Maiden copper exploration program intersects mineralisation
Released
Released
Announcement PDF
ASX Release May 15, 2024
Honeymoon Uranium Project, South Australia
Maiden copper exploration program
intersects encouraging mineralisation
The results come from First Quantum Minerals’ initial drilling program at Honeymoon; In light of
these results, First Quantum has committed to proceeding with Phase 2 of the farm-in program
Highlights
• First results received from copper exploration program conducted by First Quantum under its
farm-in agreement with Boss at Honeymoon; Assays include:
•
23CURDD002: 16m @ 0.27% Cu and 0.1g/t Au, from 288m, and;
•
23CURDD006: 47m @ 0.19% Cu from 404m, with a number of narrower zones of 5-6m
containing up to 0.5% Cu and 0.12g/t Au.
• The Boss- First Quantum agreement gives First Quantum the right to earn a 51% interest in
Honeymoon’s base metal endowment by spending $6m on exploration and a further 24%
interest by sole-funding all base metals expenditure up to a Decision to Mine
• The agreement enables Boss to remain fully-focused on its core business of uranium exploration,
development and production while having exposure at no cost to the significant potential of a
base metals exploration program led by a global major
Boss Energy Limited (ASX: BOE; OTCQX: BQSSF) is pleased to announce that First Quantum Minerals’
(TSE:FM) (First Quantum) maiden diamond drilling program on Honeymoon’s tenements in South
Australia has successfully intersected basement-hosted base metal mineralisation below the Yarramba
Palaeovalley which holds the uranium.
Figure 1: Stratiform and vein-hosted chalcopyrite mineralisation in metasiltstones at Atlas target
FOR FURTHER INFORMATION PLEASE CONTACT:
Boss Energy Limited
ABN 38 116 834 336
Duncan Craib - Managing Director/ CEO
+61 (08) 6263 4494
ASX: BOE
OTCQX: BQSSF
Level 1, 420 Hay Street, Subiaco
Western Australia 6008
Paul Armstrong – Public Relations
+61 (08) 9388 1474
www.bossenergy.com
@Boss_Energy
Summary of drilling results from First Quantum 2023 drilling on EL6081 and EL6510
Following a phase of regional data assessment and targeting for base metals in the Paleo-Mesoproterozoic
basement stratigraphy, a rotary mud-diamond drilling program was conducted on EL6081 and EL6510
during October-December 2023. Six holes totalling 2,473.4m across three targets were completed by
DDH1 Drilling. The program intended to test several target styles associated with the Bimba Formation,
the regionally anomalous unit that hosts the majority of known base and precious metal occurrences in
the region.
Atlas target
Three holes totalling 1,029.5m were completed at the Atlas target, 4km east of Honeymoon. Drilling
yielded several zones of stratiform and vein-hosted copper mineralisation with minor gold and outboard
weak zinc at the interpreted Bimba Formation position, in two holes separated by 1.3km strike length.
Mineralised intercepts include 16m @ 0.27% Cu and 0.1g/t Au, from 288m (23CURDD002) and 47m @
0.19% Cu from 404m (23CURDD006), with a number of narrower zones of 5-6m containing up to 0.5%
Cu and 0.12g/t Au. The intercepts are proof of process; evidence for movement and precipitation of
copper (~gold/~zinc) within the Bimba Formation in the target area.
Table 1: Atlas target intercept table. 0.1% Cu and Zn cutoff, <6m internal dilution
Pandora target
Two holes totalling 701.6m were completed at the Pandora target, 8km south of Honeymoon. One hole
intersected an interval of stratiform low grade zinc-bearing stratigraphy, inferred to be the upper portion
of the Bimba Formation. This zone potentially lies outboard of a lower copper (~gold) zone, at the
currently untested base of the Bimba Formation.
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
@Boss_Energy
Yarramba target
One deep drillhole totalling 742.3m was completed at the Yarramba dome target, 15km north of
Honeymoon. The hole targeted the inferred base of Bimba Formation and magnetic footwall beneath,
based on magnetic inversion modelling and geological interpretations. Whilst geometrically the apex of
the dome was well-tested, neither the target horizon nor any appreciable mineralisation was intersected
at economic depths; the target has been downgraded as a result.
Figure 2: RTP 1VD aeromagnetic image with location of targets and drill holes
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
@Boss_Energy
Earn-in and Joint Venture Principles
Boss Energy entered into an exploration earn-in agreement with First Quantum in February 2022. First
Quantum is a significant Canadian-listed group operating eight mines across four continents producing
copper, nickel, and gold with an additional three mines under development. With a proven track record
in discovering and developing deposits, Boss considers First Quantum an ideal partner in the exploration
and potential development of any base metal discoveries at Honeymoon.
