September 2026 Quarterly Results Presentation
Released
Released
Announcement PDF
1
September 2026 Quarterly Report Presentation
Boss Energy. A global multi-mine Uranium producer
Aglobal multi-mine Uranium producer.
ASX: BOE
OTCQX: BQSSF
bossenergy.com
28 October 2026
September 2026
Quarterly Report Presentation
2
September 2026 Quarterly Report Presentation
Boss Energy. A global multi-mine Uranium producer
Solid start to FY27 as Boss advances the transition and growth
Q1 FY27 Highlights
Deliver & optimise
Honeymoon
Build the regional
production hub
Grow the resource &
discovery pipeline
Maximise & optimise
existing portfolio
Honeymoon Production Q1 FY27 Costs Other financial highlights
359 klbs
U₃O₈ drummed
337 klbs
IX production
(0.8%)
vs Q4 FY26
(9.2%)
vs Q4 FY26
A$47/lb
C1 cost
A$79/lb
AISC
A$13M
Capital spend
A$117/lb (US$81.8/lb)
Realised price
A$194.9M
Cash & liquid assets. No debt
• 359 klbs drummed on record
flow
• NFS delivered early: ~13.8 Mlbs,
mine life to at least FY341
• EKT1 flushing underway: early
results support the wide-spaced
design
• Aspiration: 2.5 Mlbs pa at
~A$65/lb AISC by the early 2030s2
• Three deposits, one plant:
Honeymoon, Jason's, Gould’s
Dam
• EPBC referral lodged: Mine
Extension decision due Q2 FY27
• Updated Mineral Resource
underpins the NFS mine plan
• Jason’s: 137-hole, ~15.6 km
delineation program from Q2
FY27
• Aircore: up to 80 holes testing
greenfield targets near
infrastructure
• Alta Mesa (30%): 10 klbs (100%
basis); Texas permitting delayed
new wellfields
• Under-contracted: 1.64 Mlbs
inventory leveraged to rising
prices
• No debt: A$195M cash and liquid
assets supports the wide-spaced
wellfield transition
+5.4%
vs Q4 FY26
+13.3%
vs Q4 FY26
1.641 Mlbs
Total inventory
FY27 guidance
C1 A$51–56/lb
AISC A$83–92/lb
Total capex A$58–65M
1. Refer to ASX announcement dated 27 August 2026 “Honeymoon New Feasibility Study and MRE Update”
2. Refer to the "Disclaimer and Important Notices" section of this Presentation, in particular the “Aspirational Statements” for further information.
3
September 2026 Quarterly Report Presentation
Boss Energy. A global multi-mine Uranium producer
Record flow supported production
Honeymoon Production
Honeymoon quarterly production, U₃O₈ (klbs)
Quarterly operating performance
• Solid start to FY27, in line with expectations
• Record flow offset the expected tenor decline in maturing wellfields
• Drummed output supported by a drawdown of in-circuit inventory
B6: first full quarter of production
• Encouraging result from the last wellfield on the previous design
• Low calcium levels and acid consumption observed
Q2 FY27 outlook
• Steady IX production, with higher flow offsetting declining tenor
• Construction progressing at EKT2, EKT3 and HMT1
EKT1: first wide-spaced wellfield
• Early flushing performance supports confidence in the NFS design
• Final flushing and first leaching results due in the December quarter
FY27 production guidance remains 1.25–1.30 Mlbs U₃O₈
386
456
203
362 359
376
406
221
371
337
Q1 FY26 Q2 FY26 Q3 FY26 Q4 FY26 Q1 FY27
Drummed production IX production
4
September 2026 Quarterly Report Presentation
Boss Energy. A global multi-mine Uranium producer
Early EKT1 flushing supports confidence in the wide-spaced design
Honeymoon Wellfield Transition
*Wellfield spacing is the injector-to-extractor distance. All wellfields shown above (except for HMT1) are intended to operate with 16 five-spot patterns, transitioning to an injector to extractor spacing of 49 m, with 8 five-spot patterns as outlined in the NFS.
Wide-spaced transition under way
• Flushing commenced at EKT1, our first wide-spaced wellfield.
• Early flushing performance supports confidence in the design.
