Boss commences new drilling program at Jason's deposit
Released
Released
Announcement PDF
ASX Release 15 November 2023
Honeymoon Uranium Project, South Australia
Boss advances growth strategy with new
drilling program at Jason’s satellite deposit
Jason’s is one of several deposits which will underpin a Honeymoon expansion study;
Honeymoon on track for start of production this quarter
Highlights
•
The Jason’s deposit is located ~13km north of the Honeymoon mine and contains a JORC
Resource 6.2Mt at 790ppm U308 for 10.7Mlbs contained U308 (Inferred).
•
The new drilling program will provide important geological and hydrogeological information,
test for continuity and extensions to existing mineralisation and provide validation of historical
(i.e 1970s) drilling. Intercepts from historic drilling at Jason’s include:
o 2.75m @ 3,898ppm pU3O8
o 2.00m @ 4,428ppm pU3O8
o 4.00m @ 1,611ppm pU3O8
o 1.25m @ 2,579ppm pU3O8
o 3.00m @ 1,040ppm eU3O8
GT 10,720
GT 8,856
GT 6,444
GT 3,224
GT 3,120
(YAM040 from 105.79m)
(BMR043 from 105.50m)
(BMW0001 from 101.50m)
(BMR014 from 101.75m)
(580_018 from 102.10m)
•
Boss aims to drive organic growth through exploration on its 100 per cent-owned tenements;
This is designed to underpin increases in the inventory, mine life and production rates at
Honeymoon
•
Jason’s, along with the known satellite deposits of Gould’s Dam, Billeroo and Sunrise, will form
the basis of a study on increasing the forecast production rate to more than 3Mlb/annum U308
equivalent (from 2.45Mlb nameplate capacity) or an extension of mine life
•
Boss’ exploration strategy has already been highly successful, increasing the JORC Resource at
Honeymoon from 16.57Mlbs to 71.67Mlbs (~4.3x increase) since project acquisition in
December 20151
•
The current life-of-mine plan at Honeymoon is based on just 50% of the existing JORC Resource
Boss Energy Limited (ASX: BOE; OTCQX: BQSSF) is pleased to announce the start of a new infill and scout
drilling program at the Jason’s deposit, located ~13km north of the Honeymoon Mine (Figure 1).
Boss Managing Director Duncan Craib said: “In parallel with the impending start of production at
Honeymoon, we are driving our organic growth strategy.
“Satellite deposits such as Jason’s will help underpin our expansion study, which is aimed at increasing
the inventory and production rate.
“This will also enable us to leverage the existing infrastructure at Honeymoon and capitalise on the
growing demand for uranium from tier-one locations such as Australia”.
1
Refer to ASX: BOE announcement dated 25 February 2019. Refer Appendix 1 for Honeymoon JORC 2012 Resource.
FOR FURTHER INFORMATION PLEASE CONTACT:
Boss Energy Limited
ABN 38 116 834 336
Duncan Craib - Managing Director/ CEO
+61 (08) 6263 4494
ASX: BOE
OTCQX: BQSSF
Level 1, 420 Hay Street, Subiaco
Western Australia 6008
Paul Armstrong – Public Relations
+61 (08) 9388 1474
www.bossenergy.com
@Boss_Energy
Infill drilling Program
The current extent of the Jason’s satellite deposit covers a strike length of ~2.5km and is hosted by Eyre
Formation sediments within the Yarramba palaeovalley approximately 13km north of the Honeymoon
mine. The area has been subject to drilling periodically since the early 1970s, with the most recent
program completed by Boss in 2016 culminating in the release of the current JORC Inferred resource of
10.7M lbs U3O8. Drill line spacing across the deposit is still relatively coarse, ranging from ~100m to more
commonly up to 250m.
Figure 1: Location of the Jason’s satellite deposit.
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
@Boss_Energy
The drilling program is designed to provide important geological and hydrogeological information for the
Eyre Formation sediments that host the uranium mineralisation. This program will comprise a
combination of resource infill and step-out rotary mud drilling, with the aim of both confirming and
extending the continuity of identified mineralised zones along with confirmation/upgrade of a number of
historical drill results within the resource model.
All holes will be logged with Boss’ inhouse Prompt Fission Neutron (PFN) tools, along with a combination
of Borehole Magnetic Resonance (BMR), neutron porosity, formation density and calibrated gamma tools.
