Quarterly Activities Report - June 2025
Released
Released
Announcement PDF
ASX Release 28 July 2025
June 2025 Quarterly Report
Boss beats FY25 production and cost guidance
Successful ramp-up takes total production since start of commissioning to 1M lbs
Highlights
Honeymoon Uranium Project, South Australia (Boss 100%)
• Strong quarterly operational performance, with 349,188 lbs of U3O8 drummed (up 18% from
March quarter) and 396,346 lbs IX production (up 60%)
• Average realised price of A$109/lb (US$71/lb) with cash received for 100,000 lbs; Boss
leveraged its strong balance sheet and contracting position to ensure a strong realised price
• C1 cost from drummed uranium for the quarter of A$36/lb (US$23/lb) is below second-half
FY25 guidance of A$37-41/lb (US$23-25/lb)
• FY25 production totalled 872,607 lbs U3O8; Second-half C1 cost was A$35/lb (US$23/lb)
• Assembly of the NIMCIX columns 4-6 practically complete; Final pipework is being installed,
with commissioning to begin in the next quarter
• Wellfield 4 complete and in flushing with wellfield 5 to be complete and commissioned next
quarter
Alta Mesa Uranium Operation, South Texas (Boss 30%)
•
Total production of 203,798 lbs of U3O8 (100% basis); Total pro rata share of inventory received
of 43,846 lbs U3O8
• Recent management changes and operational efficiencies have resulted in increased uranium
extraction and lower costs
Corporate
• Robust Balance Sheet with A$224M of cash and liquid assets on hand; zero debt
• Drummed inventory on hand of 1.41M lbs U3O8 (excluding loan receivables)
• Two highly experienced Directors were appointed to the Company’s Board - Ms Joanne Palmer
and Ms Caroline Keats, bolstering its capabilities
• Subsequent to quarter end, the Company announced that Managing Director & CEO Mr
Duncan Craib would step down effective 30 September 2025, and at the Board’s request,
remain as a Non-Executive Director from 1 January 2026. COO Mr Matt Dusci will be appointed
Managing Director & CEO from 1 October 2025.
Boss’ June quarterly conference call will be held today at 9am AWST (11am AEST). The call can be
accessed at https://loghic.eventsair.com/105665/672155/Site/Register
FOR FURTHER INFORMATION PLEASE CONTACT:
Boss Energy Limited
ABN 38 116 834 336
Duncan Craib - Managing Director/ CEO
+61 (08) 6263 4494
ASX: BOE
OTCQX: BQSSF
Level 1, 420 Hay Street, Subiaco
Western Australia 600
Paul Armstrong – Public Relations
+61 (08) 9388 1474
www.bossenergy.com
@Boss_Energy
Boss Energy Limited (ASX: BOE; OTCQX: BQSSF) (“Boss” or the “Company”) is pleased to report on another
strong quarter which culminated in the Company beating FY25 production and cost guidance at its
Honeymoon uranium project in South Australia.
The highly successful ramp up at Honeymoon also resulted in the project’s total production since
commissioning passing the major milestone of 1M lbs last week.
Boss Managing Director Duncan Craib said:
“To beat our first year of production and cost guidance and then hit the 1M lbs milestone are huge
achievements and reflect the skills and dedication of our team. On behalf of the Board, I would like to thank
them for their commitment and hard work.
Our margins are strong, our balance is extremely robust and we are perfectly positioned to capitalise on an
upturn in the uranium market, which we believe is inevitable as demand rises on the back of the nuclear power
resurgence.
With production on track to ramp up significantly over FY26, we will see the financial strengths of Honeymoon
come to the fore with cashflow set to increase substantially. In parallel with the ongoing ramp-up, we are
driving our exploration program forward with the aim of creating value by establishing new resources. This
will see updated resource estimates for Gould’s Dam and Jason’s this quarter. There will also be more work
done to continue growing Gould’s Dam and progressing greenfield targets”.
