Quarterly Activities Report - December 2025
Released
Released
Announcement PDF
ASX Release 28 January 2026
FOR FURTHER INFORMATION PLEASE CONTACT:
Boss Energy Limited
ABN 38 116 834 336
Level 1, 420 Hay Street, Subiaco
Western Australia 600
Matthew Dusci - Managing Director/ CEO
+61 (08) 6263 4494
Paul Armstrong – Public Relations
+61 (08) 9388 1474
ASX: BOE OTCQX:
BQSSF
www.bossenergy.com
@Boss_Energy
Q2 December FY26 Quarterly Report
Production supports lower cost guidance
and growth in inventory and cash
Highlights
• Strong Honeymoon performance with record drummed production of 456 klbs U3O8 (up 18%) and
IX production of 406 klbs (up 8%), driven by higher flow from new wellfields. Remain on track for
FY26 production guidance of 1.6 Mlbs.
• Honeymoon C1 cost of $30/lb (US$20/lb) down $4/lb (12%) following positive results mainly from
reagent optimisation in the wellfields and plant.
• Honeymoon cost guidance adjusted lower with C1 cost guidance revised from $41-45/lb (US$27-
29/lb) to $36-40/lb (US$24-26/lb) and AISC revised from $64-70/lb (US$41-45) to $60-64/lb
(US$40-42/lb).
• Alta Mesa drummed production (on a 100% basis) of 143 klbs (down 31%). Boss received 68 klbs
(up 51%).
• Balance sheet remains strong with $208M of cash and liquid assets, including cash on hand of
$53M (up 11%) and 1.62 Mlbs of drummed inventory (up 12%).
• Average realised price of $112/lb (US$74/lb) supports Boss’ strategy to remain under-contracted.
• Brooks Dam North, Jason’s Deposit and Gould’s Dam permitting progressing.
• Honeymoon Review completed and path forward identified with New Feasibility Study initiated.
Changes to wellfield design could deliver lower costs, improved lixiviant grades, lower reagent
consumption and utilisation of wellfield infrastructure over a larger surface area with more
uranium under leach.
December Quarter Performance Q2 FY26 Q1 FY26 QoQ QoQ (%)
Honeymoon Drummed Production lbs U3O8 455,791 385,910 69,881 18%
Honeymoon AISC1
US$/lb 33 33 (1) (3%)
Alta Mesa Production (100%) lbs U3O8 142,699 206,231 (63,532) (31%)
Sales and loan repayments2
lbs U3O8 350,000 500,000 (150,000) (30%)
Realised Price2
US$/lb 74 75 (1) (1%)
Cash and liquid assets A$M 208 212 (5) (2%)
Notes: (1) AUD/USD Q1: 0.6602 Q2:0.6693 (2) Q1 includes loan repayments.
ASX: BOE OTCQX: BQSSF www.bossenergy.com Page 2
“This quarter was significant for Boss, following completion of the Honeymoon Review and initiation of
the New Feasibility Study. The pathway forward through a new wide-spaced wellfield design has the
potential to lower operating costs, optimise production profiles, and extend mine-life. The successful and
timely delivery of this study has the potential to deliver significant value and is a strategic priority.
“With regards to production, the team has delivered a record quarter of 455,791 lbs of U3O8 drummed at
a C1 cash cost of $30/lb. As a result of the continued work to optimise the operation, it is pleasing to
reconfirm production guidance of 1.6 Mlb for FY26 while revising down our C1 and AISC costs. We continue
to balance investment in the current wellfield design with delivering the New Feasibility Study as we
prioritise delivery of production whilst also minimising spend on wellfield designs that could be improved
under the wide-spaced wellfield design.
“During the quarter, we continued to build strength in our balance sheet, including increased cash and
accumulation of uranium inventory, which is now at 1.62 Mlbs. This ensures that Boss will continue to
benefit from a tightening uranium market.”
Matthew Dusci
Managing Director and Chief Executive Officer
ASX: BOE OTCQX: BQSSF www.bossenergy.com Page 3
Honeymoon Safety Performance
The Total Reportable Injury Frequency Rate (TRIFR1
) reduced slightly to 19.6 from 20.7 during the quarter
due to four recordable incidents, which included one Lost Time Incident (LTI) during the quarter. The
Health and Safety and operational teams continue to implement initiatives at Honeymoon to improve the
safety of team members.
