Honeymoon NFS confirms continued
economic production
Boss has established world-class ISR technical capability, operating experience and advanced
modelling which underpin a robust pathway to long-term economic uranium production
Highlights
• Successful NFS confirms economic production pathway – New Feasibility Study (NFS) confirms
that a wide-spaced ISR wellfield design is viable and is forecast to support continued economic
uranium production at Honeymoon until at least FY34, with forecast life-of-mine production, of
approximately 13.8Mlbs U₃O₈ drummed over a nine-year operating period.
• Wider well spacing materially lowers costs – Increasing wellfield spacing mitigates the impact
of the lower Mineral Resource Estimate (MRE) and reduces life-of-mine AISC by approximately
$30/lb on a like-for-like basis compared with applying the original planned wellfield spacing to
the updated MRE.
• Favourable deposit characteristics – The wide-spaced wellfield design is enabled by
Honeymoon’s unique combination of favourable deposit characteristics, including a
combination of high permeability and hydraulic connectivity, effective aquifer confinement, low
natural groundwater-flow velocity and low acid consumption.
• Benchmarking inline against established ISR operations – Key wellfield design and operating
parameters have been benchmarked in line with several ISR operations in Kazakhstan.
• Adopted world-class technical approach to ISR mine planning – Utilising deposit-scale reactive
transport modelling (RTM) calibrated against extensive historical operating data, representing a
world-class technical approach to ISR mine planning.
Cautionary Statement
The production target and forecast financial information referred to in this announcement (including
attachments) is based on 65% Indicated Mineral Resources and 35% Inferred Mineral Resources over the
9-year life-of-mine. The first 4 years of the production target is underpinned by 89% Indicated Mineral
Resources and 11% Inferred Mineral Resources. There is a low level of geological confidence associated
with Inferred Mineral Resources and there is no certainty that further exploration work will result in the
determination of Indicated Mineral Resources or that the production target will be realised.
The Company believes that it has a reasonable basis for providing the production target and forward-
looking statements in this announcement as the Inferred Mineral Resources are not the determining factor
in project viability (noting, most significantly that Honeymoon is already in production). Refer to Section
12 of the New Feasibility Study (attached to this announcement) for the material assumptions
underpinning the production target and forecast financial information.
ASX: BOE OTCQX: BQSSF www.bossenergy.com Page 2
Life-of-mine plan, production and cost
• Nine-year production profile – Forecast life-of-mine production, of approximately 13.8Mlbs
U₃O₈ drummed over a nine-year operating period, to reach 1.9Mlbs per annum from FY30 to
FY33.
• Lower cost through higher PLS grades and reduced infrastructure – Average C1 cost of A$50/lb
(US$35/lb) and AISC of A$79/lb (US$55/lb),1
reflecting an increase in concentration of uranium
in the pregnant leach solution (PLS) grade by circa 28% and reduction in wellfield infrastructure
of circa 50% as compared with the historical design being applied to the updated MRE.
• Capital-light ongoing transition to wide-spacing – Most of the total capital is sustaining capital
which is phased as new wellfields are brought online over the life-of-mine. Minimal additional
facilities capital of $48M to be phased over the next three years (total of $58M over life-of-
mine).
• Disciplined capital allocation through transition – The short-term production and cost profile
reflects mine-development uncertainty since July 2025 and Boss’ disciplined decision to limit
further investment in legacy wellfields where the expected returns did not deliver an acceptable
return on capital. This approach prioritised long-term value and balance-sheet strength while
balancing near-term production during the transition to the wide-spaced wellfield design, which
commenced in January 2026.
• Substantial recovery of MRE reduction – Forecast life-of-mine production is 26% lower as
compared to the 2021 EFS2
, reflecting a substantial recovery of a 63% decline from the 2019
MRE to the updated MRE at a like for like cut-off grade of 250 ppm. This demonstrates the
benefit of the wide-spaced wellfield design to enable a reduction in cut-off grade to 100 ppm
which has brought substantial low-grade resource into an economic wellfield design.