This downhole logging suite will provide a detailed picture of the geological and hydrogeological setting
of uranium mineralisation across the deposit and will ultimately be used for future infill and/or step-out
drilling in the area.
Jason’s deposit
The Jason’s deposit is located ~13km north of the Honeymoon Mine and currently contains a JORCcompliant resource (Table 1) 6.2Mt at 790ppm U308 for 10.7Mlbs contained U308 (Inferred).
Table 1: Summary of Mineral Resource for the Jason’s satellite deposit
Resource
Classification
Tonnage
(Million Tonnes)
Average Grade
(ppm U3O8)
Contained Metal
(Kt, U3O8)
Contained Metal
(Mlb, U3O8)
Jason’s deposit (March 2017) 2
Inferred
6.2
790
4.9
10.7
Honeymoon Project Mineral Resource
The global Honeymoon Mineral Resource stands at 71.6 Mlb (52.4Mt) with an average grade of 620ppm
U308, using a cut-off grade of 250ppm, as summarised in Table 2.
The current Honeymoon restart feasibility studies utilise only a portion of Honeymoon’s JORC resource,
excluding 36Mlb of JORC resource outside the HRA, which could expand the mine life, and Boss’ defined
exploration target could potentially extend the mine life beyond the initial 11 years and increase the
production profile. Honeymoon’s Federal EPIP Act approvals allow export of more than 3Mlbs/annum
U308 equivalent.
In addition to the global Mineral Resource, the Honeymoon Uranium Project also has an Exploration
Target range of 28 Mt to 133 Mt of mineralisation at a grade of 340 ppm to 1,080 ppm U308 for a contained
58 Mlbs to 190 Mlbs U308 (26,300 to 86,160 tonnes of contained U308), using a cut-off of 250ppm3. Note
the potential quantity and grade of the Exploration Target range is conceptual in nature. There has been
insufficient exploration to estimate a Mineral Resource and it is uncertain whether future exploration will
result in the definition of a Mineral Resource.
2 Refer to ASX: BOE announcement dated 15 March 2017.
3 Refer to ASX: BOE announcement dated 25 March 2019.
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
@Boss_Energy
Table 2: Summary of Mineral Resource for satellite deposits of Gould’s Dam and Jason’s
Resource
Classification
Tonnage
(Million Tonnes)
Average Grade
(ppm U3O8)
Contained Metal
(Kt, U3O8)
Contained Metal
(Mlb, U3O8)
4.9
10.7
Jason’s (March 2017)2
Inferred
6.2
790
Gould’s Dam (April 2016)4
Indicated
4.4
650
2.9
6.3
Inferred
17.7
480
8.5
18.7
Honeymoon Restart Area (January 2019)
Measured
3.1
1,100
3.4
7.6
Indicated
14
610
8.7
19
Inferred
7.0
590
4.1
9.1
GLOBAL HONEYMOON URANIUM PROJECT
Measured
3.1
1,100
3.4
7.6
Indicated
18.4
630
12.0
25.3
Inferred
30.9
570
18.0
38.5
Total
52.4
620
32.5
71.6
About Boss Energy
Honeymoon is on track for first production in the December quarter, 2023. The mine is increasing the
production profile to 2.45 Mlb/annum over a plus-10 year mine life but utilising only 36Mlbs of the
Project’s global JORC Resource of 71.6Mlbs. This means there is substantial scope to extend the mine life
and increase the EFS production nameplate capacity of 2.45Mlb/annum from the remaining identified
JORC Resource. There are also significant resource growth opportunities from the Company’s satellite
deposits and significant defined Exploration Target3.
The Company anticipates the satellite resources to allow both an increase in the overall production profile
with minimal disturbance to operations and extend the mine life of the Honeymoon Project. Boss holds
high expectations that its exploration activities will continue to deliver increase Resources. The Company
has grown the global JORC resource from 16.6Mlbs to 71.6Mlbs (~4.3x increase) since acquiring
Honeymoon in December 2015.
4 Refer to ASX: BOE announcement dated 8 April 2016.
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
@Boss_Energy
This ASX announcement was approved and authorised by the Board of Boss Energy Limited.