Table 1: Honeymoon TRIFR (12-month moving average)
Quarter ended Q2 FY26 Q1 FY65
TRIFR 19.6 20.7
Honeymoon Production Results
Production continued to ramp up during the quarter, with a record 456 klbs U3O8 drummed and 406 klbs
IX produced. This represents a growth of 70 klbs (18%) in U3O8 drummed and 30 klbs (8%) in IX production
compared to the previous quarter. The production increase was reflective of a full quarter of production
from four wellfields as compared to the prior quarter which only included a partial quarter of production
from Wellfield B4.
The PLS to IX U3O8 tenor during the quarter was 77 mg/l compared to the prior quarter of 81 mg/l. Whilst
the decline in average tenor from existing wellfields online and no new wellfields coming online in the
quarter was expected, average tenors were elevated due to positive results from the lixiviant optimisation
program.
Table 2: Operational physicals
Quarter ended Unit Q2 FY26 Q1 FY26 YTD FY26
Wellfields online # 4 4 4
NIMCIX Columns online # 3 3 3
IX Flow (total)1
(m3
) 2,458,050 2,166,348 4,624,398
PLS to IX tenor2
(U3O8 mg/l) 77 81 79
IX Recovery (%) 97.5 97.8 97.6
IX Production (total)1
(lbs) 406,006 376,025 782,031
U3O8 Drummed (total) (lbs) 455,791 385,910 841,701
Notes: (1) Conversions: There are 1,000 litres per m3
and 0.00000220462 lbs per mg. (2) Tenors currently being
extracted exceed the average tenors forecast in the Enhanced Feasibility Study and should not be extrapolated across
the life of mine.
It is expected that drummed production in Q3 FY26 will be lower than Q2 FY26, mainly due to a decline in
average PLS to IX tenor and less opening inventory in circuit, partially offset by increased flow capacity
with column 4 commissioning in March 2026. It is expected that production will then increase again in Q4
FY26 as a full quarter of production from wellfield B5 is recorded and B6 comes online near the end of
FY26.
1 Total Reportable Injury Frequency Rate (TRIFR) measures the rate of restricted work injuries (RWIs), medical treated injuries
(MTI) and lost time injuries (LTIs) that occur per million hours worked.
ASX: BOE OTCQX: BQSSF www.bossenergy.com Page 4
Honeymoon Costs
Boss recorded a decline in C1 and All In Sustaining Cost during the period from $34/lb and $50/lb in Q1
FY26 to $30/lb (down 12%) and $49/lb (down 3%) respectively, in Q2 FY26.
Table 3: Production and Capital Costs
Key Metric Unit
Q2 FY26 Q1 FY26 YTD FY26
AUD USD AUD USD AUD USD
C1 Cash Cost $/lb 30 20 34 22 32 21
All In Sustaining Cost (AISC) $/lb 49 33 50 33 49 33
Capital expenditure
Sustaining $M 6 4 6 4 12 8
Project and Supporting Infrastructure $M 11 7 9 6 20 13
Total Capital Expenditure $M 17 11 15 10 32 22
Notes: (1) AUD/USD Q1: 0.6602 Q2:0.6693.
The decline in C1 cost was primarily driven by positive results from a series of reagent optimisation
programs in the wellfields, the precipitation circuit and the conversion liquor process and higher
production which fractionalised fixed costs.
Sustaining capital expenditure was consistent with the prior quarter and mainly represented costs
incurred in relation to wellfields B5-B7.
The Project and Supporting Infrastructure spend increased from $9M in Q1 FY26 to $11M in Q2 FY26.
Spend for the quarter was mainly driven by wellfield supporting infrastructure costs including the East
Kalkaroo trunkline and the ongoing delineation drilling program. Costs also continued to be incurred for
the ongoing completion of NIMCIX columns 4-6.
Guidance – Production and Cost
FY26 production guidance remains at 1.6 Mlbs of drummed U3O8 with C1 cost guidance adjusted lower by
$5/lb, and total capital expenditure adjusted higher by $4M.
