Quarterly Activities Report - March 2025
Released
Released
Announcement PDF
ASX Release 29 April 2025
March 2025 Quarterly Report
Honeymoon generates first free cashflow on
highly successful ramp up and strong margins
Outstanding quarter puts project well on track to meet FY25 production guidance of
850,000lbs U3O8 at C1 cost of A$37-41/lb (US$23-25/lb)
Highlights
Honeymoon Uranium Project, South Australia (Boss 100%)
• Strong quarterly operational performance, with 295,819 lbs of U3O8 drummed (up 116% from
December quarter) and 246,869 lbs IX production (up 15%)
• Average realised price of A$133/lb (US$84/lb) with cash received for 268,000 lbs
• C1 cost from drummed uranium of A$33/lb (US$21/lb) is below second-half FY25 guidance of
A$37-41/lb (US$23-25/lb); This implies a C1 margin of 68%-71% based on Term Price, which
ended the quarter at an all-time high in AUD terms (A$127/lb)
• The robust margin led to Honeymoon generating its maiden quarter of positive free cash flow
• Key infrastructure continued to be brought online including NIMCIX column 3 and Wellfield 3
• NIMCIX columns 1 and 2 continue to perform at nameplate capacity
Alta Mesa Uranium Operation, South Texas (Boss 30%)
•
Total production of 98K lbs of U3O8; Total inventory received of 29,126 lbs U3O8
•
Average daily capture rate in March of 1,900 lbs U3O8, representing the highest rate since the
Alta Mesa plant returned to operations in June 2024
•
Successful startup of the 2nd Ion Exchange Circuit, doubling the total flow capacity
Corporate
• Robust Balance Sheet remains strong with $229M of cash and liquid assets on hand; zero debt
• Drummed inventory balance on hand of 1.21M lbs U3O8 (including loan receivables)
• Strategic investment of 19.7% in Laramide Resources to secure exposure to the significant
exploration and development upside at the Westmoreland Uranium Project in Queensland
Boss’ March quarterly conference call will be held today at 8am AWST (10am AEST). The call can be
accessed at https://loghic.eventsair.com/983274/983265/Site/Register
FOR FURTHER INFORMATION PLEASE CONTACT:
Boss Energy Limited
ABN 38 116 834 336
Duncan Craib - Managing Director/ CEO
+61 (08) 6263 4494
ASX: BOE
OTCQX: BQSSF
Level 1, 420 Hay Street, Subiaco
Western Australia 600
Paul Armstrong – Public Relations
+61 (08) 9388 1474
www.bossenergy.com
@Boss_Energy
Boss Energy Limited (ASX: BOE; OTCQX: BQSSF) is pleased to announce outstanding operational and financial
results for the three months to 31 March 2025.
The ramp up at its Honeymoon Uranium Project continues to meet or exceed production and cost guidance,
resulting in robust margins and the first quarter of free cashflow.
Boss Managing Director Duncan Craib said: “This was a pivotal quarter for Boss as we started generating free
cashflow at Honeymoon.
“This milestone is the result of the highly successful ramp up, which saw production and costs meet or exceed
our guidance.
“Importantly, we generated robust margins at current prices, demonstrating the strength of Honeymoon in
the current market and the project’s immense upside on the back of future increases in the uranium price as
the market tightens.
“Our success in delivering free cashflow within a year of starting production reflects the skills and
commitment of our people, who have worked tirelessly to ensure we meet our undertakings to the market.
“Thanks to our team, we have done exactly what we said we would do”.
Honeymoon Safety Performance
The Total Reportable Injury Frequency Rate (TRIFR1) was 9.9 at the end of the quarter. Given TRIFR is
calculated per million hours worked, and the comparatively low hours worked at Honeymoon, a small
number of incidents will have a significant impact to the TRIFR result. The majority of incidents contributing
to the TRIFR are low-severity incidents. During the quarter, there was one Lost Time Incident (LTI). The LTIFR
for the quarter was 2.5.
Table 1: Honeymoon TRIFR (12-month moving average)
Key Metric Quarter ended
March Q3 FY25
December Q2 FY25
9.9
4.4
TRIFR
We continue to make significant progress on improving the safety culture and maturity of our safety systems.