For further information, contact:
Duncan Craib
Chief Executive Officer
P: +61 (8) 6263 4494
E: boss@bossenergy.com
For media enquiries, contact:
Paul Armstrong
Read Corporate
P: +61 (8) 9388 1474
E: info@readcorporate.com
Competent Person’s Statement
The information contained in this announcement that relates to exploration results is provided by Mr
Jason Cherry, who is a Member of the Australasian Institute of Geoscientists (AIG). Mr Cherry has
sufficient experience that is relevant to the style of mineralisation and type of deposit under
consideration, and to the activity being undertaken to qualify as a Competent Person, as defined in the
JORC 2012 edition of the “Australasian Code for Reporting of Mineral Resources and Ore Reserves”. Mr
Cherry has 17 years’ experience and is a full-time employee as Geology Manager for Boss Energy Ltd. Mr
Cherry consents to the inclusion in this report of the matters based on this information in the form and
context in which they appear.
Reference to previous ASX announcements
In relation to the results of the Feasibility Study announced 21 January 2020, the Company confirms that
all material assumptions underpinning the production target and forecast financial information included
in that announcement continue to apply and have not materially changed. Nothing in this announcement
pre-empts the findings of the Enhanced Feasibility Study currently being undertaken.
In relation to the Mineral Resource announced on 8 April 2016, 25 February 2019 and the Exploration
Targets announced on 25 March 2019, the Company confirms that it is not aware of any new information
or data that materially affects the information included in the original market announcement and that all
material assumptions and technical parameters underpinning the estimates in that market
announcement continue to apply and have not materially changed.
Forward-Looking Statements
This announcement includes forward-looking statements. These forward-looking statements are based
on the Company’s expectations and beliefs concerning future events. Forward-looking statements are
necessarily subject to risks, uncertainties, and other factors, many of which are outside the control of Boss
Energy, which could cause actual results to differ materially from such statements. Boss Energy makes no
undertaking to subsequently update or revise the forward-looking statements made in this
announcement, to reflect the circumstances or events after the date of this announcement.
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
@Boss_Energy
APPENDIX 1 – Table 1: Historical drill results
In accordance with ASX Listing Rule 5.7.2, the Company provides the following information:
Table 1: Summary of historical drill holes listed within this report.
All holes were drilled vertically (-90˚ inclination and 0˚ azimuth).
Hole ID
Easting
Northing
MGA94, z54
RL
EOH
From
To
Width
pU3O8
(m)
(m)
(m)
92.90
102.10
92.95
102.95
105.79
101.5
(m)
93.50
105.10
95.70
103.70
108.54
105.5
(m)
0.60
3.00
2.75
0.75
2.75
4.00
(ppm)
700
1,040
1,056
2,455
3,898
1,611
Grade
Thickness
(m.ppm)
420
3,120
2,904
1,841
10,720
6,444
82.50
96.00
101.75
86.50
95.75
105.50
83.00
96.50
103.00
87.50
97.50
107.50
0.50
0.50
1.25
1.00
1.75
2.00
651
845
2,579
1,610
471
4,428
326
423
3,224
1,610
824
8,856
580_018 *
467531
6500114
97
112
YAM040
467,592
6,500,808
96
128
BMW001
467,544
6,500,777
96
115
BMR014
466,521
6,502,072
95
120
BMR043
467,738
6,500,637
96
114
All results reported as PFN-derived pU3O8 in the above table unless otherwise indicated.
* indicates gamma-derived equivalent eU3O8.
Values are reported above the nominal 250ppm eU3O8 cutoff grade, 0.5m minimum interval thickness
and maximum 1m internal dilution.
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
@Boss_Energy
JORC Code, 2012 Edition – Table 1
Section 1 – Sampling Techniques and Data
(Criteria in this section apply to all succeeding sections.)
Criteria
JORC Code explanation
Commentary
Sampling
techniques
• Nature and quality of sampling (eg cut channels, random chips, or specific
specialised industry standard measurement tools appropriate to the
minerals under investigation, such as down hole gamma sondes, or
handheld XRF instruments, etc). These examples should not be taken as
limiting the broad meaning of sampling.
• Include reference to measures taken to ensure sample representivity and the
appropriate calibration of any measurement tools or systems used.
• Aspects of the determination of mineralisation that are Material to the
Public Report.
• In cases where ‘industry standard’ work has been done this would be
relatively simple (eg ‘reverse circulation drilling was used to obtain 1 m
samples from which 3 kg was pulverised to produce a 30 g charge for fire
assay’). In other cases more explanation may be required, such as where
there is coarse gold that has inherent sampling problems. Unusual
commodities or mineralisation types (eg submarine nodules) may warrant
disclosure of detailed information.
