Gould's Dam & Jason's Mineral Resource & Permitting Update
Released
Released
Announcement PDF
ASX Release 19 March 2026
FOR FURTHER INFORMATION PLEASE CONTACT:
Boss Energy Limited
ABN 38 116 834 336
Level 1, 420 Hay Street, Subiaco
Western Australia 6008
Matthew Dusci - Managing Director/ CEO
+61 (08) 6263 4494
Paul Armstrong – Media Relations
+61 (08) 9388 1474
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
@Boss_Energy
Gould’s Dam and Jason’s Deposit Mineral
Resource and Permitting Update
Highlights
Gould’s Dam Deposit Mineral Resource
• Gould’s Dam total Mineral Resource Estimate (MRE) is 38.7Mt @ 388ppm U3O8 for 33.1Mlbs of
contained U3O8 metal (23% Indicated; 77% Inferred Mineral Resource Classification).
• Total contained uranium has increased by 8.1Mlbs U3O8 (30%) and average grade has declined by
122ppm U3O8 (24%) from the previous resource estimate (2016).
• Mineral Resource update follows additional drilling and improved understanding gained from the
Honeymoon Operation.
• Mineralisation is generally hosted in highly permeable unconsolidated sands with the Mineral
Resource constrained to permeable sequence considered amenable to in-situ recovery (ISR) mining.
• Strong continuity of uranium mineralisation within the palaeochannel sequence over 15km.
• The wide-spaced wellfield extraction approach being studied for Honeymoon is likely to be
applicable to Gould’s Dam, which could potentially lead to conversion of a material portion of the
total Mineral Resource into a mine plan if successful.
• Further drilling is planned to increase the resource confidence and potentially expand the updated
resource.
Jason’s Deposit Mineral Resource
• Jason’s Deposit total MRE is 13.3Mt @ 410ppm U3O8 for 12.0Mlbs of uranium (41% Indicated; 59%
Inferred Mineral Resource Classification).
• Total contained uranium increased by 1.3Mlbs U3O8 (9%) and average grade has declined by 380ppm
U3O8 (48%) from the previous resource estimate (2017); Update follows additional drilling and
improved geological and mineralisation understanding.
• Mineralisation remains open, providing scope for additional drilling upside.
Development Pathway
• Development pathway for both Gould’s Dam and Jason’s Deposit accelerated over the past six
months with all baseline and technical studies for permitting applications being advanced.
• State and Federal approvals processes targeted to commence in the second-half CY26.
• Timing from initial applications to the granting of a mining lease is expected to take up to 18 to 24
months; subsequently, a further six to 12 months will be required for the Program for Environment
Protection and Rehabilitation (PEPR) approval process.
ASX: BOE OTCQX: BQSSF www.bossenergy.com @Boss_Energy
Boss Energy Limited (ASX: BOE; OTCQX: BQSSF) (Boss or the Company) is pleased to report updated
MREs for its satellite uranium deposits, Gould’s Dam and Jason’s Deposit, adjacent to its Honeymoon
Operation in South Australia. Gould’s Dam and Jason’s Deposit are located approximately 80km and
13km respectively from the producing Honeymoon Operation.
Table 1: Gould’s Dam and Jason's Mineral Resource Estimate (effective 31 December 2025)
Resource Category
Ore Grade Metal
Mt ppm U3O8 kt U3O8 Mlbs U3O8
GOULD'S DAM
Indicated 7.5 465 3.5 7.7
Inferred 31.2 369 11.5 25.4
TOTAL 38.7 388 15.0 33.1
JASON’S DEPOSIT
Indicated 4.8 464 2.2 4.9
Inferred 8.5 380 3.2 7.1
TOTAL 13.3 410 5.4 12.0
Notes:
• See sections below on Mineral Resource Reporting criteria.
Boss Managing Director Matthew Dusci said:
“Over the past six months, the Company has initiated several strategic programs aimed at unlocking
shareholder value. One of these is aimed at progressing the value realisation of Gould’s Dam and
Jason’s Deposit located close to the Honeymoon Operation.
