Quarterly Activities Report
Released
Released
Announcement PDF
ASX ANNOUNCEMENT
30 October 2015
ASX: BOE
30 SEPTEMBER 2015 QUARTERLY REPORT
HIGHLIGHTS
Honeymoon Uranium Project, South Australia
Boss entered into an agreement with Uranium One Inc. to acquire the Honeymoon
Project
Honeymoon Project has resources (up to 2,100ppm) amenable to in situ leach
processing
Full mine infrastructure in place with 880,000lb pa solvent extraction plant already built
One of only 4 fully permitted uranium projects in Australia
Placed on care and maintenance in 2013 – never fully commissioned in period of low
uranium prices
Large 2,595km2 tenement package with excellent exploration potential
Company-transforming acquisition places Boss at the forefront of aspiring Australian
uranium producers
Corporate
Successful completion of oversubscribed non-renounceable rights issue and placement
raises $4.3 million to fund Honeymoon Project acquisition
Honeymoon Uranium Project
Boss Resources Ltd (Boss or the Company) announced the agreement to acquire the
Honeymoon Uranium Project in South Australia via the acquisition of 100% of the issued share
capital of Uranium One Australia Pty Ltd (ASX: 1 September 2015). Boss will form a SPV with
Wattle Mining Pty Ltd (Wattle) whereby Boss will own 80% and Wattle will own 20% of Uranium
One Australia Pty Ltd, with Boss holding an option to acquire Wattle’s 20% post completion of a
BFS.
The Honeymoon Uranium Project (“Honeymoon” or the “Project”) (Figure 1) is located in South
Australia and is approximately 80km north-west from the town of Broken Hill near the SA / NSW
border.
The Project consists of 1 granted Mining Lease, 5 granted Exploration Licenses, 8
Retention Leases and 2 Miscellaneous Purposes Licenses. The Honeymoon mining infrastructure
Suite 23, 513 Hay St, Subiaco WA
PO Box 1311, Subiaco WA 6904
P: +61 (8) 6143 6730
E: admin@bossresources.com.au
ABN 38 118 834 336
is located on ML6109 and hosts one of the highest grade ISL Mineral Resources in Australia (1.44Mt
@ 0.21% U O ) and has produced some 335t of U O from 2011 to 2012.
3
8
3
8
There are 2 main exploration regions: the Eastern Region (EL’s 5215 and 5621) which hosts the
Honeymoon, Brooks Dam and East Kalkaroo Resources; and the Western Region (EL’s 5043, 5623
and 5622) which hosts the Goulds Dam and Billeroo deposits which have historical Mineral
Resource estimates (Figure 4). The large tenement package covers approximately 2,595km2 and
has excellent exploration potential to identify further resources.
Native title agreements with respect to the exploration and mining activities have been signed with
the local indigenous communities. Mining and uranium export permits (both State and Federal)
are in place.
Figure 1: Honeymoon Uranium Project. The pink shaded regions represent palaeodrainage channels which have
potential to host uranium mineralisation and are the focus of exploration efforts.
GEOLOGY
The Honeymoon Uranium Project is located in the southern part of the Callabonna sub-basin in
South Australia. Uranium mineralisation within the project area is hosted by the Yarramba and
Billeroo palaeochannels (Figure 2). These consist of Palaeogene age palaeovalleys filled by a
sequence of inter-bedded sand, silt and clay (Figure 2). Thickness of the palaeochannels at
Honeymoon deposit area reaches a maximum of 55m thick.
The uranium mineralisation represents a classic basal channel type sandstone-hosted uranium
roll-front model. This model implies the movement of oxidised, uranium-bearing fluid through a
largely reduced aquifer, with mineralisation occurring at the redox front of the fluid. A geochemical
zonation is associated with the roll front, including oxidation of the sands upstream (orange and
yellow limonite) and abundance of pyrite/marcasites and organic matter downstream.
Mineralisation is associated with discreet accumulations of organic matter and pyrite within the
palaeovalley sequence.
