Honeymoon Achieves Project Milestone - NIMCIX delivery
Released
Released
Announcement PDF
ASX Release 3 August 2023
Honeymoon Uranium Project, South Australia
Honeymoon Achieves Project Milestone
Further delivery of the first set of NIMCIX loading and
elution columns for the new Ion Exchange circuit
Boss Energy (ASX: BOE; OTCQB: BQSSF) is pleased to announce another major milestone at its
Honeymoon Uranium project with the arrival onsite of the first set of NIMCIX loading and elution
columns for the new Ion Exchange (IX) circuit.
The adoption of IX technology, which is central to the processing plant, will enable highly efficient
capture, concentration, and purification of the uranium from the wellfields. This will result in increased
throughput, more production and lower costs than was possible using the solvent extraction system
previously employed at Honeymoon. This was proven by the extensive tests conducted by Boss and
leading independent industry experts, before and during the Honeymoon feasibility studies.
Boss Managing Director Duncan Craib said the IX circuit would drive efficiencies at Honeymoon,
increasing production throughput to nameplate capacity of 2.45Mlb/annum of U3O8 while reducing
ramp up time and technical risks. It will also reduce operating costs to industry benchmarks, including
a forecast AISC of US$25/lb and cash costs of less than US$20/lb.
Image 1: First NIMCIX elution column entering Honeymoon uranium mine site
FOR FURTHER INFORMATION PLEASE CONTACT:
Boss Energy Limited
ABN 38 116 834 336
Duncan Craib - Managing Director/ CEO
+61 (08) 6263 4494
ASX: BOE
OTCQX: BQSSF
Level 1, 420 Hay Street, Subiaco
Western Australia 6008
Paul Armstrong – Public Relations
+61 (08) 9388 1474
www.bossenergy.com
@Boss_Energy
“IX is used in the vast majority of uranium in-situ leach operations in Kazakhstan, the USA and Australia.
In terms of operating and capital costs, IX has significant advantages over all other technologies,” Mr
Craib said.
"Honeymoon is one of the world’s most advanced uranium development projects and is being fasttracked to re-start production in Q4 2023. The first set of loading and elution columns will be sufficient
to enable Boss to commission the project and commence production. Another five sets will be added
as part of the subsequent production ramp up.”
In addition to the first set of NIMCIX loading and elution columns being delivered, the Company is also
pleased to announce the arrival of the majority of steel required for the IX tower reconfiguration.
Image 2: Boss owned 400T crane advancing construction activities
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
@Boss_Energy
Image 3: Removal of redundant Solvent Exchange pulse columns
This ASX announcement was approved and authorised by the Board of Boss Energy Limited.
For further information, contact:
Duncan Craib
Chief Executive Officer
P: +61 (8) 6263 4494
E: boss@bossenergy.com
For media enquiries, contact:
Paul Armstrong
Read Corporate
P: +61 (8) 9388 1474
E: info@readcorporate.com
Reference to previous ASX announcements
In relation to the results of the Enhanced Feasibility Study announced on 21 June 2021, the Company
confirms that all material assumptions underpinning the production target and forecast financial
information included in that announcement continue to apply and have not materially changed.
Forward-Looking Statements
This announcement includes forward-looking statements. These forward-looking statements are
based on the Company’s expectations and beliefs concerning future events. Forward-looking
statements are necessarily subject to risks, uncertainties, and other factors, many of which are outside
the control of Boss Energy, which could cause actual results to differ materially from such statements.
Boss Energy makes no undertaking to subsequently update or revise the forward-looking statements
made in this announcement, to reflect the circumstances or events after the date of this
announcement.