Established operation and infrastructure
• Existing infrastructure – Full ongoing utilisation of the existing processing plant, trunklines and
other infrastructure.
• Proven processing performance – Since restarting in April 2024, Honeymoon has produced
more than 2.3Mlbs of drummed U₃O₈, demonstrating proven processing performance and the
effectiveness of the ongoing lixiviant chemistry and resin loading and unloading processes.
• Targeted capacity upgrades – Completion of NIMCIX column 6 and the staged expansion of the
Water Treatment Plant (WTP) are required to support the life-of-mine production schedule.
• Production upside – Earlier delivery of the Water Treatment Plant expansion or continued
optimisation of water treatment requirements could accelerate the production ramp-up.
1 C1 cost and AISC reflect the life-of-mine average to 2034
2 Refer to ASX Release dated 21 June 2021, titled “Updated Feasibility Study identifies lower costs and increased financial returns”. Comparison adds
back drummed production up to 30 June 2026 of 2.3Mlbs for a like for like comparison.
ASX: BOE OTCQX: BQSSF www.bossenergy.com Page 3
Updated Mineral Resource Estimate
• Updated Mineral Resource – Updated Honeymoon Deposit MRE of 21.4 Mt @ 440 ppm3
U3O8
for 20.8 Mlbs of U3O8 metal at 100 ppm cut-off, comprising 66% Indicated and 34% Inferred.4
• Updated Mineral Resource foundation – NFS is underpinned by an updated MRE incorporating
substantially increased drilling density, revised geological interpretations, estimation
methodology, incorporated operating permeability data, and experience gained since
production recommenced. This enables a materially enhanced understanding of the
mineralisation grade and distribution, geology and permeability.
• Uranium in clay has been excluded – The updated MRE includes only uranium hosted within
permeable reservoir sands that is considered contactable by lixiviant, based on a newly
developed permeability model.
• Updated estimation methodology – The MRE incorporates a reduction in cut-off grade from
250 ppm to 100 ppm U3O8, a change in estimation approach and the application of ISR-specific
criteria for assessing the reasonable prospects for eventual economic extraction.
• Decrease compared with previous resource – The updated Honeymoon MRE (at a 100 ppm
U3O8 cut-off and depleted as of 30 June 2026) represents a decrease in metal of 15.1 Mlbs U3O8
(-42%), with an average grade reduction of 220 ppm U3O8 (-33%) compared to the 2019 MRE (at
a 250 ppm U3O8 cut-off and depleted through to 2019)5
, which supported the 2021 EFS. At a 250
ppm cut-off and without accounting for depletion, the U3O8 metal has decreased by 63%, and
the U3O8 grade has increased by 16% from the 2019 Honeymoon MRE to the updated MRE.
Improvement, growth and approvals
• Further wellfield optimisation potential – The NFS identifies opportunities to further optimise
wellfield spacing, which could reduce infrastructure requirements and improve capital
efficiency, recovery and unit costs.
• Brooks Dam North included in the mine plan — The NFS life-of-mine production target includes
Brooks Dam North, which contributes approximately 15% of forecast production. Production
from this domain requires the planned Honeymoon Mine Extension, with approvals targeted by
2030.
• Regional growth opportunity beyond the NFS – Jasons Deposit and Gould’s Dam contain a
combined Mineral Resource of 45.1Mlbs U₃O₈6
and are not included in the NFS life-of-mine plan.
Their proximity, and similarity of deposit characteristics, to Honeymoon potentially provide a
low-capital pathway to extend mine life and increase production by leveraging existing
infrastructure, ISR capability and the operating workforce, subject to studies.
A conference call will be held today, Thursday, 27 August 2026, at 7am AWST (9am AEST).
To register and listen in live, please click on the link below:
https://loghic.eventsair.com/568147/931415/Site/Register
3 The Mineral Resource is mainly based on equivalent U3O8 (eU3O8), without adjusting for localised radiometric disequilibrium effects.
