March 2026 Quarterly Report
Honeymoon Infrastructure Ramp-Up
Progresses
Operational focus remains on infrastructure delivery, wellfield development and ramp-up
execution; Wide-spaced wellfield design work continues as optimal pathway forward
Highlights
• Honeymoon Q3 FY26 production of 203 klbs U3O8 drummed; C1 cost of $60/lb (US$41/lb) reflects
adverse weather conditions and expected declines in tenor.
• Production for the nine months to March 31 was 1,044 klbs U3O8 drummed; C1 costs were $37/lb
(US$25/lb) and All-In Sustaining Costs (AISC) were $58/lb (US$39/lb).
• FY26 production guidance reduced to between 1.40 Mlbs and 1.45 Mlbs U3O8 drummed, from
previous guidance of 1.6 Mlbs U3O8 drummed, primarily due to adverse weather conditions.
• FY26 C1 cost guidance of $36-40/lb (US$24-26/lb) and AISC guidance of $60-64/lb (US$40-42/lb)
reconfirmed towards the upper end of the guidance range.
• Alta Mesa drummed production of 97 klbs (on a 100% basis) due to timing of permitting in Texas
for administrative reasons, resulting in delays of new wellfields coming online.
• Balance sheet remains strong with $211 million of cash and liquid assets, including cash on hand
of $38 million which was lower due to timing of receipts.
• Average realised sale price of $106/lb (US$74/lb). Boss remains strategically under-contracted
and has inventory on hand of 1.53 Mlbs U3O8 drummed.
• Work on the wide-spaced wellfields design continues to confirm it as the optimal pathway
forward. Completion of the New Feasibility Study targeted for the September quarter 2026.
• Work ongoing for a new Honeymoon JORC resource to support the New Feasibility Study,
including drilling and reinterpretation and remodelling of historic grade and permeability data.
• Mineral Resource Estimate (MRE) update provided for Gould’s Dam with a total of 38.7 Mt @
388ppm U3O8 for 33.1 Mlbs of contained U3O8 and Jason’s Deposit with a total MRE of 13.3 Mt @
410ppm U3O8 for 12.0 Mlbs contained U3O8.1
• The development pathway for both Gould’s Dam and Jason’s Deposit has been accelerated over
the past six months. Timing, from initial applications to the granting of a mining lease and Program
for Environment Protection and Rehabilitation (PEPR) approval, is expected to take up to 24 to 36
months.
1
Refer to ASX announcement dated 19 March 2026 titled “Gould’s Dam and Jason’s Deposit Mineral Resource and Permitting Update” for detail.
The company confirms that it is not aware of any new information or data that materially affects the information included in the original market
announcement and that all material assumptions and technical parameters underpinning the Mineral Resource Estimates in the original market
announcement continue to apply and have not materially changed. The company confirms that the form and context in which the Competent
Person’s finding are presented have not been materially modified from the original market announcement.
ASX: BOE OTCQX: BQSSF www.bossenergy.com Page 2
March Quarter Performance Q3 FY26 Q2 FY26 QoQ QoQ (%)
Honeymoon Drummed Production lbs U3O8 202,781 455,791 (253,010) (56%)
Honeymoon C1 Cost1
US$/lb 41 20 21 103%
Honeymoon AISC1
US$/lb 64 33 31 94%
Alta Mesa Production (100%) lbs U3O8 97,022 142,699 (45,677) (32%)
Sales lbs U3O8 325,000 350,000 (25,000) (7%)
Realised Price1
US$/lb 74 74 (0) (1%)
Cash and liquid assets A$m 211 208 3 2%
Notes: (1) AUD/USD Q3: 0.6845 Q2:0.6693
Boss CEO and Managing Director, Matthew Dusci, said:
“Operationally, this was a difficult quarter for the business. Production at Honeymoon of 203 klbs U3O8
was below our expectations. As a result, we have revised our FY26 production guidance to 1.40 Mlbs to
1.45 Mlbs U3O8.
“The primary driver was the impact of heavy and repeated rainfall events during March, which restricted
access to site and limited the delivery of key reagents required to maintain stable leaching conditions. This
was compounded by the knock-on effect of delays in commissioning critical infrastructure.