Honeymoon Safety Performance
The Total Reportable Injury Frequency Rate (“TRIFR”1) was 12.8 at the end of the quarter. Given TRIFR is
calculated per million hours worked, and the comparatively low hours worked at Honeymoon, a small
number of incidents have had, and continue to have, a significant impact on the TRIFR result. During the
quarter, there was one Lost Time Incident (LTI), occurring in April. There remains a heightened focus on
safety and improvement in our incident/hazard reporting and action tracking.
Table 1: Honeymoon TRIFR (12-month moving average)
Quarter ended
TRIFR
Q4 FY25
Q3 FY25
Q2 FY25
Q1 FY25
12.8
9.9
4.4
2.1
Honeymoon Production Results
Production continued to ramp up during the quarter, with 349,188 lbs U3O8 drummed and 396,346 lbs IX
production. This represents a growth of 53,369 lbs (18 per cent) in U3O8 drummed and 149,477 lbs (60 per
cent) in IX production compared to the previous quarter. The growth in IX production was a result of doubling
the flow from the previous quarter, utilising the third NIMCIX column, as well as three wellfields being
operational for the whole quarter. The additional flow was partially offset by the expected decrease in PLS
tenor from wellfields 1 and 2.
1 Total Reportable Injury Frequency Rate (TRIFR) measures the rate of restricted work injuries (RWIs), medical treated injuries (MTI)
and lost time injuries (LTIs) that occur per million hours worked.
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
Page 2
Table 2: Operational physicals
Quarter ended
Q4 FY25
Q3 FY25
Q2 FY25
Wellfields online
3
3
2
1
3
NIMCIX Columns online
IX Flow (total)1
3
3
2
1
2,102,310
1,088,704
861,204
729,299
3
4,781,518
(U3O8 mg/l)
88
108
116
71
95
IX Recovery
(%)
96.9
95.5
97.8
97.2
96.8
IX Production (total)1
(lbs)
396,346
246,869
215,319
110,050
968,585
U3O8 Drummed (total)
(lbs)
349,188
295,819
137,084
89,516
871,607
PLS to IX tenor
Unit
2
(m3)
Q1 FY25
FY25 Total
Notes: (1) Conversions: There are 1,000 litres per m3 and 0.00000220462 lbs per mg. (2) Tenors currently being
extracted exceed the average tenors forecast in the Enhanced Feasibility Study and should not be extrapolated across
the LOM.
Total production IX production for FY25 was 969K lbs, with U3O8 drummed of 872K lbs U3O8.
Honeymoon Construction Activities
Construction activities continued in earnest during the quarter, with the assembly of the NIMCIX columns 46 practically complete, along with the associated steel structure. Final pipework is being installed, with
commissioning to begin in the next quarter.
Along with the process plant construction, wellfield construction continues with wellfield 4 complete and in
flushing, and wellfield 5 to be complete and commissioned in Q3 CY25. East Kalkaroo trunkline materials are
on site, with construction to begin in August.
Figure 1: NIMCIX columns 4 to 6 installed
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
Page 3
Exploration Activities
Exploration in the quarter focused on the Lake Constance target area, 40 km south-west of the Gould’s Dam
resource. The Lake Constance target occupies an inferred NE-SW trending palaeochannel that was drilled in
the early 1970s with several radioactive intersections recorded. These were not followed up at the time,
apparently owing in part to the focus on the Gould’s Dam discovery.
A total of thirty-three aircore holes were drilled for 3,770m. The use of aircore drilling was designed to reduce
environmental impact and drilling costs at the same time as delivering better quality samples for geological
analysis. Another innovation was the use of a driller-operated gamma radiation probe for detecting uranium
downhole. The program was successfully completed and results are awaited of analysis of samples from
several radiometrically anomalous intervals.
AMC consultants progressed MRE updates for Gould’s Dam and Jason’s during the quarter, and updated
resource estimates will be delivered in this coming quarter.
Exploration activities for the next quarter will focus on further expansions to the resource at Gould’s Dam,
as well as defining and progressing greenfield exploration targets with passive seismic surveys and further
aircore drilling.
