Honeymoon reaches major milestone - wellfields complete
Released
Released
Announcement PDF
ASX Release 28 June 2023
Honeymoon Uranium Project, South Australia
Honeymoon reaches major milestone
with wellfield construction complete
Honeymoon on track for first production in December quarter
Key Points
•
Drilling, casing and screening of the first three wellfields is complete
•
Startup wellfield installation is complete, flushing will commence soon
•
Water treatment plants are nearing completion
•
Committed expenditure now totals 77% of total projected spend and on budget
•
Discussions concerning long-term offtake contracts advancing with potential customers
•
Spot uranium price increases to US$56/lb, valuing Boss’ strategic U3O8 stockpile at US$70m
Boss Energy Limited (ASX: BOE; OTCQX: BQSSF) is pleased to announce a pivotal achievement in the restart
of the Honeymoon uranium project in South Australia, with the first wellfield complete, and related gypsum
pond and water treatment plants nearing completion.
Completion of this milestone ensures Honeymoon remains on track for production in the December
quarter, 2023.
Preparatory work to commence flushing the startup wellfields is now underway.
Boss Managing Director Duncan Craib said: “The project development is proceeding to plan and remains on
time and on budget as we move towards the restart of Honeymoon.
“Our timing is looking ideal, with the uranium market continuing to tighten and the spot price moving up.”
“Boss remains fully-funded through to production, with cash on hand of A$103M 1 and a strategic uranium
stockpile valued at A$105M 2 (US$70M) based on current spot prices. The Company has no long-term debt".
1 As at 31 March 2023 (excluding 100% cash backed environmental bond of approximately A$9M)
2 Strategic uranium stockpile valued at A$105M based on a spot U O price of US$56/lb and an exchange rate of A$1:US$0.67
3 8
FOR FURTHER INFORMATION PLEASE CONTACT:
Boss Energy Limited
ABN 38 116 834 336
Duncan Craib - Managing Director/ CEO
+61 (08) 6263 4494
ASX: BOE
OTCQX: BQSSF
Level 1, 420 Hay Street, Subiaco
Western Australia 6008
Paul Armstrong – Public Relations
+61 (08) 9388 1474
www.bossenergy.com
@Boss_Energy
Mr Craib said committed expenditure now totals 77 per cent, or A$81.5M, of the budgeted ~A$105.4M
CAPEX.
All critical path items remain on track for delivery in line with the project schedule. More than 135
procurement packages have been issued. The packages awarded to date are in line with the cost estimates
contained in the front-end engineering design (FEED) released to the ASX on 31 March 2022.
Wellfield Construction
The project reached a key point in its redevelopment with completion of construction of the three startup
wellfields. This comprises 86 drilled and cased new production wells and 31 recompletions of existing wells.
Pressure testing and line flushing of the first wellfield has been completed and the liquid disposal line (3km)
and associated pumps and instrumentation have been commissioned.
The next stage is to run structured pumping tests. The purpose of this work is to ensure the pump setpoints are correct, and that the wells are hydraulically connected to one another in the orebody.
This will pave the way to start wellfield flushing and commissioning.
Ground water extraction and construction of the new raw water system is also on target to begin delivering
to the processing plant in coming weeks. The necessary reagent areas are in the final stages of preparation
for receiving their first fill.
All significant procurement items have been delivered and installed, raw water supply and liquid disposal
lines (180mm poly pipe of approximately 5,800 metres) have been welded, completed and ready for use.
Image 1: Wellfield electrical, instrumentation, and piping materials has been installed
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
@Boss_Energy
Gypsum Pond
Installation of lining material for the 25,000-ton gypsum pond is nearing completion for full operational
use.
Image 2: 25,000-ton gypsum pond lining being installed
250m3 /hour RO Plant
The 250m3 /hour RO plant mechanicals are installed, with electrical and final piping nearing completion.
The RO pant consists of 6 containers of filters, pumps and reverse osmosis tubes with associated chemical
dosing systems.
Image 3: 250m3 /hour RO Plant
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
@Boss_Energy
This ASX announcement was approved and authorised by the Board of Boss Energy Limited.
For further information, contact:
Duncan Craib
Chief Executive Officer
P: +61 (8) 6263 4494
E: boss@bossenergy.com
For media enquiries, contact:
Paul Armstrong
Read Corporate
P: +61 (8) 9388 1474
E: info@readcorporate.com
Reference to previous ASX announcements
In relation to the results of the Enhanced Feasibility Study announced on 21 June 2021, the Company
confirms that all material assumptions underpinning the production target and forecast financial
information included in that announcement continue to apply and have not materially changed.
Forward-Looking Statements
This announcement includes forward-looking statements. These forward-looking statements are based on
the Company’s expectations and beliefs concerning future events. Forward-looking statements are
necessarily subject to risks, uncertainties, and other factors, many of which are outside the control of Boss
Energy, which could cause actual results to differ materially from such statements. Boss Energy makes no
undertaking to subsequently update or revise the forward-looking statements made in this announcement,
to reflect the circumstances or events after the date of this announcement.
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
@Boss_Energy
Share your feedback
Discover