December 2024 Quarterly Results Presentation
Released
Released
Announcement PDF
A global multi-mine Uranium producer
Positioned to benefit from a rising Uranium market
December 2024 Quarterly Results
29 January 2025
ASX: BOE | OTCQX: BQSSF
bossenergy.com
Boss Energy remains on track to deliver 850Klbs in FY2025
Highlights
Key ramp up
milestones delivered
Strong Financial
Position
Further ramp up
and growth
initiatives underway
• 137,084lbs of U3O8 drummed (up 53%
from September quarter) and
215,319lbs IX production (up 96%)
•
•
Remain on track to deliver 850k lbs
of U3O8 drummed in FY2025
•
Wellfield 3 commissioned and
available for use
•
Mineral Resource update for Jasons
and Goulds in Q3 FY25
•
Alta Mesa expected to reach full
operational capacity of 1.5M lbs of
U3O8 a year by 2026
•
Progressing initiatives to further
derisk production ramp up
• NIMCIX column 3 ramping up; Columns
1 and 2 operating at nameplate
capacity
• Final commissioning of Kiln 2
completed; Now operating
•
Recorded 200,000lbs sales in
December quarter at a realised price
of USD77.5/lb
•
Continued disciplined approach to
contracting with ~85% of
Honeymoon product remaining
uncontracted
• Commercial production declared,
effective 1 January 2025
• Alta Mesa’s second IX circuit planned to
commence by March 2025 and the
third IX circuit planned to be online by
end of CY2025
Boss Energy | A global multi-mine Uranium producer
$252 million in cash and liquid assets,
representing 57 per cent of capital
raised. Of this, $65 million is held in
cash
•
2H FY25 C1 cost guidance set at
$37-41/lb (USD $23-25/lb)
2
Continued strong growth in quarterly production
Production Results
Honeymoon Quarterly Production
lbs
250,000
• Strong quarter on quarter growth in IX production (96%) and U3O8
drummed (53%)
96%1
growth
200,000
• Key milestones delivered during quarter included:
150,000
92%1
Commissioning of Kiln 2 is finalised
o
Final installation and commissioning of NIMIX Column 3
o
Preparation and readiness of Wellfield 3
• Production was impacted in October with the abnormal weather event
which affected power supply to these regions
growth
100,000
o
• Production was also impacted by slight time delays in commissioning and
tuning of Kiln 2. This explains the variance in IX production and U3O8
drummed at the end of December quarter
50,000
0
4Q24
1Q25
IX Production
2Q25
U3O8 Drummed
Notes:
1. Growth reflects growth in IX production
Boss Energy | A global multi-mine Uranium producer
3
Key milestones and run rate already achieved - derisking delivery of 850Klbs
Production Ramp Up
Honeymoon daily 2H25 run rate (to achieve 850k lbs)
lbs
4,000
Achieved
14-27 Jan 2025
3,500
3,000
Achieved
2Q 2025
Operation of NIMCIX column 3 will increase 2QFY25
IX throughput capacity by a 50%. IX production rate
required has already been consistently achieved in
2Q FY2025, with only 2 NIMCIX columns
Operation of two kilns. From 14th until 27th January
the step-change in average daily production to
3,902lbs U3O8 demonstrates Honeymoon is already
achieving the required rate and trending upward
2,500
2,000
1,500
Wellfield 3 available for use when required.
Additional wellfields will continue to be made
available ahead of required production time.
1,000
500
0
Required average daily production for 2H25
IX Production
Boss Energy | A global multi-mine Uranium producer
NIMCIX Columns 4-6 will be installed by June 2025
U3O8 Drummed
4
Growth
Exploration focussed on increasing production rate and mine life
Exploration
“These satellite deposits have the potential to drive growth as well as enabling us to
leverage existing infrastructure and further capitalise on the opportunity presented
by growing global demand for uranium from tier-one locations”
•
•
Key activities for the quarter:
o
Completed infill drilling at for the Gould’s Dam and Jasons satellite deposit
- a number of significant intersections, including 3.25m @ 3,873 pU308
(WRM176)
o
Consultants engaged to produce a mineral resource update for the Gould’s
Dam and Jasons satellite deposits (Q3 FY2025)
o
New exploration drilling on the Cummins Dam prospect has defined a zone
of mineralisation of approximately 1km x 1km, which remains open
Key upcoming exploration activities:
o
Further drilling on the Cummins Dam prospect in Q3 FY25
o
Continue to generate exploration targets around the Honeymoon
operation, aimed at identifying high-priority targets that could represent
additional undiscovered resources
Boss Energy | A global multi-mine Uranium producer
6
Alta Mesa continues to ramp up to nameplate capacity of 1.5 million pounds
Alta Mesa
Boss Energy | A global multi-mine Uranium producer
•
On the 8th October 2024, enCore Energy Corp.