During the quarter, site strengthened its incident/ hazard reporting and action tracking with the
implementation of Donesafe, and Cert 3 Emergency Response Training was provided to volunteers amongst
permanent employees to ensure the safety of the team. Risk management and hazard reduction remains a
key focus.
Honeymoon Production Results
Production continued to ramp up during the quarter, with 246,869 lbs IX production and 295,819 lbs U3O8
drummed. This represents a growth of 31,550 lbs (15 per cent) in IX production and 158,735 lbs (116 per
cent) in U3O8 drummed compared to the previous quarter. U3O8 drummed exceeded IX production as a
portion of the inventory accumulated in previous quarters was processed through the drying and packing
stage during the quarter.
1 Total Reportable Injury Frequency Rate (TRIFR) measures the rate of restricted work injuries (RWIs), medical treated injuries (MTI)
and lost time injuries (LTIs) that occur per million hours worked.
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
Page 2
Table 2: Operational physicals
Key Metric Quarter ended
March Q3 FY25
December Q2 FY25
Wellfields online
3
2
NIMCIX Columns operational
3
2
1,088,704
861,204
(U3O8 mg/l)
108
116
(%)
95.5
97.8
(lbs)
246,869
215,319
(lbs)
295,819
137,084
IX Flow (total)
Unit
1
(m3)
PLS to IX tenor (weighted average)
2
IX Recovery (weighted average)
IX Production (total)
1
U3O8 Drummed (total)
Notes: (1) Conversions: There are 1,000 litres per m3 and 0.00000220462 lbs per mg. (2) Tenors currently being
extracted exceed the average tenors forecast in the Feasibility Study and should not be extrapolated across the LOM.
A number of key milestones were delivered during the quarter as part of the ramp-up plan, including bringing
in production from Wellfield B3 and commencing operations from NIMCIX Column 3, which occurred in
March. Kiln 2 was also commissioned and became operational during the quarter.
There were some commissioning challenges with the kiln and baghouse (which form a part of the drying and
packing stage), resulting in some unplanned downtime during the quarter. These challenges continue to be
resolved but are not expected to impact Boss’ guidance target of 850,000 lbs U3O8 in FY 2025.
Despite the challenges noted above, Boss delivered record production during February of 123,188 lbs U3O8
drummed which represents an annualised run-rate of ~1.5M lbs. This provides Boss confidence in the delivery
of the ramp-up plan as it tests the plant's capability.
Average IX recovery underperformed for the quarter due to commissioning activities related to NIMCIX
Column 3 and the availability of the drying and packing stage. Uranium in solution that the Ion Exchange
process does not capture is reprocessed back through the wellfields, hence is not lost from the total circuit,
but reflects a measure of flow efficiency.
Key activities to be achieved as part of the ramp-up plan for the coming quarter include increasing the flow
rate with the availability of NIMCIX Column 3 and Wellfield B3, along with changing the precipitation circuit
operating regime from batch to continuous operation.
Boss remains on track to deliver 850,000 lbs of U3O8 drummed for the financial year ended 30 June 2025.
Honeymoon Construction Activities
Construction activities on site increased during the quarter, with the focus on steel erection along with pipe
spooling and assembly for NICMCIX Columns 4 to 6. Construction activities will largely be completed by the
end of the financial year, with the commissioning and production from NIMCIX Column 4 in Q3 CY25. NIMCIX
Columns 5 and 6 will become operational in Q4 CY25, aligned with new wellfields being brought into
production to increase flow and production.
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
Page 3
Figure 1: Steelwork foundations installed for construction of NIMCIX columns 4 to 6
Exploration Activities
During the quarter, RSC Consultants delivered a prospectivity map for Honeymoon-style sandstone-hosted
uranium deposits, covering the high-priority 80 km exploration zone around the Honeymoon operation. RSC
identified 23 high-priority targets.