“The updated Mineral Resource Estimates for Gould’s Dam and Jason’s Deposit incorporate additional
drilling and an improved understanding of geology and mineralisation controls derived from the
Honeymoon deposit. This work highlights the significance of these deposits, with Gould’s Dam and
Jason’s Deposit hosting 33Mlbs and 12Mlbs of uranium, respectively, with mineralisation at both
deposits remaining open. Further drilling programs are planned to commence in the second half of this
calendar year to continue to extend both resources.
“In parallel with advancing our geological and resource understanding, the Company has been
progressing ecological, groundwater and radiological baseline surveys together with preliminary
technical studies. These activities are designed to support the accelerated permitting of the deposits,
with the Company targeting submission of Mining Lease applications during the second half of this
calendar year. The permitting process is on the critical path to bringing both deposits into production.
“The wide-spaced wellfield design being advanced as part of the New Feasibility Study at Honeymoon
is also expected to be directly applicable to these satellite deposits. If successful, this approach has the
potential to deliver a high conversion of resource to wellfield mining inventory through cost-efficient
extraction.
“Early indications suggest that both deposits could be material production sources of uranium in the
future, leveraging the existing infrastructure at the Honeymoon Operation.”
ASX: BOE OTCQX: BQSSF www.bossenergy.com @Boss_Energy
Summary
Gould’s Dam and Jason’s Deposit are satellite uranium deposits to the Honeymoon Operation located
approximately 80km west and 13km north of the Honeymoon Operation respectively (See Figure 1), in
South Australia.
A Mineral Resource Estimate (MRE) for Gould’s Dam and Jason's Deposit was scheduled to be completed
in July 2025, based on drilling programs completed in 2024. However, this was deferred given the
developments in the understanding being gained at Honeymoon regarding the interpretation of the
historic data, geology, and mineralisation distribution.
Learnings from Honeymoon have been applied to the current MRE at Gould’s Dam and Jason’s Deposit,
including: a) domaining and constraining high-grade mineralisation; b) application of a permeability
filter; and c) the application of resource classification.
The MRE, as reported, will replace the Gould’s Dam and Jason’s Deposit MRE estimates of 2016 and
2017 respectively.1
The primary reasons for the variance in average grade and tonnage as compared to
the 2016 MRE estimate are the inclusion of additional data from infill drilling programs including from
prompt fission neutron (PFN) and borehole magnetic resonance (BMR) downhole geophysical tools and
improved interpretations of gamma data, mineralisation and stratigraphy.
Figure 1: Location map showing the Honeymoon Mine relative to the Gould’s Dam and Jason’s Deposit.
1 Refer to ASX announcements on 8 April 2016 titled “BOSS INCREASES HONEYMOON URANIUM PROJECT RESOURCE BY 90% TO 53MLBS
U3O8” and on 15 March 2017 titled “SUBSTANTIAL RESOURCE UPDATE FOR JASONS DEPOSIT”
ASX: BOE OTCQX: BQSSF www.bossenergy.com @Boss_Energy
Mineral Resource Estimate - Gould’s Dam
Gould’s Dam comprises several permeable sand aquifers within the Eyre Formation of the Billeroo
Palaeovalley. The sand aquifers range between 5m and 20m thick at a depth of between 85m and 135m
below the surface. The majority of the uranium mineralisation is hosted in a middle sand unit bounded
by more impermeable clay horizons and varies in thickness from 2m to 6m.
Boss’ initial understanding is that Gould’s Dam has good permeability and hydraulic connectivity and is
amenable to ISR mining. Mineralogy appears similar to Honeymoon, with limited acid-consuming
minerals (carbonates etc.) identified, albeit this has not been a focus for the updated MRE.
Gould’s Dam total MRE is 38.7Mt @ 388ppm for 33.1Mlbs of uranium reported above a 250ppm U3O8
lower cut-off grade and a 100md Ksdr permeability threshold. This would approximate the permeability
limits considered amenable for ISR mining. The MRE for Gould’s Dam is shown in the table below,
showing mineral resource classification:
Table 2: Gould’s Dam Mineral Resource Estimate (effective 31 December 2025)
Resource Category
Ore Grade Metal
Mt ppm U3O8 kt U3O8 Mlbs U3O8
GOULD'S DAM
Indicated 7.5 465 3.5 7.7
Inferred 31.2 369 11.5 25.4
TOTAL 38.7 388 15.0 33.1
Notes:
• The model is reported unconstrained and above a 250ppm U3O8 lower cut-off grade and 100mD Ksdr permeability lower cutoff for
all mineralisation subdomains in consideration of potential for recovery by ISR processing.