Distribution of the uranium accumulations within the palaeochannels is controlled by fluid
pathways that have transported the dissolved uranium and the distribution of organic matter
which served as reductants causing precipitation of uranium. Interplay of these two main factors
has created a stacked geometry of the “uranium rolls” commonly distributed as elongate pods
along the strike of the palaeovalley (Figures 1 and 2). This style of mineralisation is similar to that
seen in the Shinarump, Monitor Butte and Moss Back members of the Upper Triassic Chinle
formation in the White Canyon areas of the uranium mining districts of South Eastern Utah, USA.
Figure 2: Geological map showing distribution of uranium mineralisation in southern part of the Yarramba
palaeochannel. Shaded areas denote interpreted thicker conductive palaeo sedimentary packages, dots are the ore
grade drill hole intersections, defined at 300ppm U O cut off
3
8
Figure 3: Conductivity map of Billeroo palaeochannel (Airborne EM data) that hosts Goulds Dam and Billeroo deposits
showing priority target regions. Note: Blue regions indicate potential palaeochannel areas.
RESOURCES
The Mineral Resources for Honeymoon, Brooks Dam and East Kalkaroo are summarised in Table
1. In total, they contain 5.3Mt of mineralisation at the average grade of 0.14 % U O , which
3
8
corresponds to 16.6Mlb (7,540 tonnes) of contained U O above a 0.05% U O lower cutoff.
3
8
3
8
All Mineral Resources are located below the water table at the depth of approximately 100m and
hosted by the palaeochannel sedimentary sequence composed of weakly lithified permeable
sands intercalated with clays. Previous hydro-geological test work including pilot production
mining study have confirmed that Mineral Resources are amenable for exploitation using in situ
leach technologies.
Table 1 – Honeymoon Project Resource Summary – 13 July 2015
Classification
Cut-off grade
Tonnage
Grade
Contained U O
(% U O )
(Mt)
(% U O )
(Thousand Tonnes)
(Million Pounds)
0.05
1.44
2.97
6.54
3
8
3
3
Contained U O
8
3
1
8
8
Honeymoon
Indicated
1
0.23
Total adjusted to account for historical production of ~335 tonnes U O Note: Figures have been rounded
3
8.
Brooks Dam (BKD)
Indicated
0.05
Inferred
0.05
0.78
0.11
0.87
1.92
0.75
1.66
2.94
6.45
Brooks Dam Extension (BDE)
0.51
0.15
East Kalkaroo
Inferred
0.05
2.56
0.11
Combined Honeymoon, Brooks Dam, Brooks Dam Extension and East Kalkaroo
Indicated and
Inferred
0.05
5.29
0.14
7.53
16.57
EXPLORATION OPPORTUNITIES
The Board considers that the Project contains significant potential for additional Mineral
Resources to be defined. Specifically, the Goulds Dam and Billeroo regions (Figure 3) contain
historical Mineral Resource estimates that have not yet been validated by the Boss technical team.
Regionally, in the Gould’s Dam region (Figure 3) airborne geophysical data indicates the potential
for untested paleochannel regions, with historical drilling data indicating the presence of uranium
mineralisation. Boss has chosen not to publicly announce the potential endowment of these
regions until further technical validation endeavours have been completed.
Additionally, past exploration drilling has shown that uranium mineralisation continues up and
downstream from ML6109 for more than 15km in each direction within EL’s 5215 and 5621 (Figures
1 and 2).
The project database contains some 208 drill holes that intersected ore grade
mineralisation, with grades of up to 4,000ppm eU O (Figure 2). These regions will also be the focus
3
for exploration targeting.
