Honeymoon start-up wells yield production-grade uranium
Released
Released
Announcement PDF
ASX Release November 30, 2023
Honeymoon Uranium Project, South Australia
Pre-flushing of start-up wells yields
production-grade uranium
Latest milestone achievement ensures project remains on time and budget, with
processing ponds set to be filled with Pregnant Leach Solution this year
Boss Energy Limited (ASX: BOE; OTCQX: BQSSF) is pleased to announce it has passed another key
milestone in the development of its Honeymoon project, with production-grade uranium generated
during the pre-flushing of the start-up wells.
This is significant because it shows Boss is on track to fill the Pregnant Leach Solution (PLS) processing
ponds by the end of this calendar year in line with the overall development timetable.
Boss Managing Director Duncan Craib said: “To see production-grade uranium in well pre-flushing augurs
extremely well for the start of commissioning and production ramp-up.
“We continue to execute our development strategy in line with the timetable and budget.
“With the uranium price recently hitting a 15-year high of US$81 a pound1, we are perfectly positioned to
capitalise on this huge opportunity.
“Our position is further strengthened by the fact that we have no debt, cash on hand of $63 million2 and
a strategic uranium stockpile now worth $1563 million based on current spot prices, representing a book
profit of more than $100M since acquisition in March 2021”.
Procurement
Committed expenditure under the Honeymoon re-development program now totals A$98M (or 92%) of
the budgeted ~A$106M CAPEX, excluding a A$7M contingency, with incurred costs amounting to A$81M.
All critical path items remain on track for delivery in line with the project schedule. More than 279
procurement packages have been issued. The packages awarded to date are in line with the front-end
engineering design (FEED) released to the ASX on 31 March 2022.
ISR Wellfields
Pre-conditioning of Honeymoon’s start-up wells to facilitate efficient leaching and uranium capture are
already showing leached uranium in the solution. Targeted calcium and chlorides are being removed from
the orebody, leading to highly favourable flushing results.
1 Source: TradeTech, LLC (www.uranium.info) as at 24 November 2023
2 As at 30 September 2023 (excluding 100% cash backed environmental bond of approximately A$9M)
3 Strategic uranium stockpile valued at A$156M based on a spot U O price of US$81/lb and an exchange rate of A$1:US$0.65
3 8
FOR FURTHER INFORMATION PLEASE CONTACT:
Boss Energy Limited
ABN 38 116 834 336
Duncan Craib - Managing Director/ CEO
+61 (08) 6263 4494
ASX: BOE
OTCQX: BQSSF
Level 1, 420 Hay Street, Subiaco
Western Australia 6008
Paul Armstrong – Public Relations
+61 (08) 9388 1474
www.bossenergy.com
@Boss_Energy
Once flushed, Honeymoon will start the leaching with optimal lixiviant to achieve targeted tenors of
uranium. This involves fortifying the pre-conditioned groundwater with reagents prior to injecting the
lixiviant into and through the orebody to dissolve uranium. The uranium-rich solution is then pumped to
the surface via extraction wells and discharged to the Pregnant Leach Solution (PLS) process ponds.
Uranium is captured via Ion Exchange (IX), precipitated and calcined to produce a high-quality saleable
uranium oxide (U3O8) product.
Honeymoon’s goal is to fill the PLS pond this calendar year in preparation for commissioning the IX circuit
in January with the first drum of uranium on track to be produced as planned in Q1 2024.
The supporting infrastructure is operating to design specifications, including the raw water system, the
25,000 ton gypsum repository, reagent handling systems and first fills of key reagents.
Figure 1: Pre-flushing of the Start-up Wellfields
IX Processing Plant
The first set of NIMCIX loading and elution columns for the new Ion Exchange (IX) circuit have been
installed, with electrical and piping works nearing completion. Delivery of 160,000 litres of IX resin has
been completed to facilitate the process, enough to operate one column for 10 years.
The adop on of IX technology, which is central to the processing plant, will enable highly efficient capture,
concentra on and purifica on of the uranium from the wellfields. This will result in increased throughput,
more produc on and lower costs than was possible using the solvent extrac on system previously
employed at Honeymoon.
The IX circuit will drive efficiencies at Honeymoon, increasing production throughput to nameplate
capacity of 2.45Mlb/annum of U3O8 while reducing ramp up time and technical risks. It will also reduce
operating costs to industry benchmarks. This was proven by the extensive tests conducted by Boss and
leading independent industry experts, before and during the Honeymoon feasibility studies.
Although not needed for first production, the next two IX circuits arrived in Port Adelaide this week.
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
@Boss_Energy
Figure 2: Installation of last section of the absorption Column 1 & steelworks
Commissioned plant currently operating includes:
Safety showers
High-pressure air services
Reverse Osmosis (RO) Plant
Water Treatment Plant (WTP)
Start-up wellfield injection/ extraction wells
25,000 ton gypsum repository
Potable water RO plant
Borefields
This ASX announcement was approved and authorised by the Board of Boss Energy Limited.
For further information, contact:
Duncan Craib
Chief Executive Officer
P: +61 (8) 6263 4494
E: boss@bossenergy.com
For media enquiries, contact:
Paul Armstrong
Read Corporate
P: +61 (8) 9388 1474
E: info@readcorporate.com
ASX: BOE
www.bossenergy.com
OTCQX: BQSSF
@Boss_Energy
Forward-Looking Statements
This announcement includes forward-looking statements. These forward-looking statements are based
on the Company’s expectations and beliefs concerning future events. Forward-looking statements are
necessarily subject to risks, uncertainties and other factors, many of which are outside the control of Boss,
which could cause actual results to differ materially from such statements. Boss makes no undertaking to
subsequently update or revise the forward-looking statements made in this announcement, to reflect the
circumstances or events after the date of this announcement.