• The U3O8 lower cut-off grade reflects the assumed lower detection limit of the PFN tool.
• A Ksdr permeability is assumed to be moderate permeable equivalent to a well-sorted sand/gravels which would be amenable for
ISR mining.
• There is no historic depletion by production.
• Estimation of the combined PFN data and disequilibrium factored gamma data with high-grade cuts is by ordinary kriging using
dynamic anisotropy for the mineralised zones.
• The definition of the mineralised zones is refined by conditional indicator kriging (CIK) estimate based on a 250ppm U3O8 indicator
and a resultant estimated 17% probability of being above the indicator cut-off grade. The subdomains are used as hard boundaries.
• Density is for the Eyre Formation based on analyses of sonic core as 1.9 t/m3
, which is consistent with semi-consolidated quartz
sandstone.
• The model assumes agglomeration of 10mE x 10mN x 1mRL parent blocks for definition of wellfields for production in the Gould’s
Dam area. The surrounding areas that are still at an early stage of resource definition with less available data were modelled on
larger 40mE x 40mN x 1mRL panels.
• The model does not account for dilution, ore loss, hydrogeology, or recovery issues. Continuity of high-grade U3O8 is expected to be
locally erratic throughout the palaeovalley. These parameters will be considered during the mining study as being dependent on the
ISR treatment process.
• Classification is according to JORC Code Mineral Resource categories.
• Estimated disequilibrium factors applied to the gamma data cannot fully mitigate the risk of assumptions about the tenor of uranium
mineralisation based on that gamma data. The gamma data does not directly measure uranium.
• A Mineral Resource requires technical and economic evaluation and consideration of modifying factors for conversion to an Ore
Reserve. It is possible that not all Mineral Resource will convert to an Ore Reserve.
• Totals may vary due to rounded figures.
Known mineralisation extends for over 15km in a north-south direction. As set out in Figure 2 below,
the majority of this mineralisation is unclassified and falls outside the MRE, given the reliance on historic
drill data and the low drilling density with Gould’s Dam mineralisation and the extent of the Inferred and
Indicated MRE boundaries. Further drilling is required at Gould’s Dam to confirm the extent of known
mineralisation outside the MRE and to improve confidence and potentially extend the Inferred Mineral
Resource Classification.
ASX: BOE OTCQX: BQSSF www.bossenergy.com @Boss_Energy
Drilling will commence at Gould’s Dam in Q4FY26, with the programs expected to take three to six
months. Data from these drill programs will be used to provide a further updated Mineral Resource and
an initial Pre-Feasibility Study by Q2CY27.
Mineral Resource Estimate - Jason’s Deposit
Jason’s Deposit is hosted within the Yarramba Palaeovalley, which also hosts the producing Honeymoon
Operation to the South. The deposit, as currently defined, extends for 3.5km in length and 1.4km in
width.
Several sand aquifers within the Eyre Formation occur at depths from 75m to 120m below the surface.
The main mineralised horizon at Jason’s Deposit is located within the lower/basal sand aquifer, with
uranium mineralisation thicknesses varying from approximately 1m to 5m.
Jason’s Deposit total MRE is 13.3Mt @ 410ppm U3O8 for 12.0Mlbs of uranium reported above a 250ppm
U3O8 lower cut-off grade and 100mD Ksdr permeability. This would also approximate the permeability
considered amenable for ISR mining. The MRE for Jason’s Deposit showing resource classifications is
shown below.