“Costs increased during the quarter, mainly reflecting lower uranium production. We remain on track to
meet full-year cost guidance, albeit towards the upper end of the guidance range.
“We are restoring stable operating conditions and completing the commissioning of additional capacity to
support the delivery of between 356 klbs and 406 klbs in Q4 FY26. The commissioning of Column 4 in April
has been an important step in de-risking this production outlook.
“During the quarter, we also made strong progress on the New Feasibility Study. This included
advancement of a new Honeymoon Mineral Resource Estimate and the calibration of our reactive
transport simulation model. Operating in a data-rich environment allows us to build and rely upon
increasingly sophisticated models. We also progressed with the development of wide-spaced wellfields
trials at Honeymoon and East Kallaroo.
“We continue to make meaningful progress in de-risking the pathway forward for Honeymoon and a
stronger quarter ahead for the company.”
ASX: BOE OTCQX: BQSSF www.bossenergy.com Page 3
Honeymoon Safety Performance
The Total Reportable Injury Frequency Rate (TRIFR2
) declined during the quarter to 16.6, which included
three Lost Time Injuries (LTI) during the quarter. The Health and Safety and operational teams continue
to implement initiatives at Honeymoon to improve the safety of team members.
Table 1: Honeymoon TRIFR (12-month moving average)
Quarter ended Q3 FY26 Q2 FY26
TRIFR 16.6 19.6
Honeymoon Production Results
Production for Q3 FY26 was 203 klbs U3O8 drummed (down 56%), which reflects the impact of expected
lower tenors and heavy rain which impacted production by restricting site access and limiting the delivery
of reagents and other goods required for production and plant infrastructure ramp-up.3
For Q4 FY26, Boss
expects production of between 356k lbs and 406 klbs U3O8 drummed to achieve the revised full year
guidance of between 1.40 Mlbs and 1.45 Mlbs U3O8 drummed.
The PLS to IX U3O8 tenor during the quarter was 53 mg/l compared to the prior quarter of 77 mg/l. It is
likely that average tenors in Q4 FY26 will be slightly lower than in Q3 FY26 as tenors on existing wellfields
decline.
Table 2: Operational physicals
Quarter ended Unit Q3 FY26 Q2 FY26 YTD FY26
Wellfields online # 5 4 5
NIMCIX Columns online # 3 3 3
IX Flow (total) (m3
) 1,939,494 2,458,050 6,563,891
PLS to IX tenor (U3O8 mg/l) 53 77 71
IX Recovery (%) 97.8% 97.5% 97.7%
IX Production (total)1
(lbs) 220,952 406,006 1,002,983
U3O8 Drummed (total) (lbs) 202,781 455,791 1,044,482
2 Total Reportable Injury Frequency Rate (TRIFR) measures the rate of restricted work injuries (RWIs), medical treated injuries (MTI) and lost
time injuries (LTIs) that occur per million hours worked.
3 For further details see the Company’s announcements dated 5 March 2026, titled “Rain impacts Honeymoon production”, 23 March 2026,
titled “Boss Energy Investor Presentation” and 15 April 2026, titled “Honeymoon Update FY26 Production.”
ASX: BOE OTCQX: BQSSF www.bossenergy.com Page 4
Honeymoon Costs
Boss recorded an increase in C1 and All In Sustaining Cost during the period from $30/lb and $49/lb in
Q2 FY26 to $60/lb (up 99%) and $93/lb (up 90%) respectively, in Q3 FY26. This was primarily due to a
decline in drummed production for the quarter which resulted in a lower fractionalisation of fixed costs.