4 Due to localised variances in forecast recovery rates of Indicated and Inferred material, the production target and forecast financial information
referred to in this announcement (including attachments) is based on 65% Indicated Mineral Resources and 35% Inferred Mineral Resources over the
9-year life of mine.
5
Refer to ASX Release dated 25 February 2019, titled “149% Increase in Measured & Indicated Mineral Resources over Honeymoon Re-start Area”
6
Refer to ASX Release dated 19 March 2026, titled “Gould’s Dam and Jasons Deposit Mineral Resource and Permitting Update.” Jasons Deposit MRE
comprises 13.3Mt @ 410 ppm U₃O₈ for 12.0Mlbs U₃O₈ metal. Gould’s Dam MRE comprises 38.7Mt @ 388ppm U₃O₈ for 33.1Mlbs U3O8 metal. Refer
to Important Notices for further detail on the Gould’s Dam and Jasons Deposit MRE, including the Mineral Resource Classification
ASX: BOE OTCQX: BQSSF www.bossenergy.com Page 4
Boss Energy Limited (ASX: BOE; OTCQX: BQSSF) (“Boss” or “the Company”) is pleased to announce the
outcomes of the updated Mineral Resource Estimate (MRE) and New Feasibility Study (NFS) for its 100%-
owned Honeymoon Uranium Operation in South Australia.
The NFS establishes a new economic life-of-mine plan for Honeymoon, that is founded on new world-
class technical capability but, critically, incorporates growing operating data and experience built since
production restarted in April 2024.
The study incorporates additional drilling, an updated Mineral Resource, detailed permeability and
geometallurgical analysis, actual wellfield performance and advanced reactive transport modelling.
Combined, this work has materially improved Boss’ understanding of the distribution of uranium
mineralisation, permeability, hydraulic connectivity and the geochemical processes controlling uranium
recovery. As a result, the Company views that the NFS represents a detailed study upon which to deliver
a long-term, viable uranium operation.
The NFS confirms a wide-spaced five-spot, 8 pattern, wellfield design as optimal for the development of
Honeymoon. The design reduces the number of wells and associated surface infrastructure required to
access an equivalent mineralised area, lowering the relative cost of development. The wider-spacing and
refined operational design are enabled by deposit characteristics at Honeymoon which results in
significantly lower acid consumption and much higher lixiviant residence time. As a result, the increased
effective recoveries enable more of Honeymoon’s extensive lower-grade mineralisation to be
incorporated into the production plan.
The existing Honeymoon processing facility remains the foundation of the operation, with consistent
operations since April 2024, demonstrative of a robust flowsheet design that retains capacity to support
future production growth.
Boss CEO and Managing Director, Matthew Dusci, commented:
“The New Feasibility Study establishes a technically robust pathway for Honeymoon and delivers a
fundamental step change in the operation’s cost structure.
“86,670 metres of new drilling, commercial ISR operating data, deposit-wide permeability modelling
and advanced reactive transport modelling have transformed our understanding of the deposit and
how it can be most effectively developed.
“This work has enabled us to redesign the wellfields around the characteristics of the orebody. The
selected wide-spaced design accesses more of the resource with substantially fewer wells and less
infrastructure, while increasing lixiviant residence time to support higher PLS grades and improved
recoveries. Together, these benefits materially reduce capital intensity and operating costs,
establishing a structurally lower-cost pathway for Honeymoon compared with the previous wellfield
design.
“The NFS provides a high-confidence base-case production plan from an established operating
platform, with the processing plant and core infrastructure already in place. Importantly, this base
case is not the limit of Honeymoon’s potential. There remains significant scope to further optimise
well spacing, recovery, production, costs and mine life as operating data continues to build.
“The NFS includes only the Honeymoon Mineral Resource and excludes Gould’s Dam and Jasons
Deposit. The broader Honeymoon region comprises a combined Mineral Resource of 65.9Mlbs U₃O₈,
including 45.1Mlbs at Gould’s Dam and Jasons Deposit. These resources provide substantial
potential to increase annual production and extend mine life by leveraging Honeymoon’s
established infrastructure, operating workforce and Boss’ ISR capability.