Table 3: Jason’s Deposit Mineral Resource Estimate (effective 31 December 2025)
Resource Category
Ore Grade Metal
Mt ppm U3O8 kt U3O8 Mlbs U3O8
JASON’S DEPOSIT
Indicated 4.8 464 2.2 4.9
Inferred 8.5 380 3.2 7.1
TOTAL 13.3 410 5.4 12.0
Notes:
• The model is reported unconstrained and above a 250ppm U3O8 lower cut-off grade and 100mD Ksdr permeability lower cutoff for
all mineralisation subdomains in consideration of potential for recovery by ISR processing.
• The U3O8 lower cut-off grade reflects the assumed lower detection limit of the PFN tool.
• A Ksdr permeability is assumed to be moderate permeable equivalent to a well-sorted sand/gravels which would be amenable for
ISR mining.
• There is no historic depletion by production.
• Estimation of the combined PFN data and disequilibrium factored gamma data with high-grade cuts is by ordinary kriging using
dynamic anisotropy for the mineralised zones.
• The definition of the mineralised zones is refined by conditional indicator kriging (CIK) estimate based on a 250ppm U3O8 indicator
and a resultant estimated 17% probability of being above the indicator cut-off grade. The subdomains are used as hard boundaries.
• Density is for the Eyre Formation based on analyses of sonic core as 1.9 t/m3, which is consistent with semi-consolidated quartz
sandstone.
• The model assumes agglomeration of 10mE x 10mN x 1mRL parent blocks for definition of well fields for production in the Gould’s
Dam area. The surrounding areas that are still at an early stage of resource definition with less available data were modelled on
larger 40mE x 40mN x 1mRL panels.
• The model does not account for dilution, ore loss, hydrogeology, or recovery issues. Continuity of high-grade U3O8 is expected to be
locally erratic throughout the palaeovalley. These parameters should be considered during the mining study as being dependent on
the ISR treatment process.
• Classification is according to JORC Code Mineral Resource categories.
• Estimated disequilibrium factors applied to the gamma data cannot fully mitigate the risk of assumptions about the tenor of uranium
mineralisation based on that gamma data. The gamma data does not directly measure uranium.
• A Mineral Resource requires technical and economic evaluation and consideration of modifying factors for conversion to an Ore
Reserve. It is possible that not all Mineral Resource will convert to an Ore Reserve.
• Totals may vary due to rounded figures.
ASX: BOE OTCQX: BQSSF www.bossenergy.com @Boss_Energy
A material portion of the known mineralisation at Jason’s Deposit is unclassified and has not been
captured in the current MRE. This is largely due to resource confidence, given the reliance on historic
drilling and current drill spacings. Additional confirmatory drilling is planned for Jason’s Deposit in areas
of unclassified resource, along with extension of the known mineralisation, which could support
continued expansion of the current mineral resource.
Development Pathway – Gould’s Dam and Jason’s Deposit
Following the strategic decision made approximately six months ago to accelerate the potential
development of the Gould’s Dam and Jason’s Deposit projects (the Projects), a substantial program of
work has been completed to support key permitting milestones.
Work to date has focused on preparation for the Environment Protection and Biodiversity Conservation
Act (EPBC) referral and the application for Mining Leases, including development of Mining Lease
Proposals (MLPs) and the Public Environmental Report (PER) or Environmental Impact Statement (EIS).
Approval of each of these involves a detailed, science-based assessment undertaken by South Australian
government agencies, including the Department for Energy and Mining (DEM), Environment Protection
Authority (EPA) and the Department for Environment and Water (DEW).
Following the granting of the Mining Leases (MLs), a PEPR will be required to be developed before any
construction can commence. In addition, uranium projects may be subject to a range of additional
licences and approvals under relevant State and Commonwealth legislation.
Based on the studies completed to date, no significant issues have been identified that would represent
a material risk to the permitting pathway for the potential development of the Projects.
An overview of the work completed to date, together with the remaining activities required prior to
submission of the EPBC referral and Mining Lease applications, is provided in the table below.