Boss has confirmed that it remains on track to deliver towards the upper end of FY26 C1 cost guidance
of $36-40/lb and All In Sustaining Cost guidance of $60-64/lb. These were previously lowered from $41-
45/lb and $64-70/lb, respectively.4
Table 3: Production and Capital Costs
Key Metric Unit
Q3 FY26 Q2 FY26 YTD FY26
AUD USD AUD USD AUD USD
C1 Cash Cost $/lb 60 41 30 20 37 25
All In Sustaining Cost (AISC) $/lb 93 64 49 33 58 39
Capital expenditure
Sustaining $m 5 3 6 4 17 11
Project and Supporting Infrastructure $m 8 5 11 7 28 19
Total Capital Expenditure $m 13 9 17 11 45 30
Notes: (1) AUD/USD Q3: 0.6845 Q2:0.6693.
Sustaining capital spend for the quarter primarily reflected wellfield construction costs at wellfields B6,
EKT1 and B8. Project and supporting infrastructure mainly reflected the ongoing works for NIMCIX
columns 4 and 5, the East Kalkaroo trunkline and the accelerated delineation drilling program.
The reduction in capital spend as compared to the prior quarter reflects a disruption to site access in
March due to adverse weather conditions.
Impact of global oil market disruption
Boss has not yet experienced any fuel availability disruption to operations at Honeymoon. Boss’ primary
reliance is an indirect reliance upon diesel for reagent transport providers and jet fuel for air charter
providers. Boss’ direct consumption of diesel is limited to diesel used for drill rigs performing delineation
and production well drilling. The plant and wellfields are all connected to the main electricity grid.
Boss has not experienced any disruption in the procurement, nor any increase in cost, of its sulphuric
acid. Sulphuric acid is a key reagent used in the leaching process, and is currently sourced from Nyrstar’s
multi-metal smelter in Port Pirie, South Australia.
The overall potential cost impact has been considered when Boss reconfirmed its FY26 cost guidance at
the upper end of the guided range.
4 See the Company’s announcement dated 28 January 2026, titled “Production supports lower cost guidance and growth in inventory and cash”
for further details.
ASX: BOE OTCQX: BQSSF www.bossenergy.com Page 5
Balance Sheet
Boss finished the quarter in a strong financial position with no debt and $211.3 million of liquid assets
(being cash, liquid investments, trade receivables and physical drummed uranium), an increase of $3.3
million from the December quarter, primarily due to:
• Cash declined by $14.8 million with cash receipts from customers of $23.2 million ($11.1 million
of $34.4 million in Q3 FY26 sales were received in April 2026), offset by Honeymoon operating
and capital costs ($33.6 million) and other cash outflows ($4.4 million). See the cashflow waterfall
below for details.
• Investments increased by $4.0 million due to mark to market gains in Boss’ listed equity
investments.
• Inventory on hand increased by $3.0 million reflecting an increase in the weighted average cost
of Alta Mesa inventory, partially offset by a reduction in inventory on hand from 1.61 Mlbs to 1.53
Mlbs U3O8 drummed.
• The trade receivable reflects a sale recorded at the end of Q3 FY26 with cash received in Q4 FY26.
Table 4: Cash, inventory and investments
Notes: (1) Inventory on hand reflects drummed U3O8.
The waterfall chart below highlights the March quarter movements in cash. Excluding the impact of timing
of sales receipts ($11.1 million) and the completion of the NIMCIX columns ($4.1 million), which will wind
down at the end of Q4 FY26, cashflow would have been approximately flat quarter on quarter.
Figure 1: March Q3 FY26 Cash (A$000’s)
A$000’s Q3 FY26 Q2 FY26 QoQ ($)
Cash on hand 38,024 52,857 (14,833)
Investments and other liquid assets 48,876 44,912 3,964
Inventory on hand1
113,280 110,236 3,044
Trade receivable 11,111 - 11,111
Total cash and liquid assets 211,291 208,005 3,286
ASX: BOE OTCQX: BQSSF www.bossenergy.com Page 6
Sales, Loans and Inventory
During the quarter, Boss recorded $34.4 million (US$23.9 million) of sales for 325 klbs at an average
realised price of $106.0/lb (US$73.6/lb).
