Boss Energy Limited (ASX: BOE; OTCQX: BQSSF) (the Company or Boss) provides an update on its
Honeymoon Operational Review, which was initiated in late July 2025.1
The primary purpose of the review is to determine the potential for reduced continuity of mineralisation
and leachability compared with the assumptions contained in the Company’s Enhanced Feasibility Study
(EFS) dated 21 June 2021 and to assess any impact that may have on the Company’s ability to achieve the
production nameplate capacity specified in the EFS.
To date, Boss has established a technical team, program of work and timeline to complete the review and
currently expects the review to be completed in the December quarter, 2025. In addition to assessing the
potential impact on the EFS assumptions and production volumes, the output from the review is expected
to include an assessment of the mineral resource and wellfield design.
The progress achieved to date includes:
•
Review of the Honeymoon and satellite deposits, Jasons and Goulds Dam, underway, with a focus on
the input assumptions, data, resource domaining, estimation methodology and mineralisation
continuity. This review is being led by the Boss geological team with support and input from
competent persons and independent consultants; and
•
Engagement of additional In-Situ Leach (ISR) mining experts to complement the geological team in
assessing future wellfield design and planning. This team comprises experts who have previously
worked at Boss as well as new wellfield team members who will conduct a review of wellfield design
and planning based on international best-practice.
Boss is also accelerating resource drilling to support the wellfields planning schedule. The accelerated
drilling program is expected to commence in mid-September 2025 and is anticipated to take
approximately seven to nine months to complete.
Boss Managing Director Duncan Craib said: “We have moved quickly to appoint leading experts in their
fields with the aim of establishing an accurate and independent assessment of our resources and optimum
production rates. The review is on track for completion in the December quarter of 2025”.
This ASX announcement was approved and authorised by the Board of Boss Energy Limited.
For further information, contact:
Duncan Craib
Chief Executive Officer
P: +61 (8) 6263 4494
E: boss@bossenergy.com
For media enquiries, contact:
Paul Armstrong
Read Corporate
P: +61 (8) 9388 1474
E: info@readcorporate.com
1 See the Company’s announcements dated 28 July 2025 (“Honeymoon FY26 Guidance” and “June 2025 Quarterly Results Presentation”) and 5
August 2025 (“Response to ASX Aware Query”) for further details.
FOR FURTHER INFORMATION PLEASE CONTACT:
Boss Energy Limited
ABN 38 116 834 336
Duncan Craib - Managing Director/ CEO
+61 (08) 6263 4494
ASX: BOE
OTCQX: BQSSF
Level 1, 420 Hay Street, Subiaco
Western Australia 6008
Paul Armstrong – Public Relations
+61 (08) 9388 1474
www.bossenergy.com
@Boss_Energy
Forward-Looking Statements
This announcement includes forward-looking statements. These forward-looking statements are based
on the Company’s expectations and beliefs concerning future events. Forward-looking statements are
necessarily subject to risks, uncertainties, and other factors, many of which are outside the control of Boss
Energy, which could cause actual results to differ materially from such statements. Boss Energy makes no
undertaking to subsequently update or revise the forward-looking statements made in this
announcement, to reflect the circumstances or events after the date of this announcement.
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
@Boss_Energy
Share your feedback
Discover