Table 4: Status of permitting workstreams at Gould’s Dam and Jason’s Deposit
Key Programs of Work Completed Outstanding
Stakeholder
Engagement
• Initial stakeholder engagement
has been initiated
• Continued engagement and
dialogue with all stakeholders as
part of the approval process
Ecology (Flora and
Fauna)
• Baseline Flora and Fauna surveys
have been completed
• A Gap analysis will be undertaken
once key disturbance areas have
been identified from the
engineering works
Air Quality • Dust deposition gauges and
weather stations are installed,
with baseline data being collected
• Air quality modelling
Surface Water • Preliminary flood modelling
undertaken
• Final flood modelling required,
including surface water
management requirements
Radiation • Radiological baseline survey
commenced
• Continuation of baseline data
collection and reporting
ASX: BOE OTCQX: BQSSF www.bossenergy.com @Boss_Energy
Key Programs of Work Completed Outstanding
Soils • Baseline soil analysis at Jason's
Deposit completed
• Baseline soil analysis for Gould’s
Dam to be completed once key
disturbance areas have been
identified from engineering works
Groundwater • Groundwater modelling is being
undertaken.
• Complete pump tests and
continue groundwater modelling
and calibration, including
development of the Solute
Transport Model
Leaching Assessments • Data review completed, samples
collected and laboratory testing
underway
• Finalisation of laboratory test
work
Technical Studies Initiated several technical studies
including trade-offs to determine
project design and scale including:
• Infrastructure requirements
• Wellfield design
• Jason's Deposit potential trunk
line concept from Honeymoon
• Gould’s Dam satellite facility
options and associated interface
with Honeymoon
• Completion of preliminary
engineering design for Jason's
Deposit and option selection for
Gould’s Dam.
• Project Descriptions can then be
prepared to support permitting
applications
Given the consistencies between both Projects and the Honeymoon Operation in terms of geology,
mineralisation and hydrology, together with extensive field and laboratory test work undertaken to
date, the Company does not consider a traditional Field Leach Trial (FLT) necessary at this stage,
although continued engagement on the requirement for a FLT will be undertaken with the SA
Government agencies.
Boss has also recently developed significant in-house technical capability, including the ability to build
sophisticated 3D reactive transport models that simulate the interaction between groundwater flow and
the chemical reactions occurring between lixiviant fluids and the host rocks which is being used at
Honeymoon. These models will provide high confidence in the expected leaching performance of the
deposits. Accordingly, the Company intends to progress directly to the Mining Lease application process.
Operational wellfield trial patterns will be undertaken at a later stage of project development to
optimise production and wellfield design.
The permitting application process is anticipated to commence in H2CY26, with an anticipated
timeframe of 24 to 36 months to receive EPBC approval, granting of the Mining Leases and approval of
PEPRs. All of these approvals are required before any on-ground development work can be undertaken.
It is also important to note that the development timeline between the two Projects, post approvals,
differs significantly due to the scale and complexity of the engineering works. Jason’s Deposit is expected
to be relatively simple with a trunk line, similar to the East Kalkaroo operations, proposed while Gould’s
Dam will most likely incorporate a more complex satellite plant facility. The schedule for each of these
development paths will be defined as part of the engineering works program.
ASX: BOE OTCQX: BQSSF www.bossenergy.com @Boss_Energy
Key Catalysts – Gould’s Dam and Jason’s Deposit
Key catalysts associated with the Gould’s Dam and Jason’s Deposit deposits are shown below:
Table 4: Upcoming key milestones associated with Gould’s Dam and Jason’s Deposit
Date Catalyst
Q3CY26
• Commencement of drilling to define the extent of mineralisation and increase the Inferred
Resource at Gould’s Dam and Jason’s Deposit
Q4CY26
• Completion of Ecological, Groundwater and Radiological baseline data collection, modelling
and assessment
• Completion of initial stakeholder engagement
• Completion of Project Description and initial impact assessment
Q4CY26 • Permitting process commenced with EPBC referral and Mining Lease Assessment
Q3CY27 • Updated MRE and Pre-Feasibility Study
Pursuant to ASX Listing Rule 5.8.1 and complementing the 2021 Edition of the Australian Code for
Reporting of Exploration Results, Mineral Resources and Ore Reserves (JORC Code), Table 1, Sections 1,
2, and 3 are contained in the Annexures to this announcement.
This ASX announcement was approved and authorised by the Board of Boss Energy Limited.