The Agreement relates to base metals rights over the following 5 tenements at Boss' Honeymoon
Uranium Project: EL 6512, EL 6511, EL 6020, EL 6510, EL 6081 (collectively referred to as the "JV
Project").
Following receipt of these results, First Quantum has elected to continue to fund further exploration
under a joint venture agreement. Under the agreement First Quantum has the right but not the
obligation to spend $6M on exploration within 5 years, and maintain a minimum annual expenditure on
the JV Project of $500,000 per year. If First Quantum completes these obligations it will earn an initial
51% interest in the project ("First Earn-in").
First Quantum may elect to earn an additional 24% interest in the JV Project for a total interest of 75%
by sole funding expenditure on the JV Project until a Decision to Mine within 5 years and maintaining
minimum annual expenditure on the JV Project of $500,000 ("Second Earn-in"). First Quantum may
extend the Second Earn-in up to 10 years by increasing minimum annual expenditure on the JV Project
to $1M.
After acquiring a 75% interest, First Quantum shall continue to sole fund required studies and programs
up to receipt of all permits for commencement of construction, after which Boss can maintain its project
interest of 25% by funding its share of project development costs or dilute.
If First Quantum does not complete the Second Earn-in, Boss' interest in the JV Project will revert to 51%
with First Quantum retaining a 49% interest.
Boss shall be the operator of the JV Project until First Quantum has acquired a 51% interest after which
First Quantum can opt to become the operator.
Boss retains the sole right to explore for and exploit all uranium discoveries on the JV Project (being
greater than 50% of the in-situ metal value being uranium). Boss will have a first right of offer in respect
of any uranium discoveries made by First Quantum within the Curnamona craton of South Australia.
First Quantum may withdraw from the JV Project at any point pursuant to 60 days' notice. If the
withdrawal occurs after FMQ has earned a 51% interest, but prior earning a 75% interest, Boss shall
revert to a 51% interest. Should either party's interest fall below 10%, its interest will convert to a 1%
net smelter royalty.
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
@Boss_Energy
Figure 3: Diamond drilling at Atlas target, 4km east of Honeymoon mine
This ASX announcement was approved and authorised by the Board of Boss Energy Limited.
For further information, contact:
Duncan Craib
Chief Executive Officer
P: +61 (8) 6263 4494
E: boss@bossenergy.com
For media enquiries, contact:
Paul Armstrong
Read Corporate
P: +61 (8) 9388 1474
E: info@readcorporate.com
About Boss Energy Limited
Boss Energy Limited (ASX: BOE; OTCQX: BQSSF) (Boss Energy or the Company), is ramping up uranium
production at its Honeymoon Uranium Project in South Australia. Annual production at Honeymoon is
forecast to reach 2.45Mlbs of U3O8. Boss also owns 30 per cent of the Alta Mesa uranium project in Texas,
USA. Production at Alta Mesa is ramping up to 1.5Mlbs of U3O8 a year. For more information please
visit www.bossenergy.com
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
@Boss_Energy
Competent Person’s Statement
The information contained in this announcement that relates to exploration results is provided by Mr
Michael Christie, who is a Member of the Australasian Institute of Geoscientists (AIG). Mr Christie has
sufficient experience that is relevant to the style of mineralisation and type of deposit under
consideration, and to the activity being undertaken to qualify as a Competent Person, as defined in the
JORC 2012 edition of the “Australasian Code for Reporting of Mineral Resources and Ore Reserves”. Mr
Christie has 38 years’ experience and is a full-time employee as Director Exploration for First Quantum
Minerals Ltd. Mr Christie consents to the inclusion in this report of the matters based on this information
in the form and context in which they appear.
Forward-Looking Statements
This announcement includes forward-looking statements. These forward-looking statements are based
on the Company’s expectations and beliefs concerning future events. Forward-looking statements are
necessarily subject to risks, uncertainties, and other factors, many of which are outside the control of Boss
Energy, which could cause actual results to differ materially from such statements. Boss Energy makes no
undertaking to subsequently update or revise the forward-looking statements made in this
announcement, to reflect the circumstances or events after the date of this announcement.