• Historic uranium grade data from the 580 series drilling (completed during
the 1970s by Sedimentary Uranium N.L) was digitised from paper logs by
Southern Cross Resources.
• The YAM series drill holes were completed by Southern Cross Resources in
2004 have been geophysically logged upon completion with a combination of
Prompt Fission Neutron (PFN), calibrated gamma, conductivity & guard tool.
Data is collected at 1cm intervals and incorporated in the Boss Energy drilling
database.
• The BMR and BMW series holes were completed by Boss Resources in 2016
and geophysically logged with Prompt Fission Neutron (PFN) tools by Boss
Energy, along with calibrated gamma, formation density, induction and dual
laterolog tools by external contractor Borehole Wireline. Data was collected
at 1cm intervals and incorporated into the Boss Energy database
• All natural gamma and Prompt Fission Neutron (PFN) tools used during this
drilling program were calibrated at the PIRSA calibration facility in Adelaide
prior to the program commencing.
Drilling
techniques
• Drill type (eg core, reverse circulation, open-hole hammer, rotary air blast,
auger, Bangka, sonic, etc) and details (eg core diameter, triple or standard
tube, depth of diamond tails, face-sampling bit or other type, whether core
is oriented and if so, by what method, etc).
• The drilling technique used for all holes was Rotary Mud, with the YAM, BMR
and BMW series drill holes completed by highly experienced contractor
Watson Drilling. Drill cuttings were collected at 1m intervals for geological
logging.
• Given the historic nature of the 580 series drill holes, it is not possible to
provide further drilling details.
Drill sample
recovery
• Method of recording and assessing core and chip sample recoveries and
results assessed.
• Measures taken to maximise sample recovery and ensure representative
nature of the samples.
• Whether a relationship exists between sample recovery and grade and
whether sample bias may have occurred due to preferential loss/gain of
fine/coarse material.
• Drill chips for the YAM, BMR and BMW series holes were collected for
geological logging purposes only, with good to very good sample recoveries.
• Given the historic nature of the 580 series drill holes, it is not possible to
provide further comment on sample recoveries.
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
@Boss_Energy
Criteria
JORC Code explanation
Commentary
Logging
• Whether core and chip samples have been geologically and geotechnically
logged to a level of detail to support appropriate Mineral Resource
estimation, mining studies and metallurgical studies.
• Whether logging is qualitative or quantitative in nature. Core (or costean,
channel, etc) photography.
• The total length and percentage of the relevant intersections logged.
• If core, whether cut or sawn and whether quarter, half or all core taken.
• If non-core, whether riffled, tube sampled, rotary split, etc and whether
sampled wet or dry.
• For all sample types, the nature, quality and appropriateness of the sample
preparation technique.
• Quality control procedures adopted for all sub-sampling stages to maximise
representivity of samples.
• Measures taken to ensure that the sampling is representative of the in situ
material collected, including for instance results for field duplicate/secondhalf sampling.
• Whether sample sizes are appropriate to the grain size of the material being
sampled.
• All drill holes have been geologically logged and incorporated into the Boss
Energy database.
Quality of
assay data and
laboratory
tests
• The nature, quality and appropriateness of the assaying and laboratory
procedures used and whether the technique is considered partial or total.
• For geophysical tools, spectrometers, handheld XRF instruments, etc, the
parameters used in determining the analysis including instrument make and
model, reading times, calibrations factors applied and their derivation, etc.
• Nature of quality control procedures adopted (eg standards, blanks,
duplicates, external laboratory checks) and whether acceptable levels of
accuracy (ie lack of bias) and precision have been established.
• All PFN and gamma tools being used as part of the current drilling campaign
have been calibrated at the PIRSA calibration facility in Adelaide by both Boss
Energy and logging contractor Borehole Wireline prior to the program
commencing.
• Multiple PFN tools will be run in a number of holes throughout the upcoming
program as a QA/QC check.
• Given the historic nature of the 580 series holes, it is not possible to comment
on the calibration of gamma logging tools carried out at the time.
Verification of
sampling and
assaying
• The verification of significant intersections by either independent or
alternative company personnel.
• The use of twinned holes.