Some transition wellfields have a spacing wider than the NFS
• EKT1 and HMT1 will test a spacing that’s wider than assumed in the NFS.
• Final flushing and first leach results in Q2 FY27 will test NFS assumptions.
Wellfield build-out on track
• Construction progressing at EKT2, EKT3 and HMT1.
• A rain event caused only a minor delay to EKT1 flushing and construction.
Now (Q1 FY27)
B6 producing
30 m wellfield spacing*
EKT1 flushing
58 m wellfield spacing*
Q2 FY27
EKT1 commences leaching
58 m wellfield spacing*
Q3 FY27
HMT1 commences leaching
70 m wellfield spacing*
4 five-spot patterns
Lowest grade area of the resource
Q4 FY27
EKT2 commences leaching
49 m wellfield spacing*
Q1 FY28
EKT3 commences leaching
49 m wellfield spacing*
Transition to wide-spaced wellfields
5
September 2026 Quarterly Report Presentation
Boss Energy. A global multi-mine Uranium producer
Water Treatment Plant Upgrades
Water treatment upgrades remain on track for the transition
Stage 1 targets near-term plant optimisation. Stage 2 adds capacity for the life-of-mine production schedule.
Stage 1: completion targeted Q4 FY27
• Specialist review of the existing plant completed
• Focus on cleaning, softener settling and hydraulic constraints
Stage 2: completion targeted Q3 FY28
• Expansion scoped at approximately 300 m³/h RO feed
• Test work will establish design criteria
Stage 1 and Stage 2
Delivery remains on track
6
September 2026 Quarterly Report Presentation
Boss Energy. A global multi-mine Uranium producer
Costs remain on track for FY27 guidance as the transition progresses
Cost Performance and FY27 Guidance
Full-year costs remain on track
• Q1 performance was consistent with expectations.
• Costs are expected to rise as average PLS tenor declines.
Key metric Unit Q1 FY27 Q4 FY26 FY27 guidance
C1 cash cost A$/lb 47 45 51–56
AISC A$/lb 79 70 83–92
Capital expenditure
Sustaining A$M 9 7 33–37
Process / project¹ A$M 4 14 25–28
Total capital A$M 13 21 58–65
A$ Q1 AUD/USD: 0.6977. ¹ Q1 process facilities vs Q4 project/support infrastructure.
Rain affected sustaining capital timing
• Rain temporarily interrupted drilling and wellfield construction.
• Spending focused on EKT1 first-fill and new wellfields.
Wide-spaced design targets lower costs
• The NFS provides a pathway to improve the cost structure.
• Focus now is consistent delivery of the wide-spaced design.
Process investment weighted to the second half
• Water treatment upgrades remain on track to support the planned
production ramp-up.
Quarterly AISC and realised price (A$/lb)
50 49
93
70
79
115 114
106 107
117
Q1 FY26 Q2 FY26 Q3 FY26 Q4 FY26 Q1 FY27
AISC Realised price
7
September 2026 Quarterly Report Presentation
Boss Energy. A global multi-mine Uranium producer
A debt-free balance sheet supports the transition and uranium price upside
Sales and Financial Position
Exposure to improving uranium prices
• Boss remains strategically under-contracted.
• Preserves exposure to stronger uranium pricing.
Sales and inventory Unit Q1 FY27 Q4 FY26
Sales revenue US$M 24.6 24.4
Sales revenue A$M 35.2 34.8
Realised price US$/lb 81.8 75.1
Realised price A$/lb 117.0 107.1
Sales volume klbs 301 325
Inventory held klbs 1,641 1,581
Cash held A$M 39.2 49.7
*Illustrative inventory value: 1.641 Mlbs at uraniumprice of US$90/lb at exchange rate of 0.70 AUD/USD. Cash and investments unchanged. Excludes selling costs and tax.
Balance sheet supports the transition
• A debt-free balance sheet supports organic funding for the wide-spaced
wellfield transition.
Pricing stronger in Q2 FY27 with legacy contract in H2 FY27
• Boss expects stronger realised pricing in the December quarter.
• Legacy contract deliveries of ~250k lbs in second half FY27.