announced the grand opening celebration of the Alta
Mesa Uranium Plant with George W. Bush, the 43rd
President of the United States
•
Alta Mesa’s first IX circuit was commissioned in June
2024 with the second IX circuit planned to
commence operation in the first quarter of 2025 and
the third IX circuit planned to be online by year end
of 2025
•
Wellfield solution head grades at Alta Mesa peaked
at approximately 140 mg/l U3O8 and averaged
approximately 65 mg/l U3O8
•
Alta Mesa is ramping up to an annualised production
rate of 1.5 million pounds U3O8. Boss’ share of this
production is 30 per cent
•
Alta Mesa Project, which consists of over 200,000
acres plus the central processing plant and wellfields,
is managed by experienced uranium producer, and
partner, enCore
7
Market
Update
Boss Energy well positioned to benefit from rising Long-Term price
100
80
60
40
20
U3O8 Spot Price
May-24
May-23
May-22
May-21
May-20
May-19
May-18
May-17
May-16
May-15
May-14
May-13
May-12
May-11
May-10
May-09
During 2024 the month end spot market price fell
approximately 28% from January to December
2024. Term prices however continued to trend
upwards
120
May-08
•
The risks on the supply side with Geopolitical
concerns continue to dominate, including include
potential import bans, sanctions, transportation
issues, potential tariffs and counter tariffs
140
May-07
•
News of increasing demand from data centres,
with Amazon, Microsoft, Meta, and Google,
announcing MOUs with nuclear utilities to develop
nuclear capacity aimed at supporting data centres
160
May-06
•
Trump administration promises deregulation and
streamlined approval processes, including the
Stargate Project, a $500 billion AI infrastructure
venture
May-05
•
US$
May-04
Market Update
U3O8 Long-Term Price
Source: UxC, LLC https://www.uxc.com/
Boss Energy | A global multi-mine Uranium producer
9
Financials
Strong financial position with $252 million in cash and liquid assets
Financial Position
•
•
•
•
Balance Sheet remains robust with circa $252
million in cash and liquid investments on hand and
no debt. An increase of $6.7 million since
September quarter
Sold 200,000 lbs during the quarter at a realised
price of US$77.50
Commercial production declared will result in
production accounting from
1 January onwards
Existing cash and liquid investments will fully
support ramp up with no requirement for any
external capital or debt
Quarter ended
Unit
Sales
Lbs
December
September
200,000
200,000
Realised price
US$/lb
77.5
78.0
Revenue
US$
15,500,000
15,608,000
Cash on hand
A$ (000’s)
65,177
66,551
Inventory on hand1
A$ (000’s)
117,279
114,861
Loan receivable
A$ (000’s)
34,808
30,560
Investments and other liquid assets
A$ (000’s)
34,382
32,931
Total cash and liquid investments
A$ (000’s)
251,646
244,903
Notes: (1) Inventory includes strategic inventory and inventory on hand. Excludes inventory ‘in circuit’ e.g. IX
production
Boss Energy | A global multi-mine Uranium producer
11
Cost guidance for 2H25 indicates a high margin business competitively
positioned on the cost curve
Guidance
Cash cost expected to reduce in future years as fixed costs
are fractionalised by increased production
2H FY2025
Honeymoon Guidance1
(AUD)
(USD)2
Lbs (000’s)
625
625
Cash Cost – Fixed
$/lb
22-24
14-15
Cash Cost – Variable
$/lb
15-17
9-10
Cash Cost – Total
$/lb
37-41
23-25
Capex – Wellfields
$m
17-20
11-12
Capex – Capital Projects
$m
19-21
12-13
Capex – Other sustaining capital
$m
1-2
1-2
Capex - Total
$m
38-43
24-26
Production
Cash cost for 2H25 reflects an increase approximately inline with inflation since the EFS was completed- reinforcing
strong technical feasibility work
Wellfields capex represents cost to bring on wellfields that
are expected to come online through to the end of
FY2026. Costs also increased approximately inline with
inflation since EFS completed
Project capex represents most of the cost to complete the
Project phase which mostly represents columns 4-6. Cost
has increased mainly due to increased labour cost and
inflation
Boss Energy | A global multi-mine Uranium producer
Unit
Notes: (1) Guidance is for Honeymoon only and excludes Alta Mesa with definitions of
costs consistent with EFS. Refer to Appendix 3 for definitions (2) AUS/USD of 0.62 used
12
Appendices
Appendix 1: Quarterly Cashflow bridge
$000's
100,000
25,244
90,000
(7,545)
80,000
70,000
(967)
(9,535)
66,551
(4,341)
60,000
(3,536)
1,669
65,177
Other
Closing
Cash
(2,363)
50,000
40,000
30,000
20,000
10,000
-
Opening
Cash
Receipts
from
customers
Honeymoon
Operating
costs
Honeymoon
Wellfields
capex
Honeymoon
Capital
project
Alta Mesa
Operating
Costs
G&A
Exploration
and
investments
Notes: Other corporate costs include FX, interest income and repayment of leases
Boss Energy | A global multi-mine Uranium producer
14
Appendix 2: Physicals Summary
Honeymoon
Unit
IX Flow (total)1
m3
PLS to IX tenor
IX Recovery
IX Production (total)
1
U3O8 Drummed (total)
2Q FY25
1Q FY25
861,204
729,299
U3O8 mg/l
116
71
%
97.8
97.2
lbs
215,319
110,050
lbs
137,084
89,516
Notes:
1. Conversions: There are 1,000 litres per m3 and 0.0000022 lbs per mg.
Boss Energy | A global multi-mine Uranium producer
15
Appendix 3: Guidance definitions
Cash cost fixed: Reflects onsite processing fixed costs such as labour, insurance, camp, maintenance, laboratory, site
general and administration costs. It also includes the fixed component of other costs (e.g. power has a fixed network
connection fee)
Cash cost variable: Reflects onsite variable processing costs such as reagents and consumables, power and
transportation costs
Wellfields capex: includes drilling, casing and screening the wells, the injection and extraction pumps, the wellhouse,
the piping which connects the injection and extraction wells to the wellhouse, trunklines which connects groups of
wellfields back to the plant and first fill costs (the cost to flush and ‘charge’ the wellfield with reagents before uranium
production can begin)
Project capex: includes the EPCM / Project scope that was set out in the EFS, including the ‘Re-start’ and ‘Additional IX’
capex
Other sustaining capital: includes a range small optimisation projects to support ramp up
Boss Energy | A global multi-mine Uranium producer
16
Honeymoon and Alta Mesa Resource Tables
HONEYMOON JORC EXPLORATION TARGETS AND MINERAL RESOURCE
ALTA MESA NI 43-101 MINERAL RESOURCE ESTIMATE (2023)
The information in this Presentation relating to the Enhanced Feasibility Study (EFS) is extracted from the announcement
entitled ‘Updated Feasibility Study identifies lower costs and increased financial returns’ dated 21st June 2021. Boss Energy
confirms that all the material assumptions underpinning the production targets, and forecast financial information derived
from the production targets, continue to apply and have not materially changed. As the EFS utilises a portion of Inferred
Mineral Resources, the ASX Listing Rules (Listing Rules) require a cautionary statement to be included in this Presentation. The
EFS is based on a Mineral Resources Estimate in accordance with the JORC 2012 guidelines (ASX: 149% Increase in Measured and
Indicated Resources at Honeymoon date 25 February 2019). The Company advises that the EFS uses a portion of Inferred
Resources; in the first 3 years (less than 1%), in the first 5 years (5%) and over the 11-year life of mine (19%). The Company
confirms that the use of Inferred Resources is not a determining factor to the Honeymoon Project’s economic viability. There
is a low level of geological confidence associated with Inferred Resources and there is no certainty that further exploration or
evaluation work will result in the determination of Indicated Resources or that the production targets reported in this
announcement will be realised.
For the purposes of Listing Rule 5.12, Boss Energy cautions that the mineral resources for the Alta Mesa Project are not
reported in accordance with the JORC Code. The mineral resource estimate at Alta Mesa is a foreign estimate prepared in
accordance with Canadian National Instrument 43-101. A competent person has not done sufficient work to classify the
foreign estimate as a mineral resource in accordance with the JORC Code, and it is uncertain whether further evaluation and
exploration will result in an estimate reportable under the JORC Code. Please refer to Annexure A for additional technical
information relating to the foreign estimate.
The mineral resource estimate and exploration target in this Presentation were reported by the Company in accordance with
Listing Rules 5.8 and 5.7 (respectively) on 25 February 2019 and 25 March 2019, respectively. The Company confirms it is not
aware of any new information or data that materially affects the information included in the previous announcement and
that all material assumptions and technical parameters underpinning the estimates in the previous announcement continue
to apply and have not materially changed. In relation to the exploration target, this does not include areas of the existing
mineral resource and the potential quantity and grade reported are conceptual only in nature. Insufficient exploration has
been conducted to estimate a mineral resource and it is uncertain whether future exploration will lead to the estimation of
a mineral resource in the defined areas.