• Documentation of primary data, data entry procedures, data verification,
data storage (physical and electronic) protocols.
• Discuss any adjustment to assay data.
• A number of twin holes are being drilled as part of the current campaign. The
PFN and calibrated gamma results from this drilling will be used to verify
previous PFN results and also to verify/upgrade the historic gamma logging
from the 1970s.
• Natural gamma logs are used to depth match all geophysical tool runs to
ensure accuracy.
Sub-sampling
techniques and
sample
preparation
ASX: BOE
OTCQX: BQSSF
• The PFN tool has a depth of investigation radius of approximately 25-40 cm
around the borehole. This provides an accurate measurement of
epithermal/thermal neutron ratios for the calculation of pU3O8.
• No chemical assay sampling was carried out for the drill holes in question.
• Given the historic nature of the 580 series holes, it is not possible to comment
on the gamma logging carried out at the time.
www.bossenergy.com
@Boss_Energy
Criteria
JORC Code explanation
Commentary
Location of
data points
• Accuracy and quality of surveys used to locate drill holes (collar and downhole surveys), trenches, mine workings and other locations used in Mineral
Resource estimation.
• Specification of the grid system used.
• Quality and adequacy of topographic control.
• The YAM, BMR and BMW series drill holes were pegged using a hand-held
Garmin GPS with a nominal accuracy of ±5m. Coordinates are cited in MGA94
grid, z54.
• Given the historical nature of the 580 series drill holes, it is not possible to
comment further on the pegging method. In most cases, the collar locations
have been identified in the field and verified this way.
Data spacing
and
distribution
• Data spacing for reporting of Exploration Results.
• Whether the data spacing and distribution is sufficient to establish the
degree of geological and grade continuity appropriate for the Mineral
Resource and Ore Reserve estimation procedure(s) and classifications
applied.
• Whether sample compositing has been applied.
• The Competent Person has reviewed all available data and, based on their
knowledge and experience with the various exploration techniques
employed, is satisfied that the historical drilling data included here is of
sufficient quality and accuracy to provide a reasonable, if indicative, basis for
the mineralisation reported herein.
• The current drill line spacing at the Jason’s deposit ranges from ~100m to
more commonly up to 250m along strike. Hole spacing along drill lines ranges
from 80m to more commonly ~200m.
• All PFN and gamma-derived eU3O8 data (both new and historic) has been
composited to 25cm intervals where possible.
Orientation of
data in relation
to geological
structure
• Whether the orientation of sampling achieves unbiased sampling of possible
structures and the extent to which this is known, considering the deposit
type.
• If the relationship between the drilling orientation and the orientation of key
mineralised structures is considered to have introduced a sampling bias, this
should be assessed and reported if material.
• The measures taken to ensure sample security.
• All new & historical holes were drilled vertically which provides an accurate
intersection of the flat laying mineralised bodies.
• The results of any audits or reviews of sampling techniques and data.
• All historical information and data used in this report have been reviewed by
the Boss Energy Competent Person and has been deemed appropriate for
use.
Sample
security
Audits or
reviews
ASX: BOE
OTCQX: BQSSF
• Not applicable.
www.bossenergy.com
@Boss_Energy
Section 2 – Reporting of Exploration Results
(Criteria listed in the preceding section also apply to this section)
Criteria
JORC Code explanation
Commentary
• Type, reference name/number, location and ownership including
agreements or material issues with third parties such as joint ventures,
partnerships, overriding royalties, native title interests, historical sites,
wilderness or national park and environmental settings.
• The security of the tenure held at the time of reporting along with any
known impediments to obtaining a licence to operate in the area.
• Acknowledgment and appraisal of exploration by other parties.
• The Project consists of 1 granted Mining Lease, 5 granted Exploration
Licenses, 3 Retention Leases and 2 Miscellaneous Purpose Licenses.
Geology
• Deposit type, geological setting and style of mineralisation.
Palaeovalley-type, sand-hosted, tabular style uranium of the following model:
• Narrower, mineralised, palaeochannels within a broader palaeovalley system,
• Underlying basement faults reactivated sporadically, greatly influencing the
shape and formation of the overlying fluvial system, creating uplifted ridges
of basement and the meandering narrow palaeochannels described above;
• REDOX interfaces from the vertical and lateral movement of uraniferous
(oxidised) fluids from south (granitic source rocks in the Olary Ranges) to
north (towards Lake Frome);
• Organic/sulphide-rich horizons and possible hydrocarbon fluids, the latter
seeping upwards along the basement faults. Organic- and sulphide-rich
material formed within shallow channel embankments and ledges.