Table 4: Guidance – Production and Cost
Key Metric (FY26) Unit Guidance (Updated) Guidance (Previous)
AUD USD1
AUD USD1
Production drummed lbs (000’s) 1,600 1,600 1,600 1,600
Cash Cost $/lb 36-40 24-26 41-45 27-29
All In Sustaining Cost $/lb 60-64 40-42 64-70 41-45
Capital expenditure
Sustaining $M 30-33 20-22 29-32 19-21
Project and Supporting Infra. $M 30-33 20-22 27-30 18-20
Total Capital Expenditure $M 60-66 40-44 56-62 36-40
Notes: (1) Previous guidance AUD/USD of 0.65, Updated guidance AUD/USD of 0.66
ASX: BOE OTCQX: BQSSF www.bossenergy.com Page 5
The key changes to guidance include:
• C1 Cost (Reduced from $41-45/lb to $36-40/lb): Cost savings as a result of continued positive
results from the reagent optimisation program in the wellfields and plant which has increased
tenors and reduced consumption, and other cost reduction programs and one-off savings.
• Sustaining Capital (Increased from $29-32M to $30-33M): Increased cost associated with the
New Feasibility Study for wide-spaced wellfield design trials across Honeymoon and East Kalkaroo
that will be partially offset by savings from later timing for previously planned wellfields. Whilst
Boss continues to build some wellfields based on the current wellfield design, it is slowing some
activity to minimise spend on infrastructure that may not be relevant to the new wide-spaced
wellfield design.
• Project and Supporting Infrastructure Capital (Increased from $27-30M to $30-33M): Increased
cost due to new costs associated with the delineation drilling program.
The Sustaining capital expenditure represents the cost to bring the total number of wellfields constructed
to nine wellfields (B1-B9), five at Honeymoon (B1-B5) and four at Far East Kalkaroo (B6-B9). Of these
wellfields, B1-B5 have already been constructed and B6 is expected to complete construction in Q4 FY26.
All of these wellfields (B1-B9) are based on the current wellfield design i.e. tighter spacing of around 40
metres.
Honeymoon Construction Activities
Construction activities for the completion of NIMCIX columns 4-6 continue:
• Column 4 is nearing full completion, and is expected to be fully commissioned in Q3 FY26.
• Column 5 had jointing, piping and instrumentation completed during the quarter and is expected
to be commissioned in Q3 FY26.
• Column 6 requirements are under review as a part of the New Feasibility Study.
Wellfield construction continued with Wellfield B5 expected to be brought online during Q3 FY26 and
Wellfield B6, along with the supporting East Kalkaroo infrastructure, is expected to be completed in Q4
FY26.
Exploration Activities
Overall, exploration activities are focused on the existing tenement area surrounding the Honeymoon
operation. During the quarter, key activities for Honeymoon’s existing tenements were:
• Boss reprocessed existing, and collected new, passive seismic data. The objective of this work was
to define the prospective palaeovalleys at mineable depths.
• Drilled two sonic core holes to obtain samples for metallurgical testwork.
Activities planned for the following quarter at Honeymoon are to:
• Collect further passive seismic data to complete the palaeovalley mapping exercise.
• Complete some low-cost aircore drilling along mapped palaeovalleys.
• Complete two diamond drillholes to obtain samples for nuclear magnetic resonance / porosity /
permeability characterisation.
ASX: BOE OTCQX: BQSSF www.bossenergy.com Page 6
Satellite Deposits
The early development of Gould’s Dam and Jason’s Deposit remains a key near-term opportunity for the
Company. An updated mineral resource statement and timetable of work required to bring these satellite
deposits into production are still expected to be provided in Q3 FY26.
If Boss can successfully implement a wide-spaced wellfield design, this could potentially significantly
improve the recoverable uranium metal and reduce capital intensity and C1 cost, at these satellite
deposits.
Balance Sheet
Boss finished the quarter in a strong financial position with no debt and $208M of liquid assets (being
cash, liquid investments and physical drummed uranium), a decrease of $4.4M from the September
quarter, primarily due to:
• Cash increased by $5.1M due to the sale of 350 klbs ($39.3M) and receipt of a 50 klbs trade
receivable ($5.1M), partially offset by Honeymoon operating and capital costs ($27.9M) and other
cash outflows ($11.4M). See the cashflow waterfall below for details.