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
@Boss_Energy
APPENDIX 1 – Table 1: Drill collar table
In accordance with ASX Listing Rule 5.7.2, the Company provides the following information:
Hole ID
Easting
Northing
MGA94, z54
23CURDD001
23CURDD002
23CURDD003
23CURDD004
23CURDD005
23CURDD006
ASX: BOE
OTCQX: BQSSF
472911
472706
465513
465495
468415
471792
6488778
6489074
6481228
6479843
6503346
6488124
RL
EOH
Azimuth
Dip
(m)
(m)
Deg (˚)
Deg (˚)
137
123
133
137
90
129
195.5
358.5
482.3
219.3
742.3
484.9
147
147
180
295
330
149
-60
-60
-60
-60
-80
-70
www.bossenergy.com
@Boss_Energy
JORC Code, 2012 Edition – Table 1
Section 1 – Sampling Techniques and Data
(Criteria in this section apply to all succeeding sections.)
Criteria
JORC Code explanation
Sampling
techniques
Drilling
techniques
Drill sample
recovery
ASX: BOE
Commentary
• Nature and quality of sampling (eg cut channels, random chips, or specific
specialised industry standard measurement tools appropriate to the
minerals under investigation, such as down hole gamma sondes, or
handheld XRF instruments, etc). These examples should not be taken as
limiting the broad meaning of sampling.
• Include reference to measures taken to ensure sample representivity and the
appropriate calibration of any measurement tools or systems used.
• Aspects of the determination of mineralisation that are Material to the
Public Report.
• In cases where ‘industry standard’ work has been done this would be
relatively simple (eg ‘reverse circulation drilling was used to obtain 1 m
samples from which 3 kg was pulverised to produce a 30 g charge for fire
assay’). In other cases more explanation may be required, such as where
there is coarse gold that has inherent sampling problems. Unusual
commodities or mineralisation types (eg submarine nodules) may warrant
disclosure of detailed information.
• Drill type (eg core, reverse circulation, open-hole hammer, rotary air blast,
auger, Bangka, sonic, etc) and details (eg core diameter, triple or standard
tube, depth of diamond tails, face-sampling bit or other type, whether core
is oriented and if so, by what method, etc).
•
•
•
•
•
Drilling was conducted using rotary mud through the Cenozoic cover
sequence followed by diamond drilling using standard HQ and NQ tube.
Drill holes were angled
Holes were oriented using the Reflex ActIII electronic orientation tool
Downhole surveys were conducted using the Axis North Seeking Gyro
• Method of recording and assessing core and chip sample recoveries and
results assessed.
• Measures taken to maximise sample recovery and ensure representative
nature of the samples.
• Whether a relationship exists between sample recovery and grade and
whether sample bias may have occurred due to preferential loss/gain of
fine/coarse material.
•
•
•
Core recovery is expressed as a percentage.
Overall core recoveries averaged over 98%.
There is no relationship between sample recovery and grade.
OTCQX: BQSSF
•
•
•
•
All core was logged and photographed prior to cutting.
Core was sampled at nominally 2m intervals, reducing to 1m in
mineralisation.
Holes that did not intersect target stratigraphy were subject to 2m
samples at 10-20m intervals throughout the hole.
Adjustments were made for major geological boundaries or major visual
changes in mineralisation grade or style. Sample lengths range between
0.5m and 3m.
Half diamond drill core samples are submitted to ALS for preparation
and assay; all assay results have been received.
www.bossenergy.com
@Boss_Energy
Criteria
JORC Code explanation
Commentary
Logging
• Whether core and chip samples have been geologically and geotechnically
logged to a level of detail to support appropriate Mineral Resource
estimation, mining studies and metallurgical studies.
• Whether logging is qualitative or quantitative in nature. Core (or costean,
channel, etc) photography.
• The total length and percentage of the relevant intersections logged.
•
•
•
•
•
Sub-sampling
techniques and
sample
preparation
Quality of
assay data and
laboratory
tests
ASX: BOE
• If core, whether cut or sawn and whether quarter, half or all core taken.
• If non-core, whether riffled, tube sampled, rotary split, etc and whether
sampled wet or dry.
• For all sample types, the nature, quality and appropriateness of the sample
preparation technique.
• Quality control procedures adopted for all sub-sampling stages to maximise
representivity of samples.
• Measures taken to ensure that the sampling is representative of the in situ
material collected, including for instance results for field duplicate/secondhalf sampling.
• Whether sample sizes are appropriate to the grain size of the material being
sampled.
•
• The nature, quality and appropriateness of the assaying and laboratory
procedures used and whether the technique is considered partial or total.
• For geophysical tools, spectrometers, handheld XRF instruments, etc, the
parameters used in determining the analysis including instrument make and
model, reading times, calibrations factors applied and their derivation, etc.