The first of these targets to be tested is the Sara Dam prospect, located approximately 10 km east of the
Honeymoon mine and immediately west of Marmota Energy’s Saffron prospect. Activities completed in the
quarter included a program of wide-spaced drilling to test the largely undrilled target, with lines of holes
spaced nominally at 2.4 km and holes 480 m apart along the lines. Thirty-four holes for 4,298 m (average
126 m) were completed along a 12 km length of interpreted palaeochannel. Anomalous radioactivity was
intersected in six holes NW of the Saffron prospect, but these intersections were generally not of economic
tenor.
The second of the targets to be generated from the prospectivity analysis will be in the Lake Constance area,
approximately 22 km south-west of the Gould’s Dam deposit. Anomalous radioactivity was identified in
several holes drilled in this area during the 1970’s. Reconnaissance drilling using a low impact aircore rig is
planned for the next quarter.
Exploration activities in the quarter also included 32 rotary mud drillholes at the Cummins Dam prospect,
located approximately 2 km north-east of the East Kalkaroo (Honeymoon) deposit. Sparse drilling during the
1970’s returned several radioactive intersections, but these were never followed up. Drilling in 2024
returned several promising intersections, and follow-up drilling in 2025 was aimed at extending this
mineralisation. These follow-up holes failed to extend the mineralisation intersected in the previous quarter,
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
Page 4
which has now been shown to extend over 1.2 km and up to 250 m in width. While this is a significant body
of uranium mineralisation, many intersections are associated with saprolite, which is thought to be relatively
impermeable. Further work would be required to test the permeability of this mineralisation to determine
if it is suitable for in situ leaching.
AMC Consultants completed a thorough review of downhole geophysical data from the current Honeymoon
wellfields in order to inform Mineral Resource Estimates for the Gould’s Dam and Jason’s satellite deposits.
Updated independent mineral resource estimates (MRE) for both deposits are anticipated for the next
quarter.
Balance Sheet
As at 31 March 2025, Boss has no debt and $229.2M of liquid assets (being cash, liquid investments and
physical uranium), a decrease of $22.4M from the December Quarter primarily driven by ‘marked to market’
movements in inventory and listed investments. Positively Honeymoon realised an important milestone by
recording its first quarter of positive free cash flow.
Table 3: Cash, inventory and investments
A$000’s
March Q3 FY25 December Q2 FY25
Movement
Cash on hand
63,773
65,177
(1,404)
Investments and other liquid assets
42,386
34,382
8,004
Inventory on hand1
106,925
117,279
(10,353)
Loan receivable
16,140
34,808
(18,668)
Total cash and liquid investments
229,224
251,646
(22,422)
Unrestricted cash and cash equivalents stood at $63.8M (which excludes a fully cash-backed environmental
bond of $13.5M) with a further $165.4M in liquid investments (including inventory).
The waterfall chart below highlights the March quarter movements in cash.
Figure 2: March Q3 FY25 cash (A$000’s)
$000's
120,000
16,180
100,000
16,583
80,000
65,177
(9,867)
(5,000)
(3,866)
(6,544)
60,000
(6,383)
3,585
63,773
Other
Closing
Cash
(6,091)
40,000
20,000
-
ASX: BOE
Opening
Cash
Receipts
enCore Honeymoon Honeymoon Honeymoon Alta Mesa
from
Loan
Operating Wellfields
Capital
Costs
customers Repayment
costs
capex
project
OTCQX: BQSSF
www.bossenergy.com
G&A
Exploration
and
investments
Page 5
Inventory and investments (excluding cash) declined by A$21.0M during the March quarter due to:
•
Investments and other liquid assets ($8.0M increase): Primarily reflects increased investment in
Laramide ($16.2M), partially offset by a decline in the value of an investment in enCore ($8.1M)
driven by a decline in enCore’s share price.
•
Inventory on hand ($10.3M decrease): Primarily reflects a decline in inventory valuation due to a
decline in the Uranium spot price (from $US77.50/lb to $US64.45/lb). This ‘mark to market’ decline
is primarily a result of the 1.25M lbs of inventory that Boss purchased in January 2022 for
US$30.15/lb.
•
Loan receivable ($18.7M decrease): Reflects repayment of half of the uranium loan to enCore and
the associated interest ($19.1M). The remaining outstanding loan balance is to be received during
the current June quarter.