Boss recorded the first delivery of 125 klbs into a legacy contract with an additional 125 klbs delivered at
the beginning of Q4 FY26. No further legacy contract deliveries will occur in H1 FY27.
Table 5: Sales, Loans and Inventory
Key Metric Unit Q3 FY26 Q2 FY26 YTD FY26
Sales and loan repayments US$000’s 23,906 25,886 87,121
Sales and loan repayments A$000’s 34,447 39,876 131,746
Sales lbs 325,000 350,000 1,075,000
Loan repayment lbs - - 100,000
Average realised price US$/lb 73.6 74.0 74.1
Average realised price A$/lb 106.0 113.9 112.1
Inventory on hand lbs 000’s 1,530 1,615 1,530
Boss expects that sales and cash receipts will continue to remain mostly in line with Honeymoon
production for each quarter, subject to market prices reflecting fundamental long-term value.
Honeymoon Construction Activities
NIMCIX column 4 has now been commissioned and is operational but commissioning issues with
associated primary pumps are currently ongoing. NIMCIX column 5 is expected to be completed by the
end of Q4 FY26. NIMCIX column 6 is currently under review as a part of the New Feasibility Study.
Wellfield construction continued with Wellfield B5 commencing production in April and Wellfield B6
expected to commence production at the end of Q4 FY26.
During the Quarter, Boss experienced delays in commissioning certain infrastructure which was
compounded by the heavy rainfall restricting site access during March 2026.
Exploration Activities
Planned exploration activity in the quarter involved collection of passive seismic data in the Honeymoon
project exploration tenements to infill gaps left by previous surveys. The objective of passive seismic
surveying is to map prospective palaeovalleys at depths of approximately 100 m below the current land
surface. The contractors have yet to commence this work as heavy rain in March delayed access to the
survey area. Aircore drill-testing of palaeovalleys identified by this work, originally scheduled for Q4 FY26,
is therefore likely to be delayed to the following quarter.
Additional work included the completion of two triple-tube core holes at East Kalkaroo. This was to
provide samples for mineralogical studies, determination of radiometric disequilibrium and measurement
of porosity and permeability.
ASX: BOE OTCQX: BQSSF www.bossenergy.com Page 7
Growth Activities
An updated Mineral Resource Estimate (MRE) was released for Gould’s Dam and Jason’s Deposit. The
wide-spaced wellfield extraction approach being studied for Honeymoon is likely to be applicable to
Gould’s Dam and Jason’s Deposit, which could potentially lead to a higher conversion of the total Mineral
Resource into a mine plan, if successful.
Gould’s Dam total MRE is 38.7 Mt @ 388 ppm U3O8 for 33.1 Mlbs of contained U3O8 metal (23% Indicated;
77% Inferred Mineral Resource Classification). The total contained uranium has increased by 8.1 Mlbs
U3O8 (30%) and average grade has declined by 122 ppm U3O8 (24%) from the previous resource estimate
(2016).5
Jason’s Deposit total MRE is 13.3 Mt @ 410 ppm U3O8 for 12.0 Mlbs of uranium (41% Indicated; 59%
Inferred Mineral Resource Classification). Total contained uranium increased by 1.3 Mlbs U3O8 (9%) and
average grade has declined by 380 ppm U3O8 (48%) from the previous resource estimate (2017).6
Resource extension and delineation drilling is scheduled to commence at Gould’s Dam during Q1 FY27.
The development pathway for both Gould’s Dam and Jason’s Deposit accelerated over the past six months
with all baseline and technical studies for permitting applications being advanced. State and Federal
approvals processes are targeted to commence in the second-half CY26.
Timing from initial applications to the granting of a mining lease is expected to take up to 18 to 24 months;
subsequently, a further six to 12 months will be required for the Program for Environment Protection and
Rehabilitation (PEPR) approval process.
New Feasibility Study: Wide-Spaced Wellfield Design
Boss continues to observe the key characteristics of the Honeymoon deposit that support a wide-spaced
wellfield design. This has the potential to deliver a substantial reduction in the Honeymoon cost structure
which is required to economically extract low-grade resource. Whilst further work is required, this
reinforces the wide-spaced wellfield design as the optimal pathway forward for Boss, as compared to the
current wellfield design.7
Specifically, work to date indicates that the deposit demonstrates:
• Uranium metal with good continuity at lower grades.