• Nature of quality control procedures adopted (eg standards, blanks,
duplicates, external laboratory checks) and whether acceptable levels of
accuracy (ie lack of bias) and precision have been established.
•
OTCQX: BQSSF
•
•
•
•
100% of diamond core was logged on site during the drilling program, a
total of 1813.2m
Logging included lithology, alteration, mineralisation and structure, both
qualitative and quantitative
Magnetic susceptibility measurements were collected at 1m intervals
downhole using a handheld magnetic susceptibility meter.
Core was photographed prior to cutting.
Rotary mud material drilled through the cover sequence was also
logged.
Samples were transported to Adelaide for core cutting by Euro
Exploration Services.
Diamond core was cut and sampled as half core at nominally 2m
intervals, reducing to 1m in mineralisation.
Holes that did not intersect target stratigraphy or mineralisation were
subject to 2m samples at 10-20m intervals throughout the hole.
Adjustments were made for major geological boundaries or major visual
changes in mineralisation grade or style. Sample lengths range between
0.5m and 3m.
The sample sizes and sampling methods are considered appropriate for
the style of mineralisation at the project.
Core was transported to ALS Geochemistry in Adelaide for sample
preparation using method PREP-31; multielement assay was conducted
at ALS Geochemistry in Perth using ME-MS61, with select intervals
assayed for gold by method Au-ICP21:
o PREP-31: Crush to 70 % passing 2mm, riffle split off 250g, pulverise
split to better than 85% passing 75 microns.
o ME-MS61: Four acid digestion followed by ICP-MS measurement for
48 elements.
o Au-ICP21: Au by fire assay and ICP-AES.
www.bossenergy.com
@Boss_Energy
Criteria
JORC Code explanation
Commentary
•
•
Field QAQC protocol comprises rotating QAQC samples inserted every 20
samples (CRM standards, blanks and duplicates)
ALS also conducts its own QAQC sampling protocol in each sample batch.
Verification of
sampling and
assaying
• The verification of significant intersections by either independent or
alternative company personnel.
• The use of twinned holes.
• Documentation of primary data, data entry procedures, data verification,
data storage (physical and electronic) protocols.
• Discuss any adjustment to assay data.
• Mineralised intercepts have been visually verified by multiple members of the
geology team.
• Logging is entered into a field laptop using the LogChief software, using
logging codes and data validation.
• Data is loaded and stored in an SQL database.
Location of
data points
• Accuracy and quality of surveys used to locate drill holes (collar and downhole surveys), trenches, mine workings and other locations used in Mineral
Resource estimation.
• Specification of the grid system used.
• Quality and adequacy of topographic control.
• Data spacing for reporting of Exploration Results.
• Whether the data spacing and distribution is sufficient to establish the
degree of geological and grade continuity appropriate for the Mineral
Resource and Ore Reserve estimation procedure(s) and classifications
applied.
• Whether sample compositing has been applied.
• Whether the orientation of sampling achieves unbiased sampling of possible
structures and the extent to which this is known, considering the deposit
type.
• If the relationship between the drilling orientation and the orientation of key
mineralised structures is considered to have introduced a sampling bias, this
should be assessed and reported if material.
• The measures taken to ensure sample security.
•
Data spacing
and
distribution
Orientation of
data in relation
to geological
structure
Sample
security
ASX: BOE
OTCQX: BQSSF
•
Drillhole collars were sited using a handheld GPS with an accuracy of +/- 4
metres.
Drillhole coordinates are in GDA94 MGA Zone 54.
• The drilling completed to date is exploratory in nature, and the spacing is not
adequate for a mineral resource estimation.
• Reported mineralised intersections were aggregated using downhole length
weighting of consecutive sample assay results.
• To the best of our knowledge at this exploratory stage, drilling is broadly
perpendicular to geological contacts and a sampling bias has not been
introduced.
• Samples were stored onsite during the drilling program.
• On completion of the program, all diamond core was transported to Adelaide
for core cutting at Euro Exploration services, prior to dispatch to ALS for
sample preparation and analysis.
www.bossenergy.com
@Boss_Energy
Criteria
JORC Code explanation
Commentary
Audits or
reviews
• The results of any audits or reviews of sampling techniques and data.
• No formal auditing has been completed at this time.
• Sampling protocols are regularly reviewed internally.
Section 2 – Reporting of Exploration Results
(Criteria listed in the preceding section also apply to this section)
Criteria
JORC Code explanation
Commentary
Mineral
tenement and
land tenure
status
• Type, reference name/number, location and ownership including
agreements or material issues with third parties such as joint ventures,
partnerships, overriding royalties, native title interests, historical sites,
wilderness or national park and environmental settings.