Balance Sheet
As at 30 June 2025, Boss had no debt and A$224.0M of liquid assets (being cash, liquid investments and
physical drummed uranium), a decrease of A$5.2M from the March Quarter primarily driven by sales of 100K
lbs being materially lower than production of 349K lbs. Boss’ under-contracted sales book and strong balance
sheet enables it to strategically step away from the market when it believes that the uranium price does not
reflect long term fundamental value. Boss also recorded positive ‘marked to market’ movements in listed
investments during the quarter.
Table 3: Cash, inventory and investments
A$000’s
Q4 FY25
Q3 FY25
Q2 FY25
Q1 FY25
Cash on hand
36,530
63,773
65,177
66,551
Investments and other liquid assets
51,637
42,386
34,382
32,931
1
Inventory on hand
120,009
106,925
117,279
114,861
Loan receivable
15,819
16,140
34,808
30,560
Total cash and liquid investments
223,995
229,224
251,646
Notes: (1) Inventory on hand at 30 June 2025 comprises drummed U3O8 and work in progress
244,903
Unrestricted cash and cash equivalents stood at A$36.5M (which excludes a fully cash-backed environmental
bond of A$13.5M) with a further A$187.5M in liquid investments (including inventory).
The waterfall chart below highlights the June quarter movements in cash.
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
Page 4
Figure 2: June Q4 FY25 cash (A$000’s)
Notes: (1) Estimated cash balance assumes Boss sold an additional 293,034lbs U3O8 at US$70 per lb at AUD/USD of 0.65.
For a substantial period during the quarter, Boss believed that the market price did not represent the
fundamental long term value of uranium and on this basis decided hold back inventory from sale. This is
enabled by Boss’ strategy of remaining strategically under contracted and having a strong balance sheet. If
Boss had sold all of Honeymoon and Alta Mesa production at current market prices, it would have been
cashflow positive at a Group level.
Inventory and investments (excluding cash) increased by A$22.0M during the June quarter due to:
•
Investments and other liquid assets (A$9.3M increase): Primarily reflects a ‘marked to market’
increase in the value of the investments in enCore Energy Corp (A$5.3M) and Laramide Resources
Ltd (A$2.1M) and additional investment in Laramide (A$2.0M).
•
Drummed U3O8 Inventory (A$13.1M increase): Primarily reflects an increase in drummed Uranium
produced (393,034 lbs including Alta Mesa JV).
Cash receipts
During the quarter, Boss received A$10.9M (US$7.1M) in cash, related to a sale of 100k lbs to a utility
customer.
Table 4: Cash Receipts
Key Metric
Unit
Q4 FY25
Q3 FY25
Q2 FY25
Q1 FY25
FY25 Total
Production
Sales
Loan repayment
Cash received
Average Realised price1
Inventory on hand2
lbs
lbs
lbs
US$
US$/lb
Mlbs
349,188
100,000
7,115
71.15
1.41
295,819
150,000
118,000
22,389
83.5
1.22
137,084
200,000
15,500
77.5
1.08
89,516
200,000
15,608
78.0
1.17
871,607
650,000
118,000
60,612
78.9
Notes: (1) Average realised price in Q3 includes cash received from inventory loaned (2) Inventory on hand in Q4
excludes 100K lbs inventory loaned to enCore Energy Corp which is no longer receivable in kind. Inventory on hand
from Q1-Q3 included 100K lbs inventory loaned to enCore.
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
Page 5
Honeymoon Costs
Boss has tracked favourably against guidance, recording a C1 cost of A$36/lb (US$ 23/lb). Boss provided C1
cost guidance of A$37-41/lb (US$23-25/lb) for Honeymoon as a part of the December Quarterly.