Cash receipts
During the quarter, Boss received US$22.4M in cash, related to a sale of 150k lbs to a utility customer and
the repayment of half of the uranium (100K lbs) loaned to enCore Energy Corp (enCore), plus 18k lbs interest
at a rate of 9 per cent per annum on the total loaned material to enCore of 200,000 lbs.
Table 4: Cash Receipts
Key Metric
Unit
Q3 FY25
Q2 FY25
Q1 FY25
YTD FY25
Production
Sales
Loan repayment
Cash received
Average Realised price1
Inventory on hand2
lbs
lbs
lbs
US$
US$/lb
Mlbs
295,819
150,000
118,000
22,389
83.5
1.22
137,084
200,000
15,500
77.5
1.08
89,516
200,000
15,608
78.0
1.17
522,419
550,000
118,000
53,497
80.1
n/a
Notes: (1) Average realised price includes cash received from inventory loaned (2) Inventory on hand includes
100K lbs inventory loaned.
Honeymoon Costs
Boss has tracked favourably against guidance, recording a C1 cost of A$33/lb (US$ 21/lb). Boss provided C1
cost guidance (A$37-41/lb, US$23-25) for Honeymoon as a part of the December Quarterly.
Table 5: Production and Capital Costs
Honeymoon Costs
Cash Cost – Fixed2
Cash Cost – Variable
2
Unit
$A
March Q3 FY2025
(Actual)
2H FY2025
(Guidance provided)
$/lb
21
22-24
$/lb
13
15-17
2
Cash Cost – Total
$/lb
33
37-41
Capex – Wellfields3
$M
8
17-20
Capex – Capital Projects
$M
4
19-21
Capex – Other sustaining capital
$M
0
1-2
Capex - Total
$M
12
38-43
Notes: (1) Costs are for Honeymoon only with definitions consistent with EFS. Alta Mesa is not included. (2) Cash Cost
includes all mining costs, onsite processing costs, onsite general and administration costs and logistical costs. Excludes
royalties and capital expenditure. (3) Wellfields capex includes sustaining and deferred capex.
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
Page 6
C1 cost from drummed uranium of A$33/lb (US$21/lb) compares favourably to guidance, implying a C1
margin of 68%-71% based on the Term Price, which ended the quarter at an all-time high of AU$127/lb
(US$80/lb).
Boss expects an increase in costs in the next quarter which will result in a C1 cost for 2H25 at the bottom of
the 2H25 guidance range (A$37-41/lb, US$23-25) and will continue to pursue operational efficiencies.
Wellfields Capex of A$8M for the quarter remains on track with 2H25 guidance (A$17-20M) as progress and
the cost per wellfield remain in line with expectations. Wellfields Capex for the March Quarter includes $3.5M
of first fill costs for Wellfields 1, 2 and 3 (which is equivalent to $1.6/lb under leach) and $4.9M for Wellfields
4-9 development infrastructure.
The Capital Project expenditure, which represents most of the cost to complete columns 4-6, remains in line
with 2H25 guidance ($19-21 million). Capital Project expenditure reflects the ramp-up profile, with a
significant jump in expenditure expected in the next quarter.
Alta Mesa (Boss 30%/ enCore 70% Joint Venture)
Production during the quarter from the Alta Mesa Uranium Project, a Joint Venture with enCore Energy Corp
(NASDAQ: EU|TSXV: EU), totalled 98K lbs of U3O8 (on a 100% basis). This included 50,000 lbs U3O8 captured
between 6 March 2025 and 31 March 2025. The average daily capture rate for the last 26 days of March
2025 was in excess of 1,900 pounds of uranium per day, representing the highest rate since the Alta Mesa
plant returned to operations in June 2024. A total of 29,126 lbs U3O8 was delivered to Boss’s account in the
quarter to sell as its own inventory, unencumbered.
As reported during the quarter by enCore, the ramp-up to achieve 1.5M lbs of uranium per year was impacted
by wellfields. enCore, as the operator of the Joint Venture, has taken a number of steps to address these
challenges during ramp-up, with the focus on acceleration of wellfield development and improvement to
wellfield planning and operations.