• Listed investments decreased by $8.8M due to the decline in fair value of Boss’ listed equity
investments in enCore Energy Corp and Laramide Resources.
• Inventory on hand increased by $4.4M (175 klbs) as production exceeded sales, partially offset by
a reduction in the accounting weighted average cost of inventory from $74/lb (US$49/lb) to
$68/lb (US$46/lb).
• Trade receivables declined by $5.1M relating to a sale that was recorded in Q1 FY26 and cash
received on 1 October 2025.
Table 5: Cash, inventory and investments
Notes: (1) Inventory on hand reflects drummed U3O8.
A$000’s Q2 FY26 Q1 FY26 QoQ ($)
Cash on hand 52,857 47,767 5,090
Investments and other liquid assets 44,912 53,700 (8,788)
Inventory on hand1
110,236 105,839 4,397
Trade receivable - 5,112 (5,112)
Total cash and liquid assets 208,005 212,418 (4,413)
ASX: BOE OTCQX: BQSSF www.bossenergy.com Page 7
The waterfall chart below highlights the December quarter movements in cash.
Figure 1: December Q2 FY26 Cash (A$000’s)
Sales, Loans and Inventory
During the quarter, Boss recorded $39.3M (US$25.9M) of sales for 350 klbs at an average realised price
of $112.2/lb (US$74.0/lb).
Table 6: Sales, Loans and Inventory
Key Metric Unit Q2 FY26 Q1 FY26 YTD FY26
Sales and loan repayments1
US$000’s 25,886 37,329 63,215
Sales and loan repayments1
A$000’s 39,262 57,133 96,395
Sales lbs 350,000 400,000 750,000
Loan repayment lbs - 100,000 100,000
Average realised price2
US$/lb 74.0 74.7 74.4
Average realised price2
A$/lb 112.2 114.3 113.4
Inventory on hand3
lbs 000’s 1,615 1,440 1,615
Notes: (1) Q1 Sales and loan repayments include a sale recorded during the September quarter and cash received on
1 October (2) Q1 Average realised price includes inventory loan repaid
Boss expects that sales and cash receipts for the remainder of FY26 will remain mostly in line with
Honeymoon production for each quarter, subject to market prices reflecting fundamental long-term
value.
Guidance – Average Realised Price
In Q3 and Q4 of FY26, Boss will make its first deliveries (125 klbs in each quarter) into a legacy contract
that was entered into by one of the prior owners of Honeymoon’s mining license. The contract is for a
total of 1.7 Mlbs from CY26. It requires delivery of 20% of the previous calendar year’s production from
Honeymoon, up to a maximum quantity of 250 klbs during each delivery year. Whilst the details of the
pricing mechanism are commercially confidential, it will typically reflect an average realised price that is
circa 65-70% of the spot price at the time of delivery.
ASX: BOE OTCQX: BQSSF www.bossenergy.com Page 8
Honeymoon Review
The Honeymoon Review2
was concluded with an expected material and significant deviation from the
assumptions underpinning the Company’s 2021 Enhanced Feasibility Study (EFS). This in turn would be
expected to impact life of mine production and cost from FY27 onwards, primarily due to less continuity
of higher-grade mineralisation, mineralisation not overlapping, less leachability and smaller wellfields.
As a result, Boss formally withdrew the EFS and confirmed that it should no longer be relied upon as a
guide to future operational performance.
Through the Honeymoon Review, Boss has identified a potential pathway forward through an alternative
wide-space wellfield design (‘New Feasibility Study’) that, based on Boss’ updated understanding of the
resource and deposit characteristics, could be suitable to Honeymoon.
New Feasibility Study
A wide-spaced wellfield design could potentially deliver lower costs and improved lixiviant tenors
compared to the current wellfield design by increasing leaching time, lowering reagent use and utilising
wellfield infrastructure over a larger surface area and putting more uranium under leach. The potential
suitability of a wide-spaced wellfield design at Honeymoon remains at a concept stage.
Boss has initiated a series of accelerated work programs to assess the potential economic benefits of, and
to provide an update on work associated with, the wide-spaced wellfield design. The current primary work
programs include:
• Continued delineation drilling and resource modelling to develop an updated JORC resource and
to collect additional samples to improve geological and hydrological characterisation. Some
interim block models are also being developed to enable initial 3D simulations.