ASX: BOE OTCQX: BQSSF www.bossenergy.com Page 5
“With the base-case plan established, our focus is now on execution, optimisation and growth. We
have a clear pathway to drive further value from Honeymoon and progressively establish it as the
centre of a larger, low-capital regional uranium production hub. Boss’ strong balance sheet provides
the capacity to readily fund the additional capital identified in the NFS.
“I would like to acknowledge the exceptional effort and technical capability of the Boss team and
our consulting partners in delivering the New Feasibility Study and updated Mineral Resource
Estimate.”
ASX: BOE OTCQX: BQSSF www.bossenergy.com Page 6
1. Honeymoon Feasibility Study Outcomes - Summary
1.1. Introduction
Boss initiated the Honeymoon Review after the review of delineation drilling and operating performance
identified potential challenges that may arise in achieving nameplate capacity as previously outlined in
the EFS. This was largely due to the potential for less continuity of mineralisation and leachability. As a
result of the Honeymoon Review, Boss withdrew the EFS after identifying:
• less continuity of higher-grade mineralisation, with mineralisation occurring in more discrete
pods;
• reduced overlap between mineralised lenses across stacked horizons, limiting the ability to use
the same wellfield infrastructure to access multiple horizons;
• a material proportion of MRE mineralisation occurring within or adjacent to lower-permeability
material; and
• less uranium under leach per wellfield as the wellfield design was constrained to higher-grade
mineralisation.
The Honeymoon Review did recognise an opportunity in that the Honeymoon Deposit observed extensive,
laterally continuous lower-grade mineralisation that was not expected to be economically captured under
the previous EFS wellfield design.
Boss therefore commenced the NFS, to establish a materially lower-cost approach to developing the
Honeymoon Deposit. Central to this work was assessing whether increased spacing between injector and
extraction wells could reduce wellfield development and infrastructure requirements and enable the
lower-grade mineralisation to be economically recovered.
To determine the technical and economic viability of the wider-spaced wellfield design, Boss undertook a
comprehensive, multidisciplinary program of work, including:
• an updated MRE, reported and classified in accordance with the JORC Code (2012), supported
by accelerated delineation drilling and increased drill density;
• development of updated deposit-wide geological and permeability models;
• hydrogeological, geochemical and geometallurgical studies;
• analysis of extensive historical and recent operating data and wellfield performance;
• development and calibration of an advanced reactive transport model integrating the deposit’s
geological, hydrogeological and geochemical characteristics;
• assessment of alternative well spacings and wellfield configurations, including predicted
uranium recovery, production-solution grades and reagent consumption;
• preparation of detailed wellfield designs, development schedules and life-of-mine production
forecasts; and
• completion of the supporting engineering, capital cost, operating cost and economic evaluation
for the NFS.
The scope of the NFS was to confirm the technical, operational and economic viability of the wide-spaced
wellfield design and establish a base life-of-mine plan for the Honeymoon Deposit. Given the accelerated
timeframe and defined scope of the study, the NFS does not represent a fully optimised case, with a range
of opportunities remaining to seek to improve production, recovery, development timing and costs. The
NFS is also limited to the Honeymoon Deposit and does not include the potential future development of
Gould’s Dam or Jasons Deposit resources.
ASX: BOE OTCQX: BQSSF www.bossenergy.com Page 7
Further details of these studies are provided in the Honeymoon New Feasibility Study and Honeymoon
Mineral Resource Estimate – Technical Overview, effective August 2026 and attached to this release.