• Strong permeability & hydraulic connectivity, supporting effective flow rates and lixiviant
interactions.
• Relatively low acid consumption, reflecting low carbonate content and low acid-consuming clays.
• Favourable plume and groundwater behaviour, reducing excessive dilution of reagents.
Boss has also completed the development and calibration of a reactive transport simulation model (RTM)
to simulate and optimise wellfield design. The model is a computational technique that simulates the
movement of fluids and transport of dissolved chemical species through porous substrate while
simultaneously accounting for geochemical reactions. This represents a leading approach to ISR
development.
5
Refer to ASX announcement dated 19 March 2026 titled “Gould’s Dam and Jason’s Deposit Mineral Resource and Permitting Update” and Footnote
1 of this announcement for detail.
6
As above.
7
Refer to ASX announcement dated 18 December 2025 titled “Honeymoon Update - Amended” and the Company’s announcement dated 23 March
2026, titled “Boss Energy Investor Presentation”.
ASX: BOE OTCQX: BQSSF www.bossenergy.com Page 8
Wellfield screens and streamlines (Honeymoon) using the RTM
Figure 2: Image from the RTM mapping fluid flow pathways between injection and extraction wells as streamlines.
The simulation model developed has been based on production data since operations at Honeymoon
commenced (i.e. from Uranium One and Boss Energy). The model has now been history-matched to actual
production data, which provides Boss confidence in the simulation model.
The development of this model represents a significant step up in Boss’ ISR technical capability to plan
and optimise wellfield designs. It provides detailed uranium leaching and reagent consumption data,
which will provide Boss a greater level of detail and understanding for future wellfield planning and
production profiles. The output of this modelling will serve as the basis for the New Feasibility Study.
The development of wide-spaced trial patterns has also commenced at Honeymoon and East Kalkaroo.
East Kalkaroo Domain: Previous wellfield design East Kalkaroo Domain: Current trial design
Figure 3: East Kalkaroo showing previous wellfield design (left) and the current trial wellfield design (right). Note:
Each ‘square’ outline in the above figures represents a ‘pattern’ which consists of four injection wells on each corner
of the square and an extraction in the centre (five-spot pattern). The previous pattern size B6, B7 and B9 was 42m x
42m (30m injection to extraction well). The current trial design of EKT1 has a pattern size of 85m x 85m (60m injection
to extraction well).
For East Kalkaroo, Wellfield B6 has been kept consistent with the current wellfield design so that Boss can
get a like-for-like comparison of production data to the Honeymoon domain before trialling a new
wellfield design at East Kalkaroo. The current trial design, as shown in the figure, demonstrates the greater
surface area covered by a wide-spaced wellfield design, which brings lower-grade mineralisation into the
production profile and lowers the cost structure. The re-design has also enabled Boss to combine B7 and
B9 into a single wellfield (“EKT1”).
ASX: BOE OTCQX: BQSSF www.bossenergy.com Page 9
Boss has also commenced establishing wide-spaced wellfield designs at the Honeymoon domain as a trial,
along with some additional extension patterns.
Honeymoon Domain: Wellfield Designs
Figure 4: Wellfield design on the Honeymoon Domain showing both the trial (HMT1 & HMT2) and extension patterns
(HME1). The current wellfield design of B1-B5 has a pattern size of 56m x 56m (40m injection to extraction well), the
trial design of HMT1 has a pattern size of 100m x 100m (71m injection to extraction well) and HMT2 has a pattern
size of 90m x 90m (55m from injection to extraction well), albeit an irregular shape. HME1 consists of two additional
extraction wells, which are 40m away from the existing injection wells.
The rationale supporting each trial and extension pattern is set out below:
• HMT1 is an example of a large low-grade area that has not been contacted by any current
wellfields. It is expected to take 2-3 months to bring online due to flushing constraints. Potential
solutions to accelerate the flushing time are being investigated.