Inventory continues to provide strategic benefit
• Supports strong financial position and upside to stronger pricing.
• Inventory is carried at the lower of cost and net realisable value.
Cash and liquid assets: book vs market value (A$M)
39
39
31
31
211
124
Market value*
A$281.6M
Book value
A$194.9M
Cash Investments Inventory
8
September 2026 Quarterly Report Presentation
Boss Energy. A global multi-mine Uranium producer
One plant, three deposits
Existing infrastructure provides the foundation for regional growth
1. Refer to the “Aspirational Statements” section in the "Disclaimer and Important Notices" section of this presentation.
2. Refer to Appendix 1 for further details of Mineral Resource classification for Gould’s Dam, Jason's Deposit and Honeymoon
33.1Mlbs Gould's Dam
Central facility site plan; resin loaded on site
Resin trucked
~75 km
20.8Mlbs Honeymoon hub
Plant, utilities and workforce in place
13 km twin
trunkline
12.0Mlbs Jason's Deposit
Tanks, pumps and power only
Mineral resource by deposit²
Deposit Ore (Mt) Grade (ppm) Mlbs U₃O₈
Gould's Dam 38.7 388 33.1
Jason's Deposit 13.3 410 12.0
Honeymoon 21.4 440 20.8
Total 73.3 410 65.9
2.5Mlbs pa
Hub rate aspiration by the early
2030s, on installed back-end
capacity¹
A$65/lb
AISC aspiration at hub scale,
~A$12/lb below the NFS¹
9
September 2026 Quarterly Report Presentation
Boss Energy. A global multi-mine Uranium producer
Hub development programme
Approvals and drilling progress across the regional hub
Project Progress and next steps
Honeymoon
Mine
Extension
• EPBC referral submitted. Decision expected Q2 FY27.
• Mining Lease Application progressing, incorporating referral requirements.
Jason's
Deposit
• Referral-stage technical work complete.
• Environmental studies near completion. EPBC documents well advanced.
• 15 diamond core holes to assess hydrogeology, mineralogy and mineralization.
• 137 mud rotary holes from Q2 FY27 to improve resource confidence and test extensions.
• Both drilling programmes: completion planned Q3 FY27.
Gould’s Dam • Studies underway assessing preferred processing configuration via Honeymoon plant.
Regional hub
and
catchment
• Honeymoon NFS work supports satellite evaluation.
• Up to 80 aircore holes in Q2–Q3 FY27 targeting proximate greenfield prospects.
• Studies, field validation and approvals underway.
Next decision point: HME referral outcome expected in Q2 FY27
10
September 2026 Quarterly Report Presentation
Boss Energy. A global multi-mine Uranium producer
Permitting delays constrained production and paused operations
Alta Mesa JV: Boss 30%
206
143
97
45
10
Q1 FY26 Q2 FY26 Q3 FY26 Q4 FY26 Q1 FY27
Drummed production
Alta Mesa quarterly production (100%), U₃O₈ (klbs)
Quarterly operating performance
• 10 klbs drummed in Q1 FY27 compared with 45 klbs in Q4 FY26, on a
100% basis.
Boss product receipts
• Boss received no product during Q1 FY27, compared with 13 klbs in the
previous quarter.
Permitting and operations
• State permitting delays prevented timely replacement of declining
wellfields. Plant production has stopped pending new wellfields.
Wellfield outlook
• PAA3 expected in Q2 FY27 and PAA8 in Q3 FY27, subject to permitting.