8
URANIUM ONE AUSTRALIA ASSETS
There is significant infrastructure associated with the acquisition of Uranium One Australia. Key
assets include:
-
Solvent extraction processing plant with a capacity to produce 880,000lbs of uranium per
annum currently on care and maintenance
-
Well fields currently on care and maintenance
-
200 person operating mining camp
-
Administration buildings
-
75km power line connecting to mains power
-
A fleet of vehicles, spares and other equipment associated with the commissioning of the
Project
-
Runway capable of landing light planes
-
Extensive geological database of 1,700 drill holes and associated logging information
-
Cash backed environmental bonds in the amount of $8.7 million
Figure 4: Project infrastructure
ACQUISITION TERMS
Boss has entered into an agreement to acquire 100% of the issued share capital of Uranium One
Australia which owns the Honeymoon Uranium Project ("Acquisition"). The consideration for the
Acquisition includes:
-
A $200,000 site access fee (paid) which gave Boss the exclusive right to access the
Honeymoon Uranium Project and conduct all its due diligence
-
An initial cash payment of approximately $2,442,000 (comprising an amount of $2,115,000
plus a care and maintenance contribution of approximately $327,000) ("Closing Amount")
-
$3 million under a promissory note and repayable within 24 months of completion of the
Acquisition
-
$4 million under a promissory note issued and repayable within 48 months of completion
of the Acquisition
Boss will also make the following contingent payments to U1 upon successful recommissioning
of the Honeymoon Uranium Project:
-
$2 million payable in cash and/or shares upon the later of restart of the operations with
commercial production or 5 years of completion of the Acquisition
-
10% of the net operating cash flow of the Honeymoon Project payable annually up to a
maximum of $3 million
The payment of the Closing Amount has been guaranteed by Carbine Resources Limited
("Carbine Guarantee").
In consideration for the Carbine Guarantee, Boss issued 10 million
unlisted options exercisable at $0.02 each within 3 years from date of issue. The promissory notes
are secured under the terms of a general security deed. Repayment of the amounts due under the
promissory notes may be accelerated in certain circumstances, including where Boss raises
financing of $15 million, the sale of the shares in Uranium One Australia or the Honeymoon Project
(or part thereof) or a change in control of Boss.
Conditions to the Acquisition
Completion of the Acquisition is subject to various conditions precedent, including but not limited
to:
-
No insolvency event occurring with respect to Boss, its subsidiaries or Carbine Resources
Limited;
-
any requisite shareholder approval of Boss;
-
U1 and Uranium One Australia obtaining any necessary approvals from contractors;
-
U1 and Uranium One Australia discharging existing security interests in respect of the
shares in Uranium One Australia and the Honeymoon Project; and
-
That a material adverse change in the business or assets of Uranium One Australia does
not occur prior to the completion date.
It is anticipated that completion shall occur within approximately three months.
Option over Wattle’s 20% in Joint Venture
Boss has a call option to acquire Wattle’s 20% interest in the Joint Venture after it completes a
positive bankable feasibility study to restart the operations. The terms of the acquisition will be
mutually agreed or otherwise determined by an independent valuer taking into account the
valuation of the project and market capitalisation of Boss at the relevant point in time. The
consideration of the acquisition of Wattle’s 20% interest may, at the election of Boss, be payable in
cash and/or shares in Boss.
Burkina Faso Gold Assets
In March 2014, Boss and Gryphon Minerals Ltd (ASX: GRY) signed a binding head so fo agreemen
to establish a joint venture over Boss’ Golden Hill and Gourma Gold Projects located in Burkina
Faso (ASX: 4 July 2014 for full terms of the agreement).
Gryphon has completed a review of past work, acquired high resolution remote sensing datasets,
completed relatively high density (>1 sample per ~6 km2) drainage sampling, supplemented by
laterite sampling, where appropriate, across all joint venture projects. This strategy is allowing the
company to fast track targeting across the exploration licences. Some highly anomalous multipoint drainage anomalies have been identified on both projects and these are progressively being
followed up by soil and first pass auger drilling seeking the mineralised bedrock source. To date
Gryphon has collected over 16,000 soil samples and drilled nearly 1150 auger holes for ~600m
since commencing work on the joint venture.
With the wet season occurring throughout the quarter very limited field work took place as access
to these areas was difficult. Work was mainly limited to desktop reviews and planning for the next
field season.