On 12 March 2025 - enCore announced the successful startup of its second Ion Exchange (“IX”) Circuit at Alta
Mesa, effectively doubling the total flow capacity. In conjunction with the expansion of processing capacity,
enCore has installed additional injection and extraction wells in the currently permitted and operational
wellfields. The combination of the second IX Circuit and wellfield expansion utilizes approximately 75% of the
current processing capacity. Additional wells will be brought online systematically to increase uranium
production as the Alta Mesa ramps up to an annualised production rate of 1.5M lbs U3O8.
Laramide (Boss 19.7% ownership)
On 13 March 2025, Boss announced the acquisition of 23.5m shares in Laramide Resources (TSX & ASX: LAM),
representing approximately 9% of the issued shares at a price of C$0.60 per share for a total consideration
of A$15.5M. This comprised of approximately A$3.9M in cash and A$11.7M in scrip. The purchase increased
Boss’ interest in Laramide to approximately 18.4% on an undiluted basis at the time.
Boss continued in April to opportunistically acquire shares on market and currently holds a 19.7% interest in
Laramide on an undiluted basis. This represents a total consideration to date of approximately A$38M
(equivalent to ~3% of Boss’s market capitalisation) deployed to acquire strategic stake. Boss is not in active
discussions with Laramide and, subject to there being no actual or proposed material change in the
shareholding of Laramide (including a change of control proposal) or the actions of Laramide, Boss has no
current intention to acquire control or make a takeover offer for Laramide.
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
Page 7
Laramide’s flagship asset is the Westmorland Uranium Project in Queensland. It also owns the ChurchrockCrownpoint uranium project in New Mexico. Westmoreland has a JORC Indicated Resource of 27.8Mt at an
average grade of 770ppm U3O8 for 48.1M contained Lbs of U3O8 and an Inferred Resource of 11.8Mt at an
average grade of 680ppm U3O8 for 17.7M contained Lbs of U3O82.
Liverpool Project
On 4 March 2025, Boss entered into an option and earn-in agreement with the Eclipse Group for the Liverpool
Uranium Project in the highly prospective Alligator River Uranium Field in the Northern Territory. The
Agreement provides Boss with an option, exercisable over a 12-month period, to earn up to 80% of the
Project in return for Boss spending $250,000 in expenditure on the Project during a 12-month option
period. Upon exercising the option, Boss can earn up to an 80% interest in the Project by funding $8M of
exploration expenditure over a seven-year period, which is split into two stages.
Work has commenced compiling historic drilling data and reprocessing airborne geophysical imagery from
the Liverpool Project.
Uranium Market Analysis
The first quarter of 2025 has been characterised by uncertainty created by several factors. Some of the most
significant of these are sanctions on Russian uranium, how they will be treated and potential tariffs on
imports of nuclear fuel into the USA. The US has also launched an investigation under Section 232 of the
Trade Expansion Act, with the Secretary of Commerce expected to release a final report by mid-October
assessing risk and recommending actions to reduce US reliance on foreign sources for processed critical
minerals, including uranium. The actions could include tariffs or incentives for US production. Uncertainty
and lack of predictability are not conducive to long term decision making.
The World Nuclear Fuel Cycle conference took place in Montreal in early April. At that time there were no
US tariffs on any of the global uranium producers but there was real concern that this could change at any
time. One effect of lower spot prices and global trade uncertainty is that Buyer interest in near to mid-term
purchasing has increased. This has been reflected in the spot prices which has moved up by over a dollar
since the end of March and appears to be on an upward trend. The term price has held firm at $80/lb.
A theme that came across in many discussions was that uranium demand is growing and the demand
forecasts over the next 10 to 15 years are robust as they are primarily based on reactors in operation and
under construction. The forecast for future supply is more vulnerable to downside risks. The timely
availability of supply is threatened by geopolitical and trade risks, a weaker supply chain and several
announcements of missed ramp up targets, deferred start up decisions and increased timelines for
regulatory.