Figure 1: Location map showing the Honeymoon Operation
1.2. NFS at a Glance
The NFS defines a wide-spaced, 8-pattern, five-spot wellfield design, based on 49 m injector-to-extractor
spacing, as the base-case development scenario, with increases in spacing identified as an optimisation
opportunity. This compares with the EFS design, which adopted injector-to-extractor spacing of
approximately 30-40 m. The wide-spaced design is expected to improve operating efficiency and pregnant
leach solution (PLS) grades by:
• increasing residence time within the mineralised aquifer, allowing the lixiviant more time to
interact with the uranium mineralisation;
• increasing the distance travelled by the lixiviant, enabling more uranium mineralisation to be
contacted each time it passes through the mineralised aquifer; and
• placing a larger portion of the mineralised area under leach within each wellfield, which results
in using fewer wells, wellhouses and associated infrastructure to develop an
equivalent mineralised area.
The NFS is underpinned by an updated MRE, reported and classified in accordance with the JORC Code
(2012), an advanced RTM calibrated against actual operating performance, and feasibility-level
assessments of the wellfields, processing plant and supporting infrastructure required to deliver the life-
of-mine plan and pre-feasibility study level estimates for the WTP. It also incorporates the regulatory and
environmental approvals pathway.
ASX: BOE OTCQX: BQSSF www.bossenergy.com Page 8
The NFS life-of-mine plan is based solely on the Honeymoon MRE. However, the Honeymoon
infrastructure and wide-spaced wellfield design has potential applicability to the satellite resources of
Jasons Deposit and Gould’s Dam. Studies are underway to determine the most economical way to
leverage these resources to extend the life-of-mine plan and increase annual production beyond that
presented in the Honeymoon-only NFS.
Table 1: Honeymoon NFS at a glance summary of NFS parameters
Honeymoon NFS Parameter Unit NFS outcome
MRE
Honeymoon Mineral Resource Mlb U₃O₈ 20.8
Indicated / Inferred Mineral Resource % 66 / 34
Within / Outside ML6109 % 87 / 13
Production1
Mine total extraction Mlb U₃O₈ 14.5
Mine total drummed Mlb U₃O₈ 13.8
Indicated / Inferred Drummed % 65 / 35
Within / Outside ML6109 % 85 / 15
Maximum annual drummed production Mlb U₃O₈ 1.9
Life-of-mine duration years 9
Wellfields
Total wellfields (including existing) # 59
Total wells (including existing) # 1,340
Average active wellfields # 16
Wellfield recovery % 90
Selected injector-to-extractor spacing m 49
Long-term uranium price assumption US$/lb U₃O₈ 90
Cost
C1 Cost (to 2034) 2
$/lb U₃O₈ 50 (US$35)
AISC (to 2034) 2
$/lb U₃O₈ 79 (US$55)
Sale price3
less AISC (to 2034) $/lb U₃O₈ 50 (US$35)
Additional enabling capital A$M 58
1 This production target must be read in conjunction with the cautionary statement on page 1 of this announcement, which includes that “there is a
low level of geological confidence associated with Inferred Mineral Resources and there is no certainty that further exploration work will result in the
determination of Indicated Mineral Resources or that the production target itself will be realised”.
2
Cost average based on weighted average cost from 2027 to 2034. 2035 not included as costs are considered not meaningful.
3 Sale Price based on US$90/lb uranium price and AUD:USD of 0.70.
ASX: BOE OTCQX: BQSSF www.bossenergy.com Page 9
Refer to Section 12 of the New Feasibility Study attached to this announcement for the material
assumptions underpinning the production targets and forecast financial information, as required by ASX
Listing Rules 5.16.1 and 5.17.1.
Figure 2: Image showing continuous mineralisation of the Honeymoon Deposit with outlines of the current wellfields
ASX: BOE OTCQX: BQSSF www.bossenergy.com Page 10
2. Honeymoon Deposit Mineral Resource Overview
The following section summarises the material information relevant to the Honeymoon Deposit
(Honeymoon) MRE, in accordance with ASX Listing Rule 5.8.1. The MRE covers the Honeymoon Deposit
only and excludes the Jasons Deposit and Gould’s Dam resources. Further information is referred to the
attached Honeymoon MRE Technical Overview and JORC Code Table 1, which is included in Appendix 1 of
the Honeymoon MRE Technical Overview.