Gourma Project
The Gourma Gold Project is located within the Fada N’Gourma Greenstone Belt, 250km east of
Ouagadougou and only 80km south-southwest of Niger’s largest gold deposit, the 50,000 ounce
per annum Samira Hill gold mine (1.9 million ounce project). The Project consists of six contiguous
permits covering an area of approximately 1,300 km2 which is accessible from the south off the
Fada N’Gourma Kantchari highway via a well maintained gravel road and from the west via a
gravel road.
Observations and samples obtained during field visits prior to the wet season were used during
the quarter to assist with geological understanding, including recognition and understanding of
the mineralisation styles and associated pathfinder elements, as well as the potential controls to
mineralisation. This work will continue throughout the December quarter and will complement
the exploration being undertaken. The small efficient exploration team are working towards
generating high quality drill targets across the large land package.
Golden Hill Project
The Golden Hill Gold Project is considered particularly prospective as it is located within the highly
mineralised Houndé Greenstone Belt.
Exploration work during this quarter comprised of geological mapping and auger drilling. Auger
drilling (total of 96 holes for 558m) focused primarily at the Nahirindon North Prospect and drilled
beneath a thick ferricrete plateau on the prospective Boni Sheer Zone in a similar geological
environment to that which hosts the Siou Deposit on the Houndé Belt (reserves of 769,000oz at
4.94 g/t gold). The results to date are encouraging and these will be following up once the field
season recommences.
Auger results were received in early July including lines drilled at Nahiri Sud Nahiri Sud from a
zone dubbed Jack Hammer Hill for the prominent ridge of auriferous ferricrete. Two short auger
lines were drilled 250m apart immediately north of this ridge. The lines indicate a NE striking zone
of +100 ppb gold anomalism that is approximately 100m wide with peak values of 1.14g/t Au in
GHAU1013 and 0.73g/t Au in GHAU0990 along strike (ASX: GRY: 28 October 2015).
A geological review of Jack Hammer Hill indicates that artisanal workings are located at the
northern margin of the V7 Granite Stock; the same intrusive that hosts mineralized zones previously
targeted by Orezone (TSX: ORE) at A-Zone. The trend of anomalism is also coincident with a belt
of mafic schist recently mapped by Gryphon geologists. This mafic schist is in turn parallel to the
major Intiedougou Fault Zone, perhaps marking its eastern boundary. A review of historical
Induced Polarization geophysical data indicates a significant chargeability anomaly coincident
with the projection of several other prospects along strike, suggesting that the ground geophysics
will augment the exploration geochemistry datasets and thus aid future drill planning. Follow-up
work has been planned and will be undertaken in the new field season starting in the coming
quarter.
Fennoscandian Ni-Cu Projects
Due to the Company’s focus on the Honeymoon Project during the quarter, no material work was
undertaken on the Company’s assets in Finland, Sweden and Norway.
Corporate
On 8 September 2015, Boss lodged a prospectus for a non-renounceable rights issue to eligible
shareholders on the basis of 2 new shares for every 5 shares held at an issue price of $0.015 to
raise up to $3.3 million (before costs). The Company was pleased to announce that existing
shareholders subscribed for shares totalling $1,375,786.61 under the rights issue (ASX: 1 October
2015). Significant interest from both existing shareholders and new investors resulted in the
placement of all of the shortfall shares as well as an additional placement for a further $1.03
million. The total amount raised from the rights issue, the shortfall shares and the additional
placement resulted in a $4.3 million raising which will be used to fund the acquisition of the
Honeymoon Project and for general working capital.
