Target range is conceptual in nature. There has been
insufficient exploration to estimate a Mineral Resource and it is uncertain whether future exploration will
result in the definition of a Mineral Resource.
6 Refer to ASX: BOE announcement dated 25 March 2019.
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
Page 9
Alta Mesa Project Mineral Resource
Alta Mesa & Mesteña Grande Mineral Resource
Summary (0.30 GT cut-off)1,2,3
Tons
Avg. Grade
(% U3O8)
Pounds
Total Measured Mineral Resource1
54,000
0.152
164,000
Alta Mesa Indicated Mineral Resource
1,397,000
0.106
2,959,000
119,000
0.120
287,000
Total Measured & Indicated Resources
1,570,000
0.109
3,410,000
Alta Mesa Inferred Mineral Resource
1,263,000
0.126
3,192,000
Mesteña Grande Inferred Mineral Resource
5,733,000
0.119
13,601,000
Total Inferred Resources
6,996,000
0.120
16,793,000
Mesteña Grande Indicated Mineral Resource
1. Represents that portion of the in-place mineral resource that are estimated to be recoverable within existing wellfields.
Wellfield recovery factors have not been applied to indicated and inferred mineral resources.
2. Technical Report Summary for the Alta Mesa Uranium Project, Brooks and Jim Hogg Counties, Texas, National Instrument
43-101, Technical Report prepared for enCore Energy Corp, Doug Beahm, P.E. 19 January 2023.
3. For the purposes of ASX Listing Rule 5.12, Boss Energy cautions that the mineral resources for the Alta Mesa Project are not
reported in accordance with the Australasian Code for Reporting of Mineral Resources and Ore Reserves 2012 (JORC Code).
The mineral resource estimate at the Alta Mesa Project is a foreign estimate prepared in accordance with Canadian National
Instrument 43-101. A competent person has not done sufficient work to classify the foreign estimate as a mineral resource
in accordance with the JORC Code, and it is uncertain whether further evaluation and exploration will result in an estimate
reportable under the JORC Code.
Foreign Resource Estimate
Please refer to Boss Energy's announcement to the ASX market announcements platform dated 6
December 2023 for additional technical information relating to the foreign resource estimate for the
Alta Mesa Project. Boss Energy confirms it is not in possession of any new information or data relating
to the foreign resource estimate that materially impacts on the reliability of the estimate or Boss
Energy's ability to verify the foreign estimate as a mineral resource in accordance with the JORC Code.
Boss Energy confirms that the supporting information provided in Boss Energy's announcement to the
ASX market announcements platform on 6 December 2023 continues to apply and has not materially
changed.