IX testing paves way for first drum of uranium this quarter
Released
Released
Announcement PDF
ASX Release February 29, 2024
Honeymoon Uranium Project, South Australia
Key production tests pave way for
first drum of uranium this quarter
Testing of the Ion-Exchange circuit, which is central to the processing plant,
ensures Honeymoon remains on time and on budget.
Boss Energy Limited (ASX: BOE; OTCQX: BQSSF) is pleased to announce it has passed another key
milestone in the development of its Honeymoon project, with the start of commissioning the first IonExchange (IX) circuit within the processing plant.
The rapid progress being made on site has also resulted in successful modification and refurbishment
of the re-agent systems.
These major achievements mean Honeymoon is now running 24 hours a day, seven days a week,
further accelerating its push towards production and ramp-up.
Boss Managing Director Duncan Craib said: “The start of commissioning the IX circuit is highly
significant because it shows Boss is on track to produce its first drum of yellow cake this quarter.
“This key milestone follows the continuous operation of the wellfields, water treatment plant, RO
system and required reagents.
“We are now in the final stages of putting all the pieces of the project together and remain comfortably
on budget and on schedule.
“Our success to date has been underpinned by having our own in-house design, construction, and
commissioning team, which has given us greater efficiencies and agilities than would be the case had
we used an EPCM or full contractor development model.
“This team will also deliver substantial ongoing advantages to Boss as we grow Honeymoon, utilising
more of our significant resource and exploration upside and leveraging the infrastructure we have
established.
“With the uranium price recently hitting US$100 a pound, we are perfectly positioned to capitalise on
this huge opportunity.
FOR FURTHER INFORMATION PLEASE CONTACT:
Boss Energy Limited
ABN 38 116 834 336
Duncan Craib - Managing Director/ CEO
+61 (08) 6263 4494
ASX: BOE
OTCQX: BQSSF
Level 1, 420 Hay Street, Subiaco
Western Australia 6008
Paul Armstrong – Public Relations
+61 (08) 9388 1474
www.bossenergy.com
@Boss_Energy
IX Processing plant
Hydro testing the new IX circuit, which is central to the processing plant, will enable highly efficient
capture, concentration, and purification of the uranium from the wellfields. This will result in increased
throughput, more production and lower costs than was possible using the solvent extraction system
previously employed at Honeymoon.
Once hydrotesting is completed, Honeymoon will finalise the control circuits and run the system with RO
water followed by Pregnant Leach Solution (PLS). Uranium will then be concentrated suitable for
precipitation and calcined to produce a high-quality saleable uranium oxide (U3O8) product.
The IX circuit will drive efficiencies at Honeymoon, increasing production throughput to nameplate
capacity of 2.45Mlb/annum of U3O8 while reducing ramp up time and technical risks. It will also reduce
operating costs to industry benchmarks. This was proven by the extensive tests conducted by Boss and
leading independent industry experts, before and during the Honeymoon feasibility studies.
Pregnant Leach Solution
Honeymoon successfully achieved its commissioning target of filling the PLS pond with production tenors
of uranium solution from the pre-flushed wellfields by 31 December 2023. This was achieved in
preparation for commissioning the IX circuit, with the first drum of uranium remaining on track to be
commercially produced as planned in Q1 2024.
Honeymoon will now start leaching the wellfields with optimal lixiviant to achieve higher tenors of
uranium. This involves fortifying the pre-conditioned groundwater with reagents prior to injecting the
lixiviant into and through the orebody to dissolve uranium. The uranium-rich solution is then pumped to
the surface via extraction wells and discharged to the PLS process ponds.
Other pre-commissioning activities
Drying and packing area
The redundant vacuum dryers and supporting equipment have been removed and a new yellowcake
dewatering centrifuge, electrical kiln (calciner) and improved off gas system has been installed within the
existing building.
Precipitation Area
The precipitation area has been cleaned and flushed. The redundant batch precipitation tanks have been
converted to support a continuous operation to meet the new residence time requirements.
The uranium precipitation thickener underflow pump discharge piping is being reconfigured to enable
recycling of thickener underflow to the precipitation feed for seeding to promote crystal growth.
Regent systems
Boss has successfully completed and commissioned modifications to the Ferric sulphate and sodium
carbonate systems.
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
@Boss_Energy
Commissioned plant currently operating includes:
•
•
•
•
•
•
•
•
•
Safety showers
High-pressure air services
Reverse Osmosis (RO) Plant
Water Treatment Plant (WTP)
Start-up wellfield injection/ extraction wells
25,000 ton Gypsum repository
Potable water RO plant
Borefields
Acid injection system and storage
This ASX announcement was approved and authorised by the Board of Boss Energy Limited.
For further information, contact:
Duncan Craib
Chief Executive Officer
P: +61 (8) 6263 4494
E: boss@bossenergy.com
For media enquiries, contact:
Paul Armstrong
Read Corporate
P: +61 (8) 9388 1474
E: info@readcorporate.com
Forward-Looking Statements
This announcement includes forward-looking statements. These forward-looking statements are based
on the Company’s expectations and beliefs concerning future events. Forward-looking statements are
necessarily subject to risks, uncertainties and other factors, many of which are outside the control of Boss,
which could cause actual results to differ materially from such statements. Boss makes no undertaking to
subsequently update or revise the forward-looking statements made in this announcement, to reflect the
circumstances or events after the date of this announcement.