2.1. Summary
The updated Honeymoon MRE was prepared by RSC Global Pty Ltd (RSC) and is effective 30 June 2026.
The estimate comprises 21.4 Mt @ 440 ppm U₃O₈ for 20.8 Mlbs U₃O₈ metal. It comprises 66% Indicated
and 34% Inferred Mineral Resources by U3O8 metal. Approximately 87% of uranium is located within
Mining Lease 6109, with the balance located on the Company’s exploration licence EL6081.
Table 2: Honeymoon in-situ MRE (effective 30 June 2026)
Resource Classification
Grade Metal
Mt ppm U3O8 Kt U3O8 Mlbs U3O8
Indicated 12.1 510 6.2 13.7
Inferred 9.3 350 3.2 7.1
TOTAL 21.4 440 9.4 20.8
Notes:
The MRE is classified in accordance with the JORC Code (2012)7
.
The Mineral Resource database has a cut-off date of 31 December 2025.
The effective date of the MRE is 30 June 2026.
The MRE is reported at an in-situ cut-off of 100 ppm U3O8. A grade-thickness (GT) cut-off of GT≥400 m.ppm U3O8 was applied selectively in border
areas of the MRE.
Only the recoverable portion of blocks ≥100 ppm U3O8 is reported.
The Mineral Resource is constrained to an ISR-amenable permeability threshold of KSDR≥100 mD.
The Mineral Resource is mainly based on equivalent U3O8 (eU3O8), without adjusting for localised radiometric disequilibrium effects.
The MRE is reported net of depletion from the Honeymoon in-situ recovery (ISR) extraction of 3.3 Mlbs U3O8 (1.5 Kt U3O8) as of 30 June 2026 by
subtraction of extracted metal tonnes from Indicated Resource metal tonnes.
The MRE is reported on an in-situ tonnes basis.
The MRE is rounded to reflect the level of confidence in the estimate at the time of reporting.
Totals may vary due to rounding.
The MRE is reported both within the Honeymoon ML6109 license and outside in EL6081 license.
A substantial program of work has been completed to improve the geological understanding of the
Honeymoon deposit and increase confidence in the MRE. This included significantly increasing drilling and
data coverage, reviewing and validating historical drilling information, refining the geological and
mineralisation interpretations, and adopting an updated resource estimation approach that incorporates
permeability and other factors relevant to ISR extractability.
The updated Honeymoon MRE (at a 100 ppm U3O8 cut-off and depleted as of 30 June 2026) represents a
decrease in metal of 15.1 Mlbs U3O8 (-42%), with an average grade reduction of 220 ppm U3O8 (-33%)
compared to the 2019 MRE (at a 250 ppm U3O8 cut-off and depleted through to 2019) (Table 3). This
reflects significant new data, tighter geological domaining, depletion and the application of ISR-specific
7 Joint Ore Reserves Committee (JORC). (2012). Australasian Code for Reporting of Exploration Results, Mineral Resources, and Ore Reserves (The JORC
Code). The Joint Ore Reserves Committee of The Australasian Institute of Mining and Metallurgy, Australian Institute of Geoscientists, and Minerals
Council of Australia, 2012.
ASX: BOE OTCQX: BQSSF www.bossenergy.com Page 11
extractability and reasonable prospects of eventual economic extraction (RPEEE) criteria, including
permeability constraints partially offset by a reduction in cut-off grade from 250 ppm to 100 ppm. On a
like-for-like basis, compared with the 2019 MRE, at a 250 ppm U3O8 cut-off and without accounting for
depletion, the tonnage has decreased by 68%, U3O8 metal has decreased by 63%, and the U3O8 grade has
increased by 16% (Table 4).
2.2. Data and Deposit Understanding
The updated Honeymoon Deposit MRE reflects a substantial improvement in the geological and
hydrogeological understanding of the Honeymoon Deposit since the previous MRE completed in 2019.