Table 5: Production and Capital Costs
Honeymoon Costs FY2025 (A$)
Unit
Cash Cost – Fixed2
$/lb
20
21
20
$/lb
16
13
15
$/lb
36
33
35
$M
7
8
14
Capex – Capital Projects
$M
7
4
10
Capex – Other sustaining capital
$M
0
0
0
Capex - Total
$M
14
12
25
Cash Cost – Variable
2
Cash Cost – Total2
Capex – Wellfields
3
Q4 FY25
Q3 FY25
2HFY25 Total
Notes: (1) Costs are for Honeymoon only with definitions consistent with EFS. Alta Mesa is not included. (2) Cash Cost
includes all mining costs, onsite processing costs, onsite general and administration costs and logistical costs. Excludes
royalties, depreciation and capital expenditure. (3) Wellfields capex includes sustaining and deferred capex.
C1 cost from drummed uranium for the quarter was A$36/lb (US$23/lb), an increase of A$3/lb as compared
to the March quarter due to an increase in reagent costs associated with an expected decline in average PLS
to IX tenor. The C1 cost for the half of A$35/lb was below guidance of A$37-41/lb as provisions for unforeseen
ramp up costs were not realised.
Wellfields and Projects Capex for the quarter were A$7M each, which were both below guidance and will
result in a carryover of ~A$15M capex into FY26.
Alta Mesa (Boss 30% / enCore Energy Corp 70% Joint Venture)
Production during the quarter from the Alta Mesa Uranium Project, a Joint Venture with enCore Energy Corp
(NASDAQ: EU; TSXV: EU) (“enCore”), totalled 203,798 lbs of U3O8 compared to the previous quarter's
production of 98K lbs (on a 100% basis). Boss received 43,846 lbs of U3O8 reflecting its 30% pro rata share of
production, an increase from the prior quarter of 29,126 lbs of U3O8.
Recent Alta Mesa Project operational highlights include:
•
Uranium capture of ending 23 June 2025, in excess of 3,000 lbs per day, peaking at 3,705 lbs on 20
June 2025;
•
Uranium capture for the first 22 days of June 2025 average 2,410 lbs of uranium per day for a total
of 53,022 lbs;
•
Uranium capture for the month of May 2025 was an average of 2,103 lbs per day; April 2025 uranium
capture was an average of 1,942 lbs per day.
As reported during the quarter by enCore, recent management changes and operational efficiencies have
improved uranium extraction rates and decreased costs. Wellfield development at the Alta Mesa Project
continued to expand as part of the ongoing ramp up strategy to advance wellfield expansion every 4 to 5
weeks. Wellfield development continued at a consistently accelerated rate.
On 4 July 2025, Boss also announced that it had entered into an amendment to the existing Uranium Loan
Agreement with enCore, pursuant to which Boss extended the repayment date of the existing loan (US$10.4
million outstanding at the time of announcement) to 27 December 2025 and provided an additional cash
facility of US$3.6 million.
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
Page 6
Laramide Resources Ltd (Boss 19.9% ownership)
During the current quarter, Boss has secured a 19.9% interest in Laramide Resources Ltd (TSX: LAM; ASX:
LAM; OTCQX: LMRXF) (“Laramide”) on an undiluted basis. On 30 June 2025, Laramide announced that it has
arranged a non-brokered private placement of up to 16,666,667 common shares for gross proceeds up to
C$10,000,000. Boss has committed to take up its pro-rata share of the placement.
On 17 July 2025, Laramide announced that its 100%-owned Australian subsidiary, Tackle Resources Pty Ltd,
has received approval of a Mineral Development Licence (“MDL”) for the Westmoreland Uranium Project in
Queensland, Australia. The approval of the MDL provides a strong foundation for Laramide to advance
project permitting and to undertake mining feasibility studies, metallurgical testing and marketing, as well as
environmental, engineering and design studies required to support a future Mining Lease application2.
First Quantum Minerals Joint Venture
Boss Energy was informed during the quarter of the withdrawal of First Quantum Minerals from the
exploration joint venture entered into with Boss in February 2022 for base and precious metals over five
tenements at Honeymoon. First Quantum successfully intersected basement-hosted base metal
mineralisation below the Yarramba Palaeovalley, and screened the tenure for large-scale copper deposits at
economic depths, however mineralisation was deemed not of the size and scale required for First Quantum
as a global copper miner.