• The security of the tenure held at the time of reporting along with any
known impediments to obtaining a licence to operate in the area.
• Acknowledgment and appraisal of exploration by other parties.
• The Project consists of 1 granted Mining Lease, 5 granted Exploration
Licenses, 3 Retention Leases and 2 Miscellaneous Purpose Licenses.
Geology
• Deposit type, geological setting and style of mineralisation.
• Base metal mineralisation (Zn, Pb, Ag, Cu) is hosted by the metasedimentary
units of the Bimba Formation, comprising graphitic pelites, psammites,
psammopelites, and calc-silicates. Mineralisation consists of conformable
bands and cross-cutting veins of chalcopyrite and/or pyrrhotite and or pyrite,
with minor amounts of sphalerite/galena.
Drill hole
Information
• A summary of all information material to the understanding of the
exploration results including a tabulation of the following information for all
Material drill holes:
o easting and northing of the drill hole collar
o elevation or RL (Reduced Level – elevation above sea level in metres) of
the drill hole collar
• Please refer to Appendix 1, Table 1 for drill collar information.
Exploration
done by other
parties
ASX: BOE
OTCQX: BQSSF
• Exploration for base metal deposits within the Honeymoon exploration
licences has occurred sporadically since the late 1980’s.
• The Honeymoon Project was evaluated several times, with the degree of
details varying from scoping studies to bankable feasibility undertaken in
2006. Resource estimates have been made from 1998 to 2019.
www.bossenergy.com
@Boss_Energy
Criteria
JORC Code explanation
•
Data
aggregation
methods
•
•
•
Relationship
between
mineralisation
widths and
intercept
lengths
•
Diagrams
•
Balanced
reporting
•
Other
substantive
•
ASX: BOE
•
•
Commentary
o dip and azimuth of the hole
o down hole length and interception depth
o hole length.
If the exclusion of this information is justified on the basis that the
information is not Material and this exclusion does not detract from the
understanding of the report, the Competent Person should clearly explain
why this is the case.
In reporting Exploration Results, weighting averaging techniques, maximum
and/or minimum grade truncations (eg cutting of high grades) and cut-off
grades are usually Material and should be stated.
Where aggregate intercepts incorporate short lengths of high grade results
and longer lengths of low grade results, the procedure used for such
aggregation should be stated and some typical examples of such
aggregations should be shown in detail.
The assumptions used for any reporting of metal equivalent values should
be clearly stated.
These relationships are particularly important in the reporting of Exploration
Results.
If the geometry of the mineralisation with respect to the drill hole angle is
known, its nature should be reported.
If it is not known and only the down hole lengths are reported, there should
be a clear statement to this effect (eg ‘down hole length, true width not
known’).
Appropriate maps and sections (with scales) and tabulations of intercepts
should be included for any significant discovery being reported These should
include, but not be limited to a plan view of drill hole collar locations and
appropriate sectional views.
Where comprehensive reporting of all Exploration Results is not practicable,
representative reporting of both low and high grades and/or widths should
be practiced to avoid misleading reporting of Exploration Results.
Other exploration data, if meaningful and material, should be reported
including (but not limited to): geological observations; geophysical survey
results; geochemical survey results; bulk samples – size and method of
OTCQX: BQSSF
•
•
Reported mineralised intersections were aggregated using downhole
length weighting of consecutive sample assay results.
Lower cut-offs of 0.1% Cu and 0.1% Zn used when aggregating
intersections.
Intersections contain a maximum of 6m continuous internal dilution.
•
Down hole length, true width not known
•
Appropriate and relevant diagrams have been included in the
announcement
•
Balanced reporting has been adhered to. See previous exploration
announcements.
•
Not applicable.
•
www.bossenergy.com
@Boss_Energy
Criteria
JORC Code explanation
exploration
data
treatment; metallurgical test results; bulk density, groundwater,
geotechnical and rock characteristics; potential deleterious or
contaminating substances.
• The nature and scale of planned further work (eg tests for lateral extensions
or depth extensions or large-scale step-out drilling).
• Diagrams clearly highlighting the areas of possible extensions, including the
main geological interpretations and future drilling areas, provided this
information is not commercially sensitive.
Further work
ASX: BOE
OTCQX: BQSSF
Commentary
•
•
•
Review of drilling geochemistry results, modelling; phase 2 drilling
proposal.
May-June 2024: heritage clearance survey with NAWNTAC.
June-July: proposed phase 2 drilling program.
www.bossenergy.com
@Boss_Energy
Share your feedback
Discover