For further information please contact:
Evan Cranston
Chairman:
+61 (0) 408 865 838
Peter Williams
Technical Director:
+61 (0) 427 341 823
Appendix 1
The following information is provided pursuant to Listing Rule 5.3.3 for the quarter ended 30 September
2015:
SCHEDULE OF MINING TENEMENTS
Tenement Name
Location
Licence Number
Interest
Boutouanou
Burkina Faso
2011/11/410
100% (GRY farming in)
Diabatou
Burkina Faso
2011/11/409
100% (GRY farming in)
Tyara
Burkina Faso
2011/11-159
100% (GRY farming in)
Foutouri
Burkina Faso
2011/11-160
100% (GRY farming in)
Baniri
Burkina Faso
2009/09-060
100% (GRY farming in)
Intiedougou
Burkina Faso
2009/09-061
100% (GRY farming in)
Mougue
Burkina Faso
2009/09-062
100% (GRY farming in)
Kankandi
Burkina Faso
10/142/MCE
100% (GRY farming in)
Tyabo
Burkina Faso
10/144/MCE
100% (GRY farming in)
Liakka
Finland
Liakka nr.1
Right to earn 100%
Skogtrask Project
Sweden
Skogtrask nr.1 and 2
Right to earn 100%
Skogtrask nr.3
100%
Palange nr.1
100
Nottrask Project
Sweden
Norrtrask nr.9
100%
Lilltrask Project
Sweden
Lilltrask nr1, 2 and 3
100%
Linn Project
Norway
Linn 1 - 12
100%
Yarramba
South Australia
ELA2014/00228
Agreement to acquire*
South Eagle
South Australia
EL5215
Agreement to acquire*
Goulds Dam
South Australia
ELA2014/00240
Agreement to acquire*
Katchiwilleroo
South Australia
ELA2014/00239
Agreement to acquire*
Ethiudna
South Australia
EL5043
Agreement to acquire*
Goulds Dam
South Australia
RL83-90
Agreement to acquire*
Honeymoon Mine
South Australia
ML6109
Agreement to acquire*
No tenements were acquired or disposed of during the quarter. There were no interests in farm-in/farm-out
agreements acquired / disposed of during the quarter.
*An agreement to acquire the Honeymoon Uranium Project was entered into during the quarter and is
expected to complete around 30 November 2015.
Competent Person’s Statements
The information in this document that relates to the Honeymoon Uranium Project Mineral Resources is based on information
provided by Mr Leon Faulkner, who is a member of the Australian Institute of Geoscientists (member number 3454). Mr
Faulkner is a consultant geologist and has sufficient experience which is relevant to the style of mineralisation and type of
deposit under consideration and the activity undertaken to qualify as a Competent Person as defined in the 2012 Edition of
the “Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves”. Mr Faulkner consents to
the inclusion in the document of the matters based on information in the form and context in which it appears. This
information has not materially changed since first being reported to the ASX on 1 September 2015.
The information in this document that relates to the Exploration Data is based on information compiled by Mr Neil Inwood.
Mr Inwood is a technical consultant for Verona Capital and has sufficient experience which is relevant to the style of
mineralisation and type of deposit under consideration and the activity undertaken to qualify as a Competent Person as
defined in the 2012 Edition of the “Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore
Reserves”. Mr Inwood consents to the inclusion in the document of the matters based on information in the form and context
in which it appears. This information has not materially changed since first being reported to the ASX on 1 September 2015.
For full details of the Mineral Resources and exploration results reported in this document, see ASX announcement lodged on
1 September 2015.
The information in this report that relates to recent exploration results for the Company’s projects in Burkina Faso under Joint
Venture with Gryphon Minerals Ltd (ASX: GRY) is based on and fairly represents information which has been compiled by Mr
Sam Brooks who is a member of the Australian Institute of Geoscientists. Mr Brooks has sufficient experience relevant to the
styles of mineralisation and type of deposit under consideration and to the activity being undertaken to qualify as a
Competent Person, as defined in the 2012 Edition of the “Australasian Code for Reporting of Exploration Results, Mineral
Resource and Ore Reserves”. Mr Brooks is a full time employee of Gryphon Minerals Ltd, the joint venture partner of Boss
Resources Ltd for the Company’s Burkina Faso Projects, and has consented to the inclusion of the matters in this report based
on his information in the form and context in which it appears. This information has not materially changed since first being
reported to the ASX on 28 October 2015.