• 3D reactive transport simulations of wellfield performance based on various wellfield designs and
conditions.
• Geometallurgical testing and modelling to understand the potential impact of longer residence
time on reagent consumption.
• A review of wellfield, plant and supporting infrastructure designs or modifications required to
support a potential wide-spaced wellfield design.
• Consideration of heritage and regulatory requirements.
• Identification and design of tests and trial patterns to begin testing elements of the wide-spaced
wellfield design.
Completion of the Scoping Study is targeted for Q2 CY26 and completion of a New Feasibility Study is
expected in Q3 CY26. Boss will provide updates as work on the New Feasibility Study progresses.
Alta Mesa Joint Venture (Boss 30% / enCore Energy Corp 70%)
Drummed production during the quarter from the Alta Mesa Uranium Project, a Joint Venture with enCore
Energy Corp (NASDAQ: EU; TSXV: EU) (enCore), totalled 142,699 lbs of U3O8 compared to the previous
quarter's drummed production of 206,231 lbs of U3O8 (on a 100% basis), a decrease of 63,532 lbs. Boss
received 68,420 lbs of U3O8 reflecting its 30% pro rata share of shipped production, a 23,318 lbs increase
from the prior quarter of 45,102 lbs of U3O8. Recent Alta Mesa Project operational highlights include:
2 See the Company’s announcements dated 28 July 2025 (“Honeymoon FY26 Guidance” and “June 2025 Quarterly Results
Presentation”), 5 August 2025 (“Response to ASX Aware Query”), 11 September 2025 (“Honeymoon Review Update”), 29 October
2025 (“September Quarterly Report”), 20 November 2025 (“Chair’s Address and Managing Director’s Presentation to AGM”) and
18 December 2025 (“Honeymoon Update”) for further details.
ASX: BOE OTCQX: BQSSF www.bossenergy.com Page 9
• Wellfield 7 currently operating with earmarked additional modules expected to come online in
Q1 CY26, with continued drilling and module development planned to continue throughout CY26.
• Wellfield 3 extension is currently under development with wells being installed and ongoing
design in progress.
• Alta Mesa East (shown below as ‘Tacubaya Project Lease’) commenced drilling during the quarter
to confirm the potential of extensions of uranium mineralisation from Alta Mesa into Alta Mesa
East.
Figure 2: Alta Mesa Wellfield Boundaries
Corporate
Non-Executive Chair Mr Wyatt Buck informed the Board of his intention to step down as Chair.
Upon appointment of a new Chair, Mr Buck will continue to serve on the Board as a Non-Executive
Director. This will ensure a smooth and orderly transition, maintain continuity, and enable the Company
to continue benefiting from his extensive uranium, operational and technical experience.
Boss has commenced the recruitment process for a new Non-Executive Chair and expects to finalise this
appointment during the first half of CY26.
ASX: BOE OTCQX: BQSSF www.bossenergy.com Page 10
December FY26 Quarterly Results Conference Call – 28 January 2026
Boss will hold a conference call today, Wednesday 28 January 2026, at 9am AWST (12pm AEDT) with
Managing Director Matt Dusci and Chief Financial Officer Justin Laird, to discuss the results. To listen in
live, please click on the link below and register your details.
https://loghic.eventsair.com/693362/136951/Site/Register
Appendix 5B disclosures
In line with its obligations under ASX Listing Rule 5.3.5, Boss notes that the only payments to related
parties of the Company, as disclosed in the Appendix 5B (Quarterly Cashflow Report) for the period ended
31 December 2025, consist of executive director and chief financial officer salaries and wages (including
superannuation) and payment of non-executive director fees.
During the quarter ended 31 December 2025, the Company spent approximately $13.3M on project and
exploration activities relating to its Honeymoon and Alta Mesa Projects. These activities included:
• Technical studies costs
• Construction equipment
• Wellfield drilling and development costs
• Engineering and construction expenses
• Mineral exploration and evaluation costs
In addition to these activities the Company continued to incur costs relating to the ongoing maintenance
activities required at Honeymoon. The expenditure represents direct costs associated with these activities
as well as capitalised wages which can be directly attributable to Honeymoon.
This ASX announcement was approved and authorised by the Board of Boss Energy Limited.