Given the withdrawal of First Quantum, the base and precious metals rights revert 100% to Boss on these
tenements.
Board changes and Management Transition
On 2 June 2025, the Company announced the appointment of two highly experienced Directors to help
bolster its Board capability and further enhance the Company’s overall investment credentials.
Joanne Palmer was appointed as Non-executive Director and Chair of the Audit Committee. Ms Palmer is a
former partner at international accounting firm EY and a former Executive Director at Pitcher Partners. She
led EY’s Financial Accounting Advisory Services team in Perth with a strong focus on the resources sector.
Caroline Keats was also appointed as Non-executive Director. Ms Keats has 20 years of corporate and
commercial experience and has served in various executive roles. For nearly 15 years she worked in the
mining industry in Australia and foreign jurisdictions. Contemporaneously, the Company also announced the
retirement of long serving Non-executive Director Mr Bryn Jones.
On 24 July 2025, the Company announced a Board and Management transition, with Managing Director and
CEO Duncan Craib stepping down, effective 30 September 2025. At the Board’s request, Mr Craib will
commence as a Non-Executive Director from 1 January 2026.
Chief Operating Officer Matt Dusci will be appointed Managing Director and CEO, effective 1 October 2025,
subject to agreement between the Company and Mr Dusci on the terms.
Uranium Market Analysis
Whilst the first quarter of 2025 had been characterised by uncertainty, the second quarter reflected what
could be a positive turning point, reflected by several positive catalysts.
2
Refer to Laramide’s ASX Announcement “Laramide Granted Mineral Development Licence for Westmoreland Uranium Project”
released on 17 July 2025
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
Page 7
The uranium market has seen renewed strength since April, driven by rising government support, expanding
nuclear programs, and resurgent financial interest. In the U.S., the Nuclear Fuel Security Act unlocked US$3.4
billion for domestic enrichment and uranium production, while the Department of Energy initiated strategic
uranium purchases under its HALEU and LEU programs.
Globally, demand is rising as nuclear energy gains policy momentum. China began construction on six new
reactors, India is accelerating approvals for 21 units, and Japan extended reactor lifespans beyond 60 years.
The EU formally included nuclear in its green taxonomy, and France is advancing plans for six EPR reactors.
SMRs are also gaining traction, with Canada investing in early deployment.
Sprott Uranium Trust resumed buying in the spot market, adding over 2.5M lbs U₃O₈. As a result, the spot
availability has tightened and rising term contracting via utility RFP has also been noted. The term price
indicators could be more reactive in the coming months.
Figure 3: Historical U3O8 (Spot Price and Long-Term Price)
US$
160
140
120
100
80
60
40
20
U3O8 Spot Price
Jun-25
Jun-24
Jun-23
Jun-22
Jun-21
Jun-20
Jun-19
Jun-18
Jun-17
Jun-16
Jun-15
Jun-14
Jun-13
Jun-12
Jun-11
Jun-10
Jun-09
Jun-08
Jun-07
Jun-06
Jun-05
Jun-04
-
U3O8 Long-Term Price
Source: UxC, LLC https://www.uxc.com/
June 2025 Quarterly Results Conference Call – 28 July 2025
Boss will hold a conference call today, Monday 28 July 2025, at 11am AEST (9am AWST) with Managing
Director Duncan Craib, Chief Financial Officer Justin Laird and Chief Operating Officer Matt Dusci, to discuss
the results. To listen in live, please click on the link below and register your details.
https://loghic.eventsair.com/105665/672155/Site/Register
Appendix 5B disclosures
In line with its obligations under ASX Listing Rule 5.3.5, Boss notes that the only payments to related parties
of the Company, as disclosed in the Appendix 5B (Quarterly Cashflow Report) for the period ended 30 June
2025, consist of executive director and chief financial officer salaries and wages (including superannuation)
and payment of non-executive director fees.