Key advancements include:
• completion of an additional 685 drillholes for approximately 86,670 m of drilling within the MRE
model area;
• a comprehensive review and quality ranking of prompt fission neutron (PFN) data;
• updated geological interpretations incorporating the expanded drilling database and improved
understanding of mineralisation controls within the Yarramba palaeovalley system;
• development of deposit-wide permeability models using downhole Nuclear Magnetic
Resonance (NMR) data to better define permeable domains relevant to ISR mining; and
• integration of commercial ISR production performance data, providing direct calibration of
geological, hydrogeological and recovery assumptions to actual observed operating.
The data cut-off for input into the MRE was drilling completed up to 31 December 2025. Subsequent
drilling data will be included in future MRE updates and otherwise incorporated into detailed wellfield
design and operational planning as well as further optimisation of the LOM plan.
Figure 3: Image showing drilling completed since 2019 informing the new Mineral Resource. This represents a 34% increase in
drill metres
ASX: BOE OTCQX: BQSSF www.bossenergy.com Page 12
2.3. Geology and Geological Interpretation
Honeymoon is a sandstone-hosted palaeovalley uranium deposit within the Yarramba palaeovalley.
Mineralisation is predominantly hosted in permeable sands of the Eyre Formation at depths of
~80–120 m, and occurs as a series of pods and tabular bodies controlled by redox interfaces, permeability
contrasts, and the geometry of the palaeovalley. Geological interpretation is based on the distribution
and continuity of mineralised sands across the lower and upper Eyre Formation, with mineralisation
predominantly hosted in the basal aquifer and locally associated with roll-front systems and fault
structures. The mineralisation is controlled by localised redox interfaces and permeability contrasts within
the host sediments.
2.4. Drilling Techniques
Drilling at Honeymoon has been undertaken using rotary mud, diamond core, sonic and aircore methods,
with rotary mud drilling comprising 97% of the dataset used for the MRE. The MRE incorporates drilling
data available as of 31 December 2025, with drill spacing ranging from 5–40 m at Honeymoon, 10–60 m
at East Kalkaroo, 20–100 m at Central Kalkaroo and 20–150 m at Brooks Dam.
2.5. Sampling and Analytical Data
Uranium grades are derived principally from calibrated downhole gamma logging, which measures
radiometric response as a proxy for equivalent uranium grade (eU₃O₈), supplemented by PFN logging,
which measures uranium content directly (pU₃O₈). PFN data were quality-ranked, subject to a 250 ppm
U₃O₈ detection limit, and validated against chemical assays from sonic drill core. NMR and induction
logging provide supporting porosity, permeability and lithological data. As ~99% of the MRE data are
derived from equivalent uranium grades, the associated uncertainty was considered in classification and
precludes classification as Measured Mineral resources.
2.6. Resource Estimation Methodology
The MRE is based predominantly on uranium grades derived from downhole gamma and PFN logging.
Grade estimation was constrained to the Eyre Formation using geological and permeability models
developed from downhole geophysical data, supported by drill-chip logging and diamond and sonic core
observations. NMR-derived permeability data were used to distinguish permeable and impermeable
domains, applying a 100 mD permeability threshold.
Four geographical estimation domains were defined at Brooks Dam, Honeymoon, Central Kalkaroo and
East Kalkaroo to reflect differences in geological setting and grade distribution. The U3O8 estimation
domains were derived by intersecting the Eyre Formation layer with the permeable unit of the
permeability model, and with the four geographical domains. The lateral extent of the estimation domains
was limited by an area delineated by an 80-m radius buffer around drillholes with grade-thickness (GT)
≥1,000 m.ppm U3O8 for the entire Eyre Formation. The choice of 80 m as an extrapolation distance is
consistent with areas of larger drill spacing at Brooks Dam (up to 150 m) and Central Kalkaroo (up to 100
m), and is supported by variographic ranges between 60 m and 250 m across the