Production paused pending new wellfields
11
September 2026 Quarterly Report Presentation
Boss Energy. A global multi-mine Uranium producer
Boss Energy. A global multi-mine Uranium producer
Focussed on consistent delivery to expectations
FY27 Outlook
Debt-free funding Uranium price upside Lower-cost growth
Guidance unchanged Proving the design
A$194.9M in cash,
liquid assets and
inventory supports
the transition
Under-contracted
position retains
exposure to
stronger prices
Regional hub strategy
uses existing
infrastructure to
extend mine life
1.25–1.30 Mlbs
C1 A$51–56/lb
AISC A$83–92/lb
First EKT1 leaching
results expected
in Q2
12
September 2026 Quarterly Report Presentation
Boss Energy. A global multi-mine Uranium producer
Appendix 1 - Gould’s Dam and Jason's Deposit Mineral Resource (March 2026)
Resource Classification
Grade Metal
Mt ppm U3O8 Kt U3O8
Mlbs
U3O8
Indicated 7.5 465 3.5 7.7
Inferred 31.2 369 11.5 25.4
TOTAL 38.7 388 15.0 33.1
Table 1: Gould’s Dam Mineral Resource (reported 19 March 2026) Table 2: Jason's Deposit Mineral Resource (reported 19 March 2026)
Resource Classification
Grade Metal
Mt ppm U3O8 Kt U3O8
Mlbs
U3O8
Indicated 4.8 464 2.2 4.9
Inferred 8.5 380 3.2 7.1
TOTAL 13.3 410 5.4 12.0
Notes:
• Effective 31 December 2025
• The model is reported unconstrained and above a 250ppm U3O8 lower cut-off grade and 100mD Ksdr
permeability (unit millidarcy; mD) lower cutoff for all mineralisationsubdomains in considerationof
potential for recovery by ISR processing.
• The U3O8 lower cut-off grade reflects the assumed lower detection limit of the PFN tool. A Ksdr
permeability is assumed to be moderate permeable equivalent to a well-sorted sand/gravels which would
be amenable for ISR mining.
• There is no historic depletion by production.
• Estimation of the combined PFN data and disequilibrium factored gamma data with high-grade cuts is by
ordinary kriging using dynamic anisotropy for the mineralised zones.
• The definition of the mineralised zones is refined by conditional indicatorkriging (CIK) estimate based on a
250ppm U3O8 indicator and a resultant estimated 17% probability of being above the indicator cut-off
grade. The subdomains are used as hard boundaries.
• Density is for the Eyre Formation based on analyses of sonic core as 1.9 t/m3, which is consistent with
semi-consolidated quartz sandstone.
• The model assumes agglomeration of 10mE x 10mN x 1mRL parent blocks for definition of well fields for
production in the Gould’s Dam area. The surrounding areas that are still at an early stage of resource
definition with less available data were modelled on larger 40mE x 40mN x 1mRL panels.
• The model does not account for dilution, ore loss, hydrogeology, or recovery issues. Continuity of high-
grade U3O8 is expected to be locally erratic throughout the palaeovalley. These parameters should be
considered during the mining study as being dependent on the ISR treatment process.
• Classificationis according to JORC Code Mineral Resource categories.
• Estimated disequilibrium factors applied to the gamma data cannot fully mitigate the risk of assumptions
about the tenor of uranium mineralisation based on that gamma data. The gamma data does not directly
measure uranium.
• A Mineral Resource requires technical and economic evaluation and considerationof modifying factors for
conversion to an Ore Reserve. It is possible that not all Mineral Resource will convert to an Ore Reserve.
• Totals may vary due to rounded figures.
Notes:
• Effective 31 December 2025
• The model is reported unconstrained and above a 250ppm U3O8 lower cut-off grade and 100mD Ksdr
permeability (unit millidarcy; mD) lower cutoff for all mineralisation subdomains in considerationof
potential for recovery by ISR processing.
• The U3O8 lower cut-off grade reflects the assumed lower detection limit of the PFN tool.
• A Ksdr permeability is assumed to be moderate permeable equivalent to a well-sorted sand/gravels which
would be amenable for ISR mining.
• There is no historic depletion by production.
• Estimation of the combined PFN data and disequilibrium factored gamma data with high-grade cuts is by
ordinary kriging using dynamic anisotropy for the mineralised zones.
• The definition of the mineralised zones is refined by conditional indicatorkriging (CIK) estimate based on a
250ppm U3O8 indicator and a resultant estimated 17% probability of being above the indicator cut-off
grade. The subdomains are used as hard boundaries.
• Density is for the Eyre Formation based on analyses of sonic core as 1.9 t/m3, which is consistent with
semi-consolidated quartz sandstone.
• The Jason's Deposit model assumes agglomeration of 40mE x 40mN x 1mRL parent blocks for early-stage
resource definition with wide spaced fences, closer spaced drilling along the fences and good proportion
of recent, quality data. The model is held on 10mE x 10mN x 1m sub blocks to accommodate a lithological
model generated by Boss.