Drill hole
Information
• A summary of all information material to the understanding of the
exploration results including a tabulation of the following information for all
Material drill holes:
o easting and northing of the drill hole collar
o elevation or RL (Reduced Level – elevation above sea level in metres) of
the drill hole collar
o dip and azimuth of the hole
o down hole length and interception depth
o hole length.
• Please refer to Appendix 1, Table 1 for drill collar information.
Mineral
tenement and
land tenure
status
Exploration
done by other
parties
ASX: BOE
OTCQX: BQSSF
• The Honeymoon deposit and surrounding areas of the Yarramba palaeovalley
have been subject to exploration activities periodically since the early 1970s.
• The Honeymoon Project was evaluated several times, with the degree of
details varying from scoping studies to bankable feasibility undertaken in
2006. Resource estimates have been made from 1998 to 2019.
www.bossenergy.com
@Boss_Energy
Criteria
Data
aggregation
methods
Relationship
between
mineralisation
widths and
intercept
lengths
Diagrams
Balanced
reporting
Other
substantive
exploration
data
ASX: BOE
JORC Code explanation
Commentary
• If the exclusion of this information is justified on the basis that the
information is not Material and this exclusion does not detract from the
understanding of the report, the Competent Person should clearly explain
why this is the case.
• In reporting Exploration Results, weighting averaging techniques, maximum
and/or minimum grade truncations (eg cutting of high grades) and cut-off
grades are usually Material and should be stated.
• Where aggregate intercepts incorporate short lengths of high grade results
and longer lengths of low grade results, the procedure used for such
aggregation should be stated and some typical examples of such
aggregations should be shown in detail.
• The assumptions used for any reporting of metal equivalent values should
be clearly stated.
• These relationships are particularly important in the reporting of Exploration
Results.
• If the geometry of the mineralisation with respect to the drill hole angle is
known, its nature should be reported.
• If it is not known and only the down hole lengths are reported, there should
be a clear statement to this effect (eg ‘down hole length, true width not
known’).
• Appropriate maps and sections (with scales) and tabulations of intercepts
should be included for any significant discovery being reported These should
include, but not be limited to a plan view of drill hole collar locations and
appropriate sectional views.
• Where comprehensive reporting of all Exploration Results is not practicable,
representative reporting of both low and high grades and/or widths should
be practiced to avoid misleading reporting of Exploration Results.
• Other exploration data, if meaningful and material, should be reported
including (but not limited to): geological observations; geophysical survey
results; geochemical survey results; bulk samples – size and method of
treatment; metallurgical test results; bulk density, groundwater,
geotechnical and rock characteristics; potential deleterious or
contaminating substances.
OTCQX: BQSSF
• Mineralised intervals were chosen based upon a nominal 250ppm U3O8
cutoff, 0.50 m minimum interval thickness and maximum 1m internal dilution
for reporting. Where available, Prompt Fission Neutron (PFN) data is used
which is designated pU3O8. For historical drilling or in instances during
modern drilling where the PFN tool data was unavailable, gamma tool derived
data is used which is designated eU3O8 and may be affected by radiometric
disequilibrium.
• Historic drill traverses were oriented at oblique angles across the strike of the
palaeovalley as per the historical interpretation current at the time of drilling.
• Modern drill traverses are often oriented at right angle across the domain
strike, although this can vary depending on the interpreted geological setting
of each area.
• Appropriate and relevant diagrams have been included in the announcement
• Balanced reporting has been adhered to. See previous exploration
announcements.
• Not applicable.
www.bossenergy.com
@Boss_Energy
Criteria
JORC Code explanation
Commentary
Further work
• The nature and scale of planned further work (eg tests for lateral extensions
or depth extensions or large-scale step-out drilling).
• Diagrams clearly highlighting the areas of possible extensions, including the
main geological interpretations and future drilling areas, provided this
information is not commercially sensitive.
• Further work will involve a combination of twinning historical drill holes (to
verify grade data) and if justified step-out drilling of these holes to test for
continuity of mineralisation.
• All results will be used to update the resource model upon the completion of
drilling.
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
@Boss_Energy