The Uranium 2024: Resources, Production and Demand report which is also known as the Red Book is
published by the OECD Nuclear Energy Agency (NEA) and the International Atomic Energy Agency stressed
the need for investing in new mining project in the near to midterm.
"In conclusion, while sufficient uranium resources exist to meet demand for nuclear power generation in
both low- and high-growth scenarios through 2050 and beyond, substantial investment in new mining
projects will be essential. Given the long lead times for project development, identifying and advancing new
projects in the near to medium term is crucial to avoid potential supply disruptions."
Refer to Laramide’s ASX Announcement “Laramide MRE Update for Westmoreland Uranium Project (amended)” released on 7
March 2025
2
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
Page 8
In an unstable global environment, security of supply is paramount and nuclear fuel buyers are prioritising
supply from uranium friendly politically stable countries. Boss Energy’s Honeymoon mine is well place to
respond to near term market movements and benefit from fuel buyers desire for longer term security of
supply.
March 2025 Quarterly Results Conference Call – 29 April 2025
Boss will hold a conference call today, Tuesday 29 April 2025, at 10am AEST (8am AWST) with Managing
Director Duncan Craib, Chief Financial Officer Justin Laird and Chief Operating Officer Matt Dusci, to discuss
the results. To listen in live, please click on the link below and register your details.
Appendix 5B disclosures
In line with its obligations under ASX Listing Rule 5.3.5, Boss notes that the only payments to related parties
of the Company, as disclosed in the Appendix 5B (Quarterly Cashflow Report) for the period ended 31 March
2025, consist of executive director and chief financial officer salaries and wages (including superannuation)
and payment of non-executive director fees.
During the quarter ended 31 March 2025, the Company spent approximately $14.8M on project and
exploration activities relating to its Honeymoon and Alta Mesa Projects. These activities included:
•
Technical studies costs
•
Construction equipment
•
Wellfield drilling and development costs
•
Engineering and construction expenses
•
Mineral exploration and evaluation costs
In addition to these activities the Company continued to incur costs relating to the ongoing maintenance
activities required at Honeymoon. The expenditure represents direct costs associated with these activities as
well as capitalised wages which can be directly attributable to Honeymoon.
This ASX announcement was approved and authorised by the Board of Boss Energy Limited.
For further information, contact:
Duncan Craib
Chief Executive Officer
P: +61 (8) 6263 4494
E: boss@bossenergy.com
For media enquiries, contact:
Paul Armstrong
Read Corporate
P: +61 (8) 9388 1474
E: info@readcorporate.com
ASX: BOE
www.bossenergy.com
OTCQX: BQSSF
Page 9
Reference to previous ASX announcements
In relation to the results of the Enhanced Feasibility Study announced on 21 June 2021, the Company
confirms, for the purposes of listing rule 5.19 and for all other purposes, that all material assumptions
underpinning the production target and forecast financial information included in that announcement
continue to apply and have not materially changed.
The mineral resource estimates in this announcement were reported by the Company in accordance with
listing rule 5.8 on 25 February 2019. The Company confirms it is not aware of any new information or data
that materially affects the information included in the previous announcement and that all material
assumptions and technical parameters underpinning the estimates in the previous announcement continue
to apply and have not materially changed.
Forward-Looking Statements
This announcement includes forward-looking statements. These forward-looking statements are based on
the Company’s expectations and beliefs concerning future events. Forward-looking statements are
necessarily subject to risks, uncertainties, and other factors, many of which are outside the control of Boss
Energy, which could cause actual results to differ materially from such statements. Boss Energy makes no
undertaking to subsequently update or revise the forward-looking statements made in this announcement,
to reflect the circumstances or events after the date of this announcement.
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
Page 10
Appendix One:
Schedule of Mining Tenements
The following information is provided pursuant to Listing Rule 5.3.3 for the quarter ended 31 March 2025.