• The model does not account for dilution, ore loss, hydrogeology, or recovery issues. Continuity of high-
grade U3O8 is expected to be locally erratic throughout the palaeovalley. These parameters should be
considered during the mining study as being dependent on the ISR treatment process.
• Classificationis according to JORC Code Mineral Resource categories.
• Estimated disequilibrium factors applied to the gamma data cannot fully mitigate the risk of assumptions
about the tenor of uranium mineralisationbased on that gamma data. The gamma data does not directly
measure uranium.
• A Mineral Resource requires technical and economic evaluation and considerationof modifying factors for
conversion to an Ore Reserve. It is possible that not all Mineral Resource will convert to an Ore Reserve.
• Totals may vary due to rounded figures.
13
September 2026 Quarterly Report Presentation
Boss Energy. A global multi-mine Uranium producer
Resource Classification
Grade Metal
Mt ppm U3O8 Kt U3O8
Mlbs
U3O8
Indicated 12.1 510 6.2 13.7
Inferred 9.3 350 3.2 7.1
TOTAL 21.4 440 9.4 20.8
Table 3: Honeymoon Mineral Resource (reported 27 August 2026)
Notes:
• The Mineral Resource estimate is classified in accordance with the JORC Code (2012).
• The Mineral Resource database has a cut-off date of 31 December 2025.
• The effective date of the Mineral Resource estimate is 30 June 2026.
• The Mineral Resource estimate is reported at an in-situ cut-off of 100 ppm U3O8. A grade-thickness (GT)
cut-off of GT≥400 m.ppm U3O8 was applied selectively in border areas of the MRE.
• Only the recoverable portion of blocks ≥100 ppm U3O8 is reported.
• The Mineral Resource is constrained to an ISR-amenable permeability threshold of KSDR≥100 mD.
• The Mineral Resource is mainly based on equivalent U3O8 (eU3O8), without adjusting for localised
radiometric disequilibrium effects.
• The Mineral Resource estimate is reported net of depletion from the Honeymoon in-situ recovery (ISR)
extraction of 3.3 Mlbs U3O8 (1.5 Kt U3O8) as of 30 June 2026 by subtraction of extracted metal tonnes from
Indicated Resource metal tonnes.
• The Mineral Resource estimate is reported on an in-situ tonnes basis.
• The Mineral Resource estimate is rounded to reflect the level of confidence in the estimate at the time of
reporting.
• Totals may vary due to rounding.
• The Mineral Resource estimate is reported both within the Honeymoon ML6109 licence and outside in
EL6081 licence.
Honeymoon Project Mineral Resource Estimate — effective date 30 June 2026, reported net of ISR depletion of 3.3 Mlbs U3O8 to 30 June 2026.
Appendix 1 - Honeymoon Mineral Resource
14
September 2026 Quarterly Report Presentation
Boss Energy. A global multi-mine Uranium producer
Disclaimer and Important Notices
This investor presentation (“Presentation”)has been prepared by Boss Energy Limited (ACN 116 834 336) (“Boss Energy”, “Boss” or “Company”).
NOT INVESTMENT ADVICE
This Presentation does not constitute in any way an offer or invitationto subscribe for securities in Boss Energy pursuant to the CorporationsAct 2001 (Cth) and has not been lodged with the Australian Securities and Investments
Commission.
This Presentation does not constitute investment advice and has been prepared by Boss Energy without taking into account the recipient’s investment objectives, financialcircumstances or particular needs. Each recipient must make
his/herown independent assessment and investigation of Boss Energy and its business and assets when deciding if an investment is appropriate and should not rely on any statement or the adequacy and accuracy of any information. This
Presentation is in summary form and is not exhaustive. This Presentation should be read in conjunctionwith Boss Energy’s periodic and continuousdisclosure s lodged with the Australian Securities Exchange, which are available to
download at www.asx.com.au.