For further information, contact:
Matt Dusci
Chief Executive Officer
P: +61 (8) 6263 4494
E: boss@bossenergy.com
For media enquiries, contact:
Paul Armstrong
Read Corporate
P: +61 (8) 9388 1474
E: info@readcorporate.com
ASX: BOE OTCQX: BQSSF www.bossenergy.com @Boss_Energy
JORC Code Reportable Mineral Resource Estimate
Gould’s Dam
Ownership
Gould’s Dam is located approximately 80 km west of the Honeymoon Mine within the Billeroo West
pastoral lease (See Figure 1) within exploration licence EL6512 and retention licences 83 - 85. These
tenements are 100% owned by Boss.
Background
Gould’s Dam includes the Gould’s Dam, Billeroo and Beulah Prospects, which are together referred to
as Gould’s Dam.
Gould’s Dam was discovered in the early 1970’s through greenfields exploration drilling carried out by
Eric A Rudd and Pacminex Pty Ltd. The project area was systematically explored during the 1970s and
early 1980s, with exploration activities ceasing in response to the Australian Government’s “three mine
policy” from 1984 – 1996. This policy was abandoned in 1996, with Southern Cross Resources (and
subsequently Uranium One Australia) acquiring the Gould’s Dam project tenements and recommencing
exploration activities. This included extensive resource definition drilling across the Gould’s Dam
prospect in 2004 & 2009, along with limited sporadic exploration drilling across the Northern portion of
the project area.
Geology
Gould’s Dam is located within the NNE-SSW trending Cenozoic Billeroo Palaeovalley, which
unconformably overlies sediments of the Paleozoic Arrowie Basin. This forms part of the Curnamona
Province in northeastern South Australia.
Gould’s Dam is located within the Curnamona Province in Northeast South Australia, which comprises
an ovoid region of Late Palaeoproterozoic to Late Cambrian igneous and metamorphic rocks
subsequently deformed through regional tectonics and large-scale crustal deformation. Within Gould’s
Dam, the Proterozoic basement is variably overlain by the Southern margins of the Palaeozoic Arrowie
Basin and to a lesser extent the Mesozoic Eromanga Basin. At Gould’s Dam, the Arrowie Basin forms the
“basement” to the Cenozoic sediments of the Lake Eyre Basin, which comprises basal palaeovalley
sediments of the Eyre Formation overlain by approximately 50m of impermeable clay known as the
Namba Formation.
Mineralisation
The palaoevalley hosted mineralisation at Gould’s Dam occurs at depths between 85m to 135m below
the surface. The uranium mineralisation extends over 15km in a North-South orientation and is up to
2.5km wide. This is the principal orientation of the palaeochannel. Mineralisation can be summarised as
below:
At the Southern area of the resource, uranium mineralisation tends to be high grade and predominantly
associated with the “middle” sand unit and to a lesser extent the lower sand unit. The individual sand
units are typically 8m to 10m thick and separated by well-defined clay horizons.
High-grade mineralisation associated with the middle sand horizon ranges from ~2m to 6m in thickness.
ASX: BOE OTCQX: BQSSF www.bossenergy.com @Boss_Energy
At the central Billeroo area, the mineralisation is associated with a well-defined redox boundary within
the “lower” Eyre Formation sand. This sand horizon ranges from ~10m to 25m in thickness, with
contained uranium mineralisation varying from ~1m to 5m thick.
The geology at the northern Beulah prospect is similar to that of the central Billeroo area, with uranium
mineralisation between ~1m to 5m thick predominantly associated with a well-defined redox boundary
within the “lower” Eyre Formation sands. Some additional mineralisation occurs as narrow, low to high
grade intersections on the margin of clay bands within the “middle” Eyre Formation across the project
area, with further work required to understand the amenability of this additional mineralisation to ISR
mining.
In general, mineralisation at Gould’s Dam can be described as relatively continuous (especially at lower
grades) within well-defined sand horizons. Refer to Appendix 1 for sections noted in the figure below.
Figure 2: Gould’s Dam Deposit showing the amalgamation of Gould’s Dam prospect to the South, Billeroo
prospect central, and Beulah prospect to the North, with continuous mineralisation over 15km strike length.