• HMT2 is also a low-grade area, but given its proximity to existing wellfields, it is unlikely to require
much flushing and can be brought into production faster.
• HME1 is a small extension pattern that helps to capture learnings on fluid movements. Boss would
have likely added this pattern regardless of the New Feasibility Study.
ASX: BOE OTCQX: BQSSF www.bossenergy.com Page 10
New Feasibility Study: JORC Resource
An updated JORC resource for Honeymoon is also being developed to provide input into the New
Feasibility Study. Recall Boss previously advised that it had observed less continuity of higher-grade
mineralisation, mineralisation not overlapping, less leachability and smaller wellfields which would impact
life of mine production and cost from FY27 onwards.8
Based on the expected material and significant
deviation from the assumptions underpinning the Company’s 2021 Enhanced Feasibility Study (EFS) Boss
formally withdrew the EFS and confirmed that it should no longer be relied upon as a guide to future
operational performance.8
A new JORC resource for Honeymoon is required to support the New Feasibility Study through
incorporation of:
• An accelerated delineation drilling program. This program has experienced some delays, mainly
due to weather disruptions.
• A reinterpretation and remodelling of historic drilling data.
• An estimate of permeability, to provide a 3D interpretation which enhances recoverability
estimates in the RTM.
Additional programs of work to support the New Feasibility Study also include:
• Consideration of heritage and regulatory requirements.
• Geometallurgical testing and modelling.
• A review of wellfield, plant and supporting infrastructure designs or modifications required.
Overall, whilst there is a substantial amount of complex work being undertaken, in a relatively short
timeframe, completion of the New Feasibility Study is targeted for September quarter 2026.
Alta Mesa Joint Venture (Boss 30% / enCore Energy Corp 70%)
Drummed production during the quarter from the Alta Mesa Uranium Project, a Joint Venture with enCore
Energy Corp (NASDAQ: EU; TSXV: EU) (enCore), totalled 97 klbs of U3O8 compared to the previous
quarter's drummed production of 143 klbs of U3O8 (on a 100% basis), a decrease of 46 klbs. Boss received
35 klbs of U3O8 reflecting its 30% pro rata share of shipped production, a 33 klbs decrease from the prior
quarter of 68 klbs of U3O8. Recent Alta Mesa Project operational highlights include:
• Wellfield 7 currently operating with additional modules coming online in the quarter and
continued drilling and module development planned to continue throughout CY26.
• Wellfield 3 extension development has continued with further wells being installed and ongoing
design in progress.
• Alta Mesa East continues to be a focus with additional drilling rigs working on this property along
with acceleration of permitting constraints.
• Following Management changes, enCore’s Board noted it is committed to more fulsome
shareholder communications encompassing disclosure of technical information, project
developments and strategic objectives.9
8
Refer to ASX announcement dated 18 December 2025 titled “Honeymoon Update - Amended”.
8
As above.
9
Refer to enCore Energy news announcement dated 20 April 2026 titled “enCore energy appoints Richard Little as Chief Executive Officer; William
M. Sheriff returns as Executive Chair.
ASX: BOE OTCQX: BQSSF www.bossenergy.com Page 11
Corporate
Boss is continuing with the recruitment process for a new Non-Executive Chair and expects to finalise this
appointment, in line with expected timing, by the end of Q4 FY26.
March FY26 Quarterly Results Conference Call – 30 April 2026
Boss will hold a conference call today, Thursday, 30 April 2026, at 7am AWST (9am AEST) with Managing
Director Matt Dusci and Chief Financial Officer Justin Laird, to discuss the results. To listen in live, please
click on the link below and register your details.
https://loghic.eventsair.com/651132/635115/Site/Register
Appendix 5B disclosures
In line with its obligations under ASX Listing Rule 5.3.5, Boss notes that the only payments to related
parties of the Company, as disclosed in the Appendix 5B (Quarterly Cashflow Report) for the quarter
ended 31 March 2026, consist of executive director and chief financial officer salaries and wages (including
superannuation) and payment of non-executive director fees.