PAST PERFORMANCE
Past performance information, includingpast share price performance of Boss and past HoneymoonProject information, given in this Presentation is given for illustrative purposes only and should not be relied upon as (and is not) an
indicationof Boss’s (or anyone else’s) views on Boss’s future activities, guidance or financialperformance or condition. Past performance of Boss cannot be relied upon as an indicator of (and provides no guidance as to) the future
performance of Boss.
FORWARD LOOKING STATEMENTS
This Presentation contains certain forward-looking statements provided by or on behalf of Boss with respect to potential future matters. Forward-looking informationmay include, without limitation, statements regarding plans, strategies
and objectives of Boss, production and financial guidance, financialforecasts, estimates of project milestones and timing and expected costs or production outputs. In some cases, forward-looking information can be identified by terms
such as “may”, “will”, “should”, “expect”, “plan”, “anticipate”, “believe”, “intend”, “estimate”, “predict”, “potential”, “continue” or other similar expressions concerningmatters that are not historicalfacts.
Guidance as to production, unit costs and capital expenditure is based on assumptions, budgets and estimates existing at the time of assessment which may change over time impacting the accuracy of those estimates. These estimates are
developed in the context of an uncertain operating environment including in respect of inflationarymacroeconomic conditions, and uncertainties surrounding the risks associated with mining which may impact production and have a flow on
effect on sales. Actual results may therefore vary significantly depending on these risks and the timing required to address them.
Forward-lookingstatements reflect Boss’s expectations at the date of this Presentation, however they are not guarantees or predictions of future performance or statements of fact. Forward-looking informationinvolves known and unknown
risks, uncertainties and other factors (many of which are beyond the controlof Boss and its directors and management) which may cause the actual results, performanceor achievements of Boss and its business to be materially different
from any future results, performance or achievements expressed or implied by the forward-looking information. Accordingly, undue reliance should not be placed on forward-looking information.
The forward-lookingstatements in this Presentation reflect various assumptions by or on behalf of Boss (which assumptions may prove to be inaccurate). Accordingly, this is another reason why such statements are subject to significant
business, technical, legal, economic and competitive and other uncertainties and contingencies and other factors which may be beyond the control of Boss which could cause actual results or trends to differ materially from the forward-
looking statements in this Presentation, including but not limited to differences or inaccuracies arising from price and currency fluctuations, geotechnicalfactors, geological and miningfactors, estimated continuity of mineralisedhorizons,
metallurgical and processing factors, sales factors, drilling and production results, development progress, operating results, mineral resource estimates, legal issues, legislative, fiscal and regulatory developments, economicand financial
market conditionsin various countries, approvals and cost estimates, environmental risks, ability to meet funding requirements, share price volatility, uranium markets and other matters.
Accordingly, there can be no assurance that such forward-looking statements and projections will be realised.
Boss makes no representations as to the accuracy or completeness of any forward-lookingstatements or projections or that any forecasts will be achieved. Additionally Boss makes no representation or warranty, express or implied, in
relation to, and (to the maximum extent permitted by law) no responsibility or liability (whether for negligence, under statute or otherwise) is or will be accepted by Boss or by any of its officers, directors, shareholders, partners, employees, or
advisers as to or in relation to the accuracy or completeness of the information, statements, opinions ormatters (express or implied) arising out of, contained in or derived from this Presentation or any omission fromthis Presentation.
Boss does not undertake or accept any obligation or undertaking to release publicly any updates or revisionsto any forward-lookingstatements to reflect any change in Boss’s expectations or any change in events, conditionsor
circumstances on which any such statement is based, except as required by law.
Mineral Resource estimates are necessarily imprecise and depend on interpretations and geologicalassumptions, minerals prices, cost assumptions and statistical inferences(and assumptions concerningother factors, includingmining,
processing, metallurgical, infrastructure, economic, marketing, legal, environmental, social and governmental factors) which may ultimately prove to be incorrect or unreliable.
Mineral Resource estimates are regularly revised based on actual explorationor production experience or new information and could therefore be subject to change. In addition, there are risks associated with such estimates, including
(among other risks) that minerals mined may be of a different grade or tonnage from those in the estimates and the ability to economicallyextract and process the minerals may become compromised or not eventuate.
Accordingly, this is another reason why no assurances can be given of whether the production guidance, financialforecasts or other forecasts or other forward-lookingstatements or informationin this Presentation will be achieved.