For further information, contact:
Matt Dusci
Chief Executive Officer
P: +61 (8) 6263 4494
E: boss@bossenergy.com
For media enquiries, contact:
Paul Armstrong
Read Corporate
P: +61 (8) 9388 1474
E: info@readcorporate.com
Forward-Looking Statements
This announcement contains certain forward-looking statements provided by or on behalf of Boss with
respect to potential future matters. Forward-looking information may include, without limitation,
statements regarding plans, strategies and objectives of Boss, production and financial guidance, financial
forecasts, estimates of project milestones and timing and expected costs or production outputs. In some
cases, forward-looking information can be identified by terms such as “may”, “will”, “should”, “expect”,
“plan”, “anticipate”, “believe”, “intend”, “estimate”, “predict”, “potential”, “continue” or other similar
expressions concerning matters that are not historical facts. Guidance as to production, unit costs and
capital expenditure is based on assumptions, budgets and estimates existing at the time of assessment
which may change over time impacting the accuracy of those estimates. These estimates are developed
in the context of an uncertain operating environment including in respect of inflationary macroeconomic
conditions, and uncertainties surrounding the risks associated with mining and the further review of the
EFS which may impact production and have a flow on effect on sales. Actual results may therefore vary
significantly depending on these risks and the timing required to address them. All information is provided
as an indicative guide to assist sophisticated investors with modelling of the Company. It should not be
relied upon as a predictor of future performance.
ASX: BOE OTCQX: BQSSF www.bossenergy.com Page 11
Forward-looking statements reflect Boss’s expectations at the date of this announcement, however they
are not guarantees or predictions of future performance or statements of fact. Forward-looking
information involves known and unknown risks, uncertainties and other factors (many of which are
beyond the control of Boss and its directors and management) which may cause the actual results,
performance or achievements of Boss and its business to be materially different from any future results,
performance or achievements expressed or implied by the forward-looking information. Accordingly,
undue reliance should not be placed on forward-looking information.
The forward-looking statements in this announcement reflect various assumptions by or on behalf of Boss
(which assumptions may prove to be inaccurate). Accordingly, this is another reason why such statements
are subject to significant business, technical, legal, economic and competitive and other uncertainties and
contingencies and other factors which may be beyond the control of Boss which could cause actual results
or trends to differ materially from the forward-looking statements in this announcement, including but
not limited to differences or inaccuracies arising from price and currency fluctuations, geotechnical
factors, geological and mining factors, estimated continuity of mineralised horizons, metallurgical and
processing factors, sales factors, drilling and production results, development progress, operating results,
mineral resource estimates, legal issues, legislative, fiscal and regulatory developments, economic and
financial market conditions in various countries, approvals and cost estimates, environmental risks, ability
to meet funding requirements, share price volatility, uranium markets and other matters. Accordingly,
there can be no assurance that such forward-looking statements and projections will be realised.
Boss makes no representations as to the accuracy or completeness of any forward-looking statements or
projections or that any forecasts will be achieved. Additionally Boss makes no representation or warranty,
express or implied, in relation to, and (to the maximum extent permitted by law) no responsibility or
liability (whether for negligence, under statute or otherwise) is or will be accepted by Boss or by any of its
officers, directors, shareholders, partners, employees, or advisers as to or in relation to the accuracy or
completeness of the information, statements, opinions or matters (express or implied) arising out of,
contained in or derived from this announcement or any omission from this announcement.
Boss does not undertake or accept any obligation or undertaking to release publicly any updates or
revisions to any forward-looking statements to reflect any change in Boss’s expectations or any change in
events, conditions or circumstances on which any such statement is based, except as required by law.
Mineral Resource estimates are necessarily imprecise and depend on interpretations and geological
assumptions, minerals prices, cost assumptions and statistical inferences (and assumptions concerning
other factors, including mining, processing, metallurgical, infrastructure, economic, marketing, legal,
environmental, social and governmental factors) which may ultimately prove to be incorrect or unreliable.
Mineral Resource estimates are regularly revised based on actual exploration or production experience
or new information and could therefore be subject to change. In addition, there are risks associated with
such estimates, including (among other risks) that minerals mined may be of a different grade or tonnage
from those in the estimates and the ability to economically extract and process the minerals may become
compromised or not eventuate. Accordingly, this is another reason why no assurances can be given of
whether the production guidance, financial forecasts or other forecasts or other forward-looking
statements or information in this announcement will be achieved.