During the quarter ended 30 June 2025, the Company spent approximately $16.4M on project and
exploration activities relating to its Honeymoon and Alta Mesa Projects. These activities included:
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
Page 8
•
Technical studies costs
•
Construction equipment
•
Wellfield drilling and development costs
•
Engineering and construction expenses
•
Mineral exploration and evaluation costs
In addition to these activities the Company continued to incur costs relating to the ongoing maintenance
activities required at Honeymoon. The expenditure represents direct costs associated with these activities as
well as capitalised wages which can be directly attributable to Honeymoon.
This ASX announcement was approved and authorised by the Board of Boss Energy Limited.
For further information, contact:
Duncan Craib
Chief Executive Officer
P: +61 (8) 6263 4494
E: boss@bossenergy.com
For media enquiries, contact:
Paul Armstrong
Read Corporate
P: +61 (8) 9388 1474
E: info@readcorporate.com
Reference to previous ASX announcements
The mineral resource estimates in this announcement were reported by the Company in accordance with
listing rule 5.8 on 25 February 2019. The Company confirms it is not aware of any new information or data
that materially affects the information included in the previous announcement and that all material
assumptions and technical parameters underpinning the estimates in the previous announcement continue
to apply and have not materially changed.
Forward-Looking Statements
This announcement contains certain forward-looking statements provided by or on behalf of Boss with
respect to potential future matters. Forward-looking information may include, without limitation, statements
regarding plans, strategies and objectives of Boss, production and financial guidance, financial forecasts,
estimates of project milestones and timing and expected costs or production outputs. In some cases,
forward-looking information can be identified by terms such as “may”, “will”, “should”, “expect”, “plan”,
“anticipate”, “believe”, “intend”, “estimate”, “predict”, “potential”, “continue” or other similar expressions
concerning matters that are not historical facts. Guidance as to production, unit costs and capital expenditure
is based on assumptions, budgets and estimates existing at the time of assessment which may change over
time impacting the accuracy of those estimates. These estimates are developed in the context of an uncertain
operating environment including in respect of inflationary macroeconomic conditions, and uncertainties
surrounding the risks associated with mining and the further review of the EFS which may impact production
and have a flow on effect on sales. Actual results may therefore vary significantly depending on these risks
and the timing required to address them. All information is provided as an indicative guide to assist
sophisticated investors with modelling of the Company. It should not be relied upon as a predictor of future
performance.
Forward-looking statements reflect Boss’s expectations at the date of this announcement, however they are
not guarantees or predictions of future performance or statements of fact. Forward-looking information
involves known and unknown risks, uncertainties and other factors (many of which are beyond the control
of Boss and its directors and management) which may cause the actual results, performance or achievements
of Boss and its business to be materially different from any future results, performance or achievements
expressed or implied by the forward-looking information. Accordingly, undue reliance should not be placed
on forward-looking information.
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
Page 9
The forward-looking statements in this announcement reflect various assumptions by or on behalf of Boss
(which assumptions may prove to be inaccurate). Accordingly, this is another reason why such statements
are subject to significant business, technical, legal, economic and competitive and other uncertainties and
contingencies and other factors which may be beyond the control of Boss which could cause actual results
or trends to differ materially from the forward-looking statements in this announcement, including but not
limited to differences or inaccuracies arising from price and currency fluctuations, geotechnical factors,
geological and mining factors, estimated continuity of mineralised horizons, metallurgical and processing
factors, sales factors, drilling and production results, development progress, operating results, mineral
resource estimates, legal issues, legislative, fiscal and regulatory developments, economic and financial
market conditions in various countries, approvals and cost estimates, environmental risks, ability to meet
funding requirements, share price volatility, uranium markets and other matters. Accordingly, there can be
no assurance that such forward-looking statements and projections will be realised.