Tonnes (Mt)
Grade (%U3O8)
Contained U3O8
(Mlbs)
Measured
3.1
0.110
7.6
Indicated
18.4
0.063
25.5
The information in this Presentation and in Annexure A provided under Listing Rules 5.12.2 to 5.12.7 that relates to the
foreign estimate for the Alta Mesa Project is based on information compiled by Mr Jason Cherry, and is an accurate
representation of the available data and studies for the Alta Mesa Project.
Mr Cherry is a member of the Australian Institute of Geoscientists (AIG) and has sufficient experience that is relevant to the
style of mineralisation and type of deposit under consideration, and to the activity being undertaken to qualify as a
Competent Person, as defined in the JORC 2012 edition of the “Australasian Code for Reporting of Mineral Resources and Ore
Reserves”. Mr Cherry has 17 years’ experience and is a full-time employee as Geology Manager for Boss Energy Ltd. Mr
Cherry consents to the inclusion in this Presentation of the matters based on this information in the form and context in
which they appear.
Resource
Category
Tonnes
(‘000)
Grade (%U3O8)
Contained
U3O8
(‘000 lbs)
Within existing
wellfields
Measured
54
0.152
164
Alta Mesa
Indicated
1,397
0.106
2,959
Mesteña Grande
Indicated
119
0.120
287
1,570
0.109
3,410
Total Measured &
Indicated Mineral
Resources
Alta Mesa
Inferred
1,263
0.126
3,192
Inferred
5,733
0.119
13,601
6,996
0.120
16,793¹
Inferred
30.9
0.057
38.5
Mesteña Grande
Total
52.4
0.062
71.6
Total Inferred Mineral
Resource
Boss Energy | A global multi-mine Uranium producer
17
Disclaimer and Important Notices
IMPORTANT: You must read the following before continuing.
This investor presentation (“Presentation”) has been prepared by Boss Energy Limited (ACN 116 834 336) (Boss Energy or
Company). NOT INVESTMENT ADVICE
This Presentation does not constitute in any way an offer or invitation to subscribe for securities in Boss Energy pursuant to the
Corporations Act 2001 (Cth) and has not been lodged with the Australian Securities and Investment Commission.
This Presentation does not constitute investment advice and has been prepared by Boss Energy without taking into account the
recipient’s investment objectives, financial circumstances or particular needs. Each recipient must make his/her own independent
assessment and investigation of Boss Energy and its business and assets when deciding if an investment is appropriate and should
not rely on any statement or the adequacy and accuracy of any information. This Presentation is in summary form and does not
purpose to be exhaustive. This Presentation should be read in conjunction with Boss Energy’s periodic and continuous disclosure
announcements lodged with the Australian Securities Exchange, which are available to download at www.asx.com.au.
Boss Energy makes no representation or warranty (either expressed or implied) as to the accuracy, reliability or completeness of
the Information. Boss Energy and its directors, employees, agents and consultants shall have no liability (including liability to any
person by reason of negligence or negligent misstatement) for any statements, opinions, information or matters (express or
implied) arising out of, contained in or derived from, or for any omissions from the Presentation, except liability under statute that
can not be excluded.
FORWARD LOOKING STATEMENTS
All dollar amounts are in Australian dollars unless otherwise indicated. This announcement may contain certain statements and
projections provided by or on behalf of Boss Energy Limited with respect to the anticipated future undertakings. These forwardlooking statements reflect various assumptions by or on behalf of Boss Energy. Accordingly, these statements are subject to
significant business, economic and competitive uncertainties and contingencies associated with the mining industry which may be
beyond the control of Boss Energy which could cause actual results or trends to differ materially, including but not limited to price
and currency fluctuations, geotechnical factors, drilling and production results, development progress, operating results, reserve
estimates, legislative, fiscal and regulatory developments, economic and financial market conditions in various countries, approvals
and cost estimates, environmental risks, ability to meet funding requirements, share price volatility. Accordingly, there can be no
assurance that such statements and projections will be realised. Boss Energy makes no representations as to the accuracy or
completeness of any such statement of projections or that any forecasts will be achieved. Additionally, Boss Energy makes no
representation or warranty, express or implied, in relation to, and no responsibility or liability (whether for negligence, under
statute or otherwise) is or will be accepted by Boss Energy or by any of their respective officers, directors, shareholders, partners,
employees, or advisers as to or in relation to the accuracy or completeness of the information, statements, opinions or matters
(express or implied) arising out of, contained in or derived from this announcement or any omission from this announcement or of
any other written or oral information or opinions provided now or in the future to any interested party or its advisers. In furnishing
this announcement, Boss Energy undertakes no obligation to provide any additional or updated information whether as a result of
new information, future events or results or otherwise. Nothing in this material should be construed as either an offer to sell or a
solicitation of an offer to buy or sell securities. It does not include all available information and should not be used in isolation as a
basis to invest in Boss Energy.
