ASX Release July 4, 2024
Honeymoon Uranium Project, South Australia
Boss set to ship first U308 from Honeymoon
Ramp-up running ahead of Feasibility Study schedule, with more than 57,000lbs of
uranium produced to date; Construction of NIMCIX columns 2 and 3 almost complete,
paving way for ongoing production increases
Highlights
• Startup production exceeding ramp-up schedule per the feasibility study (FS) estimates
• NIMCIX columns 2 and 3 on target for commissioning in Q3 and Q4, respectively in 2024
• Commissioning continues to advance, with key metrics remaining ahead of FS estimates:
o
o
o
o
Wellfields continue to average 80 - 100mg/L vs FS estimate of 47mg/L (~100% uplift)
Ion Exchange loaded resin recoverability remains at 100%
Resin loading normalising at FS estimate of 27 g/L
Elution performance exceeding FS estimate at 7 – 9 g/L
• First uranium sale to occur with revenue being received this quarter
• Boss remains highly leveraged to rising uranium price
Boss Energy (ASX: BOE; OTCQX: BQSSF) is pleased to report strong progress in the commissioning and
ramp up at its Honeymoon uranium mine in South Australia, with a total of 57,364lbs of U308 produced
by June 30, 2024.
Boss will now make its first delivery to European nuclear utilities under its existing sales contracts, with
revenue to be received in the current quarter.
With NIMCIX Column 1 performing to expectations and construction of Columns 2 and 3 on track for
completion in the September and December quarters, 2024 respectively, Boss expects production to total
at least ~850,000lbs of U308 by June 30, 2025, in line with its Feasibility Study schedule1.
Boss Managing Director Duncan Craib said: “The start-up phase at Honeymoon is proceeding comfortably
to plan, with all the key metrics running in line with, or exceeding, the forecasts contained in the Feasibility
Study schedule.
“Construction of the second and third columns is also advancing well, ensuring we are on track to continue
increasing our production rates. Total production in FY26 is set to meet or exceed our feasibility study
forecasts at 1.63Mlb. The addition of columns 4, 5 and 6 are forecast to further increase the production
rate to nameplate capacity of 2.45Mlb/annum by year three.”
1
Refer to ASX: BOE announcement dated June 21, 2021.
FOR FURTHER INFORMATION PLEASE CONTACT:
Boss Energy Limited
ABN 38 116 834 336
Duncan Craib - Managing Director/ CEO
+61 (08) 6263 4494
ASX: BOE
OTCQX: BQSSF
Level 1, 420 Hay Street, Subiaco
Western Australia 6008
Paul Armstrong – Public Relations
+61 (08) 9388 1474
www.bossenergy.com
@Boss_Energy
Figure 1: Drummed uranium ready for first shipment
Figure 2: Construction of columns 2 and 3 nearing completion to increase Honeymoon's production profile
Production update
Operational focus over the coming months remains on optimisation of the ion exchange, elution,
precipitation and drying and packing processes.
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
@Boss_Energy
Wellfield performance continues to impress, with tenors from individual wellfields into the PLS averaging
80 - 100 mg/L. Honeymoon’s feasibility study assumed PLS grade of 47 mg/L based on results from the
project’s previous operation. Boss is managing the grade of uranium being leached to maximise wellfield
recoveries.
Consumption of reagents in the wellfields of sulphuric acid and ferric (pH and Eh) are normalising as per
FS expectations. The lixiviant chemistry, as proved during the field leach trial, continues to demonstrate
superior performance at commercial throughput rates. The increased leach efficiency leads to a more
efficient loading on the ion exchange resin, effectively lowering operating costs as less reagents and power
are required per drum of uranium.
Stripping of uranium from the loaded resin continues to be virtually 100%, also demonstrating that the
ion exchange process is working as designed, resulting in a high-grade concentrated eluate greater than
7-9 g/L.
Process
Uranium Leach
Performance
Resin Performance
Elution Performance
Wellfield Grade
Historic
53 mg/L
Design
48 mg/L
Observed Actual
80 to 100 mg/L
Resin Loading
Precipitation Feed Grade
N/A
N/A
27 g/L
5 – 6 g/L
27 g/L (normalised)
7 - 9 g/L
This ASX announcement was approved and authorised by the Board of Boss Energy Limited.
For further information, contact:
Duncan Craib
Chief Executive Officer
P: +61 (8) 6263 4494
E: boss@bossenergy.com
For media enquiries, contact:
Paul Armstrong
Read Corporate
P: +61 (8) 9388 1474
E: info@readcorporate.com
About Boss Energy Limited
Boss Energy Limited (ASX: BOE; OTCQX: BQSSF) (Boss Energy or the Company), is ramping up uranium
production at its Honeymoon Uranium Project in South Australia. Annual production at Honeymoon is
forecast to reach 2.45Mlbs of U3O8. Boss also owns 30 per cent of the Alta Mesa uranium project in Texas,
USA. Production at Alta Mesa is ramping up to 1.5Mlbs of U3O8 a year. For more information please
visit www.bossenergy.com
Forward-Looking Statements
This announcement includes forward-looking statements. These forward-looking statements are based
on the Company’s expectations and beliefs concerning future events. Forward-looking statements are
necessarily subject to risks, uncertainties, and other factors, many of which are outside the control of Boss
Energy, which could cause actual results to differ materially from such statements. Boss Energy makes no
undertaking to subsequently update or revise the forward-looking statements made in this
announcement, to reflect the circumstances or events after the date of this announcement.
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
@Boss_Energy
Reference to previous ASX announcements
In relation to the results of the Enhanced Feasibility Study announced on June 21, 2021, the Company
confirms that all material assumptions underpinning the production target and forecast financial
information included in that announcement continue to apply and have not materially changed.