During the quarter ended 31 March 2026, the Company spent approximately $15.8 million on project and
exploration activities relating to its Honeymoon and Alta Mesa Projects. These activities included:
• Technical studies costs
• Construction equipment
• Wellfield drilling and development costs
• Engineering and construction expenses
• Mineral exploration and evaluation costs
In addition to these activities the Company continued to incur costs relating to the ongoing maintenance
activities required at Honeymoon. The expenditure represents direct costs associated with these activities
as well as capitalised wages which can be directly attributable to Honeymoon.
This ASX announcement was approved and authorised by the Board of Boss Energy Limited.
For further information, contact:
Matt Dusci
Managing Director and Chief Executive Officer
P: +61 (8) 6263 4494
E: boss@bossenergy.com
For media enquiries, contact:
Paul Armstrong
Read Corporate
P: +61 (8) 9388 1474
E: info@readcorporate.com
ASX: BOE OTCQX: BQSSF www.bossenergy.com Page 12
Forward-Looking Statements
This announcement contains certain forward-looking statements provided by or on behalf of Boss with
respect to potential future matters. Forward-looking information may include, without limitation,
statements regarding plans, strategies and objectives of Boss, production and financial guidance, financial
forecasts, estimates of project milestones and timing and expected costs or production outputs. In some
cases, forward-looking information can be identified by terms such as “may”, “will”, “should”, “expect”,
“plan”, “anticipate”, “believe”, “intend”, “estimate”, “predict”, “potential”, “continue” or other similar
expressions concerning matters that are not historical facts. Guidance as to production, unit costs and
capital expenditure is based on assumptions, budgets and estimates existing at the time of assessment
which may change over time impacting the accuracy of those estimates. These estimates are developed
in the context of an uncertain operating environment including in respect of inflationary macroeconomic
conditions, and uncertainties surrounding the risks associated with mining and the further review of the
EFS which may impact production and have a flow on effect on sales. Actual results may therefore vary
significantly depending on these risks and the timing required to address them. All information is provided
as an indicative guide to assist sophisticated investors with modelling of the Company. It should not be
relied upon as a predictor of future performance.
Forward-looking statements reflect Boss’s expectations at the date of this announcement, however they
are not guarantees or predictions of future performance or statements of fact. Forward-looking
information involves known and unknown risks, uncertainties and other factors (many of which are
beyond the control of Boss and its directors and management) which may cause the actual results,
performance or achievements of Boss and its business to be materially different from any future results,
performance or achievements expressed or implied by the forward-looking information. Accordingly,
undue reliance should not be placed on forward-looking information.
The forward-looking statements in this announcement reflect various assumptions by or on behalf of Boss
(which assumptions may prove to be inaccurate). Accordingly, this is another reason why such statements
are subject to significant business, technical, legal, economic and competitive and other uncertainties and
contingencies and other factors which may be beyond the control of Boss which could cause actual results
or trends to differ materially from the forward-looking statements in this announcement, including but
not limited to differences or inaccuracies arising from price and currency fluctuations, geotechnical
factors, geological and mining factors, estimated continuity of mineralised horizons, metallurgical and
processing factors, sales factors, drilling and production results, development progress, operating results,
mineral resource estimates, legal issues, legislative, fiscal and regulatory developments, economic and
financial market conditions in various countries, approvals and cost estimates, environmental risks, ability
to meet funding requirements, share price volatility, uranium markets and other matters. Accordingly,
there can be no assurance that such forward-looking statements and projections will be realised.
Boss makes no representations as to the accuracy or completeness of any forward-looking statements or
projections or that any forecasts will be achieved. Additionally Boss makes no representation or warranty,
express or implied, in relation to, and (to the maximum extent permitted by law) no responsibility or
liability (whether for negligence, under statute or otherwise) is or will be accepted by Boss or by any of its
officers, directors, shareholders, partners, employees, or advisers as t
Share your feedback
Discover