The information in this document relating to the Enhanced Feasibility Study(“EFS”) is extracted from the announcement entitled
‘Updated Feasibility Study identifies lower costs and increased financial returns’ dated 21 June 2021. Boss Energy confirms that
all the material assumptions underpinning the production targets, and forecast financial information derived from the production
targets, continue to apply and have not materially changed.
The Company advises that the EFS uses a portion of Inferred Resources in the first 3 years (less than 1%), in the first 5 years(5%)
and over the 11-year life of mine(19%). The Company confirms that the use of Inferred Resources is not a determining factor to the
Honeymoon Project’s economic viability. There is a low level of geological confidence associated with Inferred Resources and there
is no certainty that further exploration or evaluation work will result in the determination of Indicated Resources or that the
production targets reported in this announcement will be realised.
REFERENCE TO PREVIOUS ASX ANNOUNCEMENTS
The mineral resource estimate and exploration target in this announcement were reported by the Company in accordance with
listing rules 5.8 and 5.7(respectively)on 25 February 2019 and 25 March 2019, respectively. The Company confirms it is not aware
of any new information or data that materially affects the information included in the previous announcement and that all material
assumptions and technical parameters underpinning the estimates in the previous announcement continue to apply and have not
materially changed.
In relation to the exploration target, this does not include areas of the existing mineral resource and the potential quantity and
grade reported are conceptual only in nature. Insufficient exploration has been conducted to estimate a mineral resource and it is
uncertain whether future exploration will lead to the estimation of a mineral resource in the defined areas.
EFFECT OF ROUNDING
A number of figures, amounts, percentages, estimates, calculations of value and fractions in this Presentation are subject to the
effect of rounding. Accordingly, the actual calculation of these figures may differ from the figures set out in this Presentation.
PAST PERFORMANCE
Past performance information, including past share price performance of Boss Energy and pro forma financial information, given in
this Presentation is given for illustrative purposes only and should not be relied upon as (and is not) an indication of Boss Energy’s
(or anyone else’s) views on Boss Energy’s future financial performance or condition. Past performance of Boss Energy cannot be
relied upon as an indicator of (and provides no guidance as to) the future performance of Boss Energy. Nothing contained in this
Presentation nor any information made available to you is, or shall be relied upon as a promise, representation, warranty or
guarantee, whether as to the past, present or future.
JORC CODE
It is a requirement of the Listing Rules that the reporting of ore reserves and mineral resources in Australia comply with the Joint
Ore Reserves Committee’s Australasian Code for Reporting of Mineral Resources and Ore Reserves ("JORC Code"). Investors
outside Australia should note that while ore reserve and mineral resource estimates of the Company in this Presentation comply
with the JORC Code (such JORC Code-compliant ore reserves and mineral resources being "Ore Reserves" and "Mineral
Resources" respectively), they may not comply with the relevant guidelines in other countries and, in particular, do not comply
with (i) National Instrument 43-101 (Standards of Disclosure for Mineral Projects) of the Canadian Securities Administrators (the
"Canadian NI 43-101 Standards"); or (ii) Item 1300 of Regulation S-K, which governs disclosures of mineral reserves in
registration statements filed with the SEC. Information contained in this document describing mineral deposits may not be
comparable to similar information made public by companies subject to the reporting and disclosure requirements of Canadian or
US securities laws.
This ASX announcement was approved and authorised by the CEO on behalf of the Board of Boss Energy.
As the EFS utilises a portion of Inferred Mineral Resources, the ASX Listing Rules require a cautionary statement to be included in
this presentation. The EFS is based on a Mineral Resources Estimate in accordance with JORC guidelines 2012 (ASX:149% Increase
in Measured and Indicated Resources at Honeymoon dated 25 February 2019).
Boss Energy | A global multi-mine Uranium producer
18
Boss Energy Limited
December 2024 Quarterly
Results
Keep in touch
+61 (8) 6263 4494
boss@bossenergy.com
ASX: BOE | OTCQX: BQSSF
Share your feedback
Discover