Effect of Rounding
A number of figures, amounts, percentages and estimates in this announcement are subject to the effect
of rounding. Accordingly, the actual calculation of these figures may differ from the figures set out in this
announcement.
Past Performance
Past performance information, including past share price performance of Boss and past Honeymoon
Project information, given in this announcement is given for illustrative purposes only and should not be
ASX: BOE OTCQX: BQSSF www.bossenergy.com Page 12
relied upon as (and is not) an indication of Boss’s (or anyone else’s) views on Boss’s future activities,
guidance or financial performance or condition. Past performance of Boss cannot be relied upon as an
indicator of (and provides no guidance as to) the future performance of Boss.
ASX: BOE OTCQX: BQSSF www.bossenergy.com Page 13
Appendix One:
Schedule of Mining Tenements
The following information is provided pursuant to Listing Rule 5.3.3 for the quarter ended 31 December 2025.
Tenement Name Location Licence Number Interest
Yarramba South Australia EL6510 100%
South Eagle South Australia EL6081 100%
Gould’s Dam South Australia EL6512 100%
Katchiwilleroo South Australia EL6511 100%
Ethiudna South Australia EL6020 100%
Gould’s Dam South Australia RL83-85 100%
Honeymoon Mine South Australia ML6109 100%
Prairie Dam South Australia EL6962 75%
Chalker Dam South Australia EL6963 75%
Oakvale South Australia EL6964 75%
Gairloch South Australia EL6965 75%
Venus Bay South Australia EL6992 100%
Darke Peak South Australia EL7013 100%
Rudall South Australia EL6999 100%
There were no mining tenement acquisitions or divestments during the quarter.
ASX: BOE OTCQX: BQSSF www.bossenergy.com Page 14
Appendix Two:
Quarterly results table
Key Metric Unit Q2 FY26 Q1 FY26 Q4 FY25 Q3FY25
Production
Wellfields online # 4 4 3 3
NIMCIX Columns online # 3 3 3 3
IX Flow (total) (m3
) 2,458,050 2,166,348 2,102,310 1,088,704
PLS to IX tenor (U3O8 mg/l) 77 81 88 108
IX Recovery (%) 97.5 97.8 96.9 95.5
IX Production (total) (lbs) 406,006 376,025 396,346 246,869
U3O8 Drummed (total) (lbs) 455,791 385,910 349,188 295,819
Honeymoon TRIFR
TRIFR 19.6 20.7 12.8 9.9
Sales
Sales and loan repayments US$000’s 25,886 37,329 7,115 22,389
Sales and loan repayments A$000’s 39,262 57,133 10,863 35,675
Sales lbs 350,000 400,000 100,000 150,000
Loan repayment lbs - 100,000 - 118,000
Average realised price US$/lb 74.0 74.7 71.2 83.5
Average realised price A$/lb 112.2 114.3 108.6 133.0
Inventory (Drummed U3O8)
Opening lbs 000’s 1,440 1,409 1,216 1,141
Honeymoon production lbs 000’s 456 386 349 296
Alta Mesa receipts lbs 000’s 68 45 44 29
Sales lbs 000’s (350) (400) (100) (150)
Loan repayments lbs 000’s 0 0 (100) (100)
Closing lbs 000’s 1,615 1,440 1,409 1,216
Costs
C1 A$/lb 30 34 36 33
AISC A$/lb 49 50 n/a n/a
Capex – Wellfields A$M’s n/a n/a 7 8
Capex – Capital Projects A$M’s n/a n/a 7 4
Sustaining Capital A$M’s 6 6 n/a n/a
Wellfields and Supporting Infra. A$M’s 11 9 n/a n/a
Total Capex A$M’s 17 15 14 12
ASX: BOE OTCQX: BQSSF www.bossenergy.com Page 15
Key Metric Unit Q2 FY26 Q1 FY26 Q4 FY25 Q3FY25
Cash and liquid investments
Cash on hand A$000’s 52,857 47,767 36,531 63,773
Investments & other liquid
assets
A$000’s
44,912 53,700 51,637 42,386
Inven