Tenement Name
Location
Licence Number
Interest
Yarramba
South Australia
EL6510
100%
South Eagle
South Australia
EL6081
100%
Gould’s Dam
South Australia
EL6512
100%
Katchiwilleroo
South Australia
EL6511
100%
Ethiudna
South Australia
EL6020
100%
Gould’s Dam
South Australia
RL83-85
100%
Honeymoon Mine
South Australia
ML6109
100%
Prairie Dam
South Australia
EL6962
75%
Chalker Dam
South Australia
EL6963
75%
Oakvale
South Australia
EL6964
75%
Gairloch
South Australia
EL6965
75%
Venus Bay
South Australia
EL6992
100%
Darke Peak
South Australia
EL7013
100%
Rudall
South Australia
EL6999
100%
There were no mining tenement acquisitions or divestments during the quarter.
EL6512, 6511, 6020, 6510 and 6081 are subject to an earn-in agreement with First Quantum Minerals in
respect to the base and precious metal rights. Refer ASX release dated 10 February 2022 for further
information.
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
Page 11
Honeymoon Project Mineral Resource
Honeymoon’s Mineral Resource (lower cut-off of 250 ppm U3O8)
Classification
Tonnage
(Million Tonnes)
Average Grade
(ppm U3O8)
Contained Metal
(Mkg, U3O8)
Contained Metal
(Mlb, U3O8)
Measured
3.1
1,100
3.4
7.6
Indicated
18.4
630
12.0
25.5
Inferred
30.9
570
18.0
38.5
Total
52.4
620
32.5
71.6
The global Honeymoon Mineral Resource stands at 71.6Mlb (52.4Mt) with an average grade of 620ppm U308,
using a cut-off grade of 250ppm.
The current Honeymoon restart feasibility studies utilise only a portion of Honeymoon’s JORC resource,
excluding 36Mlb of JORC resource outside the HRA, which could expand the mine life, and Boss’ defined
exploration target could potentially extend the mine life beyond the initial 11 years and increase the
production profile. Honeymoon’s Federal EPIP Act approvals allow export of more than 3Mlbs/annum U3O8
equivalent.
In addition to the global Mineral Resource, the Honeymoon Uranium Project also has an Exploration Target
range of 28Mt to 133Mt of mineralisation at a grade of 340ppm to 1,080ppm U308 for a contained 58Mlbs to
190Mlbs U308 (26,300 to 86,160 tonnes of contained U308), using a cut-off of 250ppm3. Note the potential
quantity and grade of the Exploration Target range is conceptual in nature. There has been insufficient
exploration to estimate a Mineral Resource and it is uncertain whether future exploration will result in the
definition of a Mineral Resource.
3
Refer to ASX: BOE announcement dated 25 March 2019
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
Page 12
Alta Mesa Project Mineral Resource
Alta Mesa & Mesteña Grande Mineral Resource
Summary (0.30 GT cut-off)1,2,3
Tons
Avg. Grade
(% U3O8)
Pounds
Total Measured Mineral Resource1
54,000
0.152
164,000
Alta Mesa Indicated Mineral Resource
1,397,000
0.106
2,959,000
119,000
0.120
287,000
Total Measured & Indicated Resources
1,570,000
0.109
3,410,000
Alta Mesa Inferred Mineral Resource
1,263,000
0.126
3,192,000
Mesteña Grande Inferred Mineral Resource
5,733,000
0.119
13,601,000
Total Inferred Resources
6,996,000
0.120
16,793,000
Mesteña Grande Indicated Mineral Resource
1. Represents that portion of the in-place mineral resource that are estimated to be recoverable within existing wellfields.
Wellfield recovery factors have not been applied to indicated and inferred mineral resources.
2. Technical Report Summary for the Alta Mesa Uranium Project, Brooks and Jim Hogg Counties, Texas, National Instrument
43-101, Technical Report prepared for enCore Energy Corp, Doug Beahm, P.E. 19 January 2023.
3. For the purposes of ASX Listing Rule 5.12, Boss Energy cautions that the mineral resources for the Alta Mesa Project are not
reported in accordance with the Australasian Code for Reporting of Mineral Resources and Ore Reserves 2012 (JORC Code).
The mineral resource estimate at the Alta Mesa Project is a foreign estimate prepared in accordance with Canadian National
Instrument 43-101. A competent person has not done sufficient work to classify the foreign estimate as a mineral resource
in a