Boss makes no representations as to the accuracy or completeness of any forward-looking statements or
projections or that any forecasts will be achieved. Additionally Boss makes no representation or warranty,
express or implied, in relation to, and (to the maximum extent permitted by law) no responsibility or liability
(whether for negligence, under statute or otherwise) is or will be accepted by Boss or by any of its officers,
directors, shareholders, partners, employees, or advisers as to or in relation to the accuracy or completeness
of the information, statements, opinions or matters (express or implied) arising out of, contained in or
derived from this announcement or any omission from this announcement.
Boss does not undertake or accept any obligation or undertaking to release publicly any updates or revisions
to any forward-looking statements to reflect any change in Boss’s expectations or any change in events,
conditions or circumstances on which any such statement is based, except as required by law.
Mineral Resource estimates are necessarily imprecise and depend on interpretations and geological
assumptions, minerals prices, cost assumptions and statistical inferences (and assumptions concerning other
factors, including mining, processing, metallurgical, infrastructure, economic, marketing, legal,
environmental, social and governmental factors) which may ultimately prove to be incorrect or unreliable.
Mineral Resource estimates are regularly revised based on actual exploration or production experience or
new information and could therefore be subject to change. In addition, there are risks associated with such
estimates, including (among other risks) that minerals mined may be of a different grade or tonnage from
those in the estimates and the ability to economically extract and process the minerals may become
compromised or not eventuate. Accordingly, this is another reason why no assurances can be given of
whether the production guidance, financial forecasts or other forecasts or other forward-looking statements
or information in this announcement will be achieved.
Effect of Rounding
A number of figures, amounts, percentages and estimates in this announcement are subject to the effect of
rounding. Accordingly, the actual calculation of these figures may differ from the figures set out in this
announcement.
Past Performance
Past performance information, including past share price performance of Boss and past Honeymoon Project
information, given in this announcement is given for illustrative purposes only and should not be relied upon
as (and is not) an indication of Boss’s (or anyone else’s) views on Boss’s future activities, guidance or financial
performance or condition. Past performance of Boss cannot be relied upon as an indicator of (and provides
no guidance as to) the future performance of Boss.
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
Page 10
Appendix One:
Schedule of Mining Tenements
The following information is provided pursuant to Listing Rule 5.3.3 for the quarter ended 30 June 2025.
Tenement Name
Location
Licence Number
Interest
Yarramba
South Australia
EL6510
100%
South Eagle
South Australia
EL6081
100%
Gould’s Dam
South Australia
EL6512
100%
Katchiwilleroo
South Australia
EL6511
100%
Ethiudna
South Australia
EL6020
100%
Gould’s Dam
South Australia
RL83-85
100%
Honeymoon Mine
South Australia
ML6109
100%
Prairie Dam
South Australia
EL6962
75%
Chalker Dam
South Australia
EL6963
75%
Oakvale
South Australia
EL6964
75%
Gairloch
South Australia
EL6965
75%
Venus Bay
South Australia
EL6992
100%
Darke Peak
South Australia
EL7013
100%
Rudall
South Australia
EL6999
100%
There were no mining tenement acquisitions or divestments during the quarter.
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
Page 11
Honeymoon Project Mineral Resource
Honeymoon’s Mineral Resource (lower cut-off of 250 ppm U3O8)
Classification
Tonnage
(Million Tonnes)
Average Grade
(ppm U3O8)
Contained Metal
(Mkg, U3O8)
Contained Metal
(Mlb, U3O8)
Measured
3.1
1,100
3.4
7.6
Indicated
18.4
630
12.0
25.5
Inferred
30.9
570
18.0
38.5
Total
52.4
620
32.5
71.6
The global Honeymoon Mineral Resource stands at 71.6Mlb (52.4Mt) with an average grade of 620ppm U308,
using a cut-off grade of 250ppm.
The current Honeymoon restart feasibility studies utilise only a portion of Honeymoon’s JORC resource,
excluding 36Mlb of JORC resource outside the HRA, which could expand the mine life, and Boss’ defined
exploration target could potentially extend the mine life beyond the initial 11 years and increase the
production profile. Honeymoon’s Federal EPIP Act approvals allow export of ~3.3 Mlbs/annum U3O8
equivalent.
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
Page 12