15
September 2026 Quarterly Report Presentation
Boss Energy. A global multi-mine Uranium producer
Disclaimer and Important Notices
CURRENCY AND EFFECT OF ROUNDING
All dollar (“$”) amounts are in Australian dollars unless otherwise stated. All cost forecasts are in real 2026 terms. A number of figures, amounts, percentages, estimates, calculations of value and fractions in this Presentation are
subject to the effect of rounding. Accordingly, the actual calculation of these figures may differ from the figures set out in this Presentation.
MINERAL RESOURCE ESTIMATES
The information in thisPresentation that relates to the MineralResource estimate for the Honeymoon Deposit was reported in an announcement by the Company dated 27 August 2026 titled “HoneymoonNew Feasibility Study and MRE
Update”.
The information in thisPresentation that relates to the MineralResource estimate for Gould’s Dam and the Jason's Deposit was reported in an announcement by the Companydated 19 March 2026 titled “Gould’s Dam and Jason's
Deposit Mineral Resource and Permitting Update.”
The Company confirmsthat it is not aware of any new information or data that materially affects the informationincluded in the original market s referred to above and that all material assumptions and technical parameters
underpinning the Honeymoon Deposit, Gould’s Dam and Jason's Deposit Mineral Resource estimates in the originalmarket s referred to above continue to apply and have not materially changed.
PRODUCTION TARGET AND FORECAST FINANCIAL INFORMATION
The information in thisPresentation that relates to the productiontarget (and forecast financial information derived from the production target) for the HoneymoonDeposit was reported in an announcement by the Company dated 27
August 2026 titled “Honeymoon New Feasibility Study and MRE Update.”
The Company confirmsthat all the material assumptions underpinning the production target and forecast financial information derived from the production target in that continue to apply and have not materially changed.
The production target and forecast financial informationfor the HoneymoonDeposit referred to in this Presentation is based on 65% Indicated MineralResources and 35% Inferred Mineral Resources over the 9-year life of mine. The first
4 years of the production target is underpinnedby 89% Indicated Mineral Resources and 11% Inferred Mineral Resources. There is a low level of geological confidence associated with Inferred Mineral Resources and there is no certainty
that further explorationwork will result in the determinationof Indicated Mineral Resources or that the productiontarget will be realised.
The Company believes that it has a reasonable basis for providingthe production target and forward-looking statements in this Presentation as the Inferred Mineral Resources are not the determining factor in project viability (noting,
most significantlythat Honeymoonis already in production). Refer to Section 12 of the New Feasibility Study (attached to the Company’s dated 27 August 2026 titled “Honeymoon New Feasibility Study and MRE Update.”) for the
material assumptions underpinningthe production target and forecast financial information.
ASPIRATIONAL STATEMENTS
The statements which appear throughout this regarding the aspiration for the HoneymoonProcessing Hub to produce 2.5M lbs U₃O₈ at an AISC of A$65/lb (US$45/lb) by the early 2030s are aspirational statements and not a Production
Target. The Company does not yet have reasonable grounds to believe these statements can be achieved. In particular, the statements are aspirational because:
1. whilst the Company has undertaken various internal studies on the Gould's Dam deposit and Jason's Deposit, the Company has not yet completed a Scoping Study or a Feasibility Study or published a Production Target for
Gould’s Dam or Jason's Deposit. Substantial further work is required before such a Scoping Study, Feasibility Study or Production Target could be completed or published; and
2. the aspiration is dependent on integrating the Gould’s Dam and Jason'sDeposit with the existing Honeymoon Mineoperations. This remains subject to a number of variables, including: further drilling and resource definition;
hydrogeological, metallurgical and wellfield performance; success of the wide-spaced wellfield design which is still currently being tested at Honeymoon; ISR recovery assumptions; selection and implementation oftransport and
processing methods, including the proposed Jason'sDeposit trunkline and Gould’s Dam resin or eluate trucking options; Honeymoonplant and infrastructure capacity and upgrades; and obtainment of applicable regulatory and
environmental approvals.
Accordingly, there is no certainty that the aspiration will be achieved.