ASX: BOE OTCQX: BQSSF www.bossenergy.com @Boss_Energy
Figure 3: Gould’s Dam map showing the various drilling campaigns and drill density.
Drillhole Data
A total of 1,181 holes have been drilled at Gould’s Dam since 1968 (Table 6) by various companies. The
drilling has been completed by a variety of methods, including rotary air blast (RAB) holes, diamond drill
core holes, sonic holes and rotary mud holes. The majority of the drilling is via rotary mud holes.
Uranium grades are determined via two different downhole geophysical tools:
• Downhole Gamma – uranium grades are measured indirectly by measuring the radioactivity emitted
by the daughter products of uranium during decay, using a gamma tool containing a sodium iodide
(Nal) crystal, which records the counts per second when hit by gamma rays. These counts are
converted to uranium grades by applying a K factor and other correction factors, including
radiometric disequilibrium during modelling, given that gamma measures uranium decay products.
A disequilibrium correction is applied using measurements from the PFN downhole geophysical tool.
ASX: BOE OTCQX: BQSSF www.bossenergy.com @Boss_Energy
• Downhole PFN – uses neutron activation as a direct measure of uranium (235
U) in drillholes. The PFN
technology is superior for direct measurement of uranium, especially at higher cut-off grades. This
also ensures that an appropriate disequilibrium factor can be applied to downhole gamma data for
the estimation of uranium. PFN data is also validated by twinning a small number of rotary mud
holes with sonic core holes, enabling chemical assay of samples for uranium. The detection limit of
the PFN tool is considered to be 250ppm U3O8 meaning that grades below this value are considered
unreliable.
A PFN tool was first used by Southern Cross Resources in 2004. Most holes drilled after 2004 have utilised
both gamma and PFN downhole geophysical tools. Boss’ PFN tools are regularly calibrated at a purpose-
built facility in Adelaide, South Australia and quality assurance is also achieved by logging a check hole
at the Honeymoon mine every 1 to 2 weeks.
For the current MRE, 56% of the grade data used are from gamma logging as compared to 87% gamma
logging used in the 2016 MRE. On this basis, grade data for the 2025 MRE is considered more reliable.
In addition to gamma and PFN downhole geophysical tools, Boss also uses a BMR tool, which provides
quantitative information on porosity and permeability enabling determination of hydraulic connectivity
and input into wellfield design. All 223 holes drilled by Boss in 2023 and 2024, and used in the MRE,
were logged with the BMR downhole geophysical tool (see ASX Announcement titled "2024 infill drilling
on satellite uranium deposits complete" dated 20 November 2024).
Table 5: Total drillholes over the different periods and downhole geophysical tools used for grade estimation
Company MRE Period Holes Metres
Grade
Estimation
Eric Rudd - 1968-1969 6 723 Gamma
Pacminex 2016 1971-1973 120 15,941 Gamma
Minad-Teton 2016 1973-1982 116 15,689 Gamma
CSR 2016 1980 213 27,493 Gamma
Southern Cross Resources 2016 1998-2006 178 23,863 Gamma/PFN
Uranium One Australia 2016 & 2025 2006-2012 325 43,132 PFN/Gamma
Total Pre-Boss 958 126,841
Boss Energy 2025 2023-2024 223 30,060 PFN
Grand Total 1,181 156,900
1,181 drillholes were used in the 2025 MRE for the Gould’s Dam Deposit, including the 223 new holes
drilled by Boss (Table 6). Most of the new drillholes were completed at the Sunrise, Billeroo and Beulah
areas (Figure 2). Summary drilling data were previously published to ASX.2
Drillhole spacing is quite variable, reflecting the multiple generations of drilling. For portions of the
mineral resource at Indicated Mineral Resource classification the drill spacing is nominally 40m x 40m
(and often 20m x 25m). Drill spacing in the Inferred Mineral Resource classified portion of the resource
is typically 80m – 100m x 80m – 100m, although spacing can be closer in some local areas. Other factors
were considered in the Mineral Resource classification.
2
Refer to ASX announcements on 16 Au