Quarterly Activities Report - December 2024
Released
Released
Announcement PDF
ASX Release 29 January 2025
December 2024 Quarterly Report
Commercial production declared at
Honeymoon following strong ramp-up
Honeymoon on track to meet FY25 production guidance; 2H FY25 C1 cost guidance set at
$37-41/lb (USD $23-25/lb)
Highlights
Honeymoon Uranium Project, South Australia
•
Strong operational performance, with 137,084lbs of U3O8 drummed (up 53% from September
quarter) and 215,319lbs IX production (up 96%)
•
NIMCIX column 3 ramping up; Columns 1 and 2 operating at nameplate capacity;
Commissioning of Kiln 2 completed; Now operating
•
Given this strong ramp-up, commercial production has been declared, effective 1 Jan 2025
•
Honeymoon remains on track to meet FY25 production guidance of 850,000lbs U3O8
•
C1 cost guidance for 2H FY25 is $37-41/lb U3O8 (USD $23-25/lb); This is in line with
inflationary increases recorded since the June 2021 Enhanced Feasibility Study (EFS)
Alta Mesa Uranium Operation, South Texas (Boss 30%)
•
Strong ramp-up ensures Boss receives first shipment of 35,181lbs U3O8 from Alta Mesa
•
Wellfield solution head grades peaked at approximately 140 mg/l U3O8 and averaged
approximately 65 mg/l U3O8
•
First IX circuit operating at nameplate capacity, second IX circuit being commissioned in March
quarter 2025 with the third IX circuit planned to be online by year-end 2025
•
Alta Mesa expected to reach full operational capacity of 1.5M lbs of U3O8 a year by 2026. Boss’
share of Alta Mesa production is 30 per cent (450,000lbs U3O8 a year at nameplate capacity)
Corporate
•
Robust balance sheet with $252M in liquid assets (quarterly growth of $7M); zero debt
•
Total Company sales in the quarter of 200,000lbs U3O8 at an average realised price of
US$77.50/lb U3O8, totalling US$15.5M ($25.2M)
•
Drummed inventory balance on hand of 1.1Mlbs U3O8 (including loan receivables); Bulk
shipments to nominated conversion facility being delivered and accepted on schedule
Boss’ December quarterly conference call will be held today at 8am AWST (11am AEDT). The call can
be accessed at https://loghic.eventsair.com/220328/795123/Site/Register
FOR FURTHER INFORMATION PLEASE CONTACT:
Boss Energy Limited
ABN 38 116 834 336
Duncan Craib - Managing Director/ CEO
+61 (08) 6263 4494
ASX: BOE
OTCQX: BQSSF
Level 1, 420 Hay Street, Subiaco
Western Australia 600
Paul Armstrong – Public Relations
+61 (08) 9388 1474
www.bossenergy.com
@Boss_Energy
Boss Energy Limited (ASX: BOE; OTCQX: BQSSF) is pleased to report on another successful quarter which
has culminated in the Company declaring commercial production at its Honeymoon Uranium Project in
South Australia.
Commissioning and production ramp-up at Honeymoon, including the wellfields and the processing plant,
are in line with or exceeding Boss’ forecasts.
Importantly, the results show conclusively that the ion-exchange technology at the heart of Boss’ strategy
to re-develop Honeymoon is extremely effective and comfortably meeting expectations.
As a result, Honeymoon is on track to meet FY25 production guidance of 850,000lbs U3O8.
In light of this performance, Boss is pleased to publish maiden C1 cost guidance for Honeymoon of
$37-41/lb1 (USD $23-25/lb) for the six months to June 30, 2025, and declare commercial production for
the project effective 1 January 2025.
Boss is also pleased to report strong results from the ramp-up at its 30 per cent-owned Alta Mesa Uranium
Operation in Texas, US. As a result, Boss received its first shipment of 35,181lbs U3O8 during the quarter.
Wellfield solutions are averaging approximately 65 mg/l U3O8, the first IX circuit is operating at nameplate
capacity, with the second IX circuit being commissioned in March quarter 2025 and the third IX circuit
planned to be online by year end 2025
Boss Managing Director Duncan Craib said: “Outstanding progress was made at Honeymoon during the
December 2024 quarter. The ramp-up of operations continued to proceed on schedule across all key
production metrics.
“Given this success, we have officially declared Commercial Production, with C1 cost guidance provided for
2H FY25 of $37-41/lb U3O8 (USD $23-25/lb). This compares favourably to other uranium development
projects and is in line with inflationary increases recorded since the June 2021 Enhanced Feasibility Study.
“The strong results reflect the significant technical changes Boss has implemented at Honeymoon,
including improvements to the lixiviant chemistry and adoption of Ion Exchange processing. Both these
measures, which were central to Boss’ re-start strategy, have proved extremely efficient and effective.
“Remaining construction activities are nearing completion with NIMCIX 1 and NIMCIX 2 operating at
nameplate production and NIMCIX 3 commissioned and expected to achieve nameplate capacity in
February 2025. NIMCIX columns 4, 5 and 6 will all be commissioned by Q3 2025. Boss’ strategy is to rampup to Feasibility Study forecasts of 2.45Mlbs/annum U3O8 in FY2027. Overall capital costs have increased
primarily due to inflation.
“Adding to Honeymoon’s progress, our valuable investment into the Alta Mesa operation is bearing fruit,
with the project’s solid ramp-up resulting in Boss receiving its first shipment of 35,181lbs U3O8.
“These achievements position us for long-term success and creation of shareholder value, maximising our
ability to capitalise on what is clearly a new uranium cycle.
“Our production and growth outlook is underpinned by a balance sheet with no debt and liquid assets of
$252M.
“Security of supply is a major concern for nuclear utilities, particularly in the western world, and as a multimine tier 1 uranium producer, Boss is set to benefit from this changing and growing market”.
1
All dollar values are in Australian Dollars unless otherwise stated.
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
Page 2
Honeymoon Safety Performance
The Total Reportable Injury Frequency Rate (TRIFR) was 4.4 at the end of the quarter. This was an increase
from the prior quarter of a TRIFR of 2.1. The rise was due to low severity injuries recorded during the
quarter.
The safety, health and wellbeing of our workforce is a leading priority. There are a number of programs
of work associated with continual improvement on our safety systems, culture and risk management to
ensure that hazards in the workplace are reduced.
Table 1: Honeymoon TRIFR (12-month moving average)
Key Metric Quarter ended
December Q2 FY25
September Q1 FY25
4.4
2.1
TRIFR
Honeymoon Production Results for the December 2024 Quarter
Ramp-up to steady-state production continues to proceed to plan, as shown in the results for the
December 2024 quarter.
During the December quarter, a total of 137,084lbs U3O8 was drummed and 215,319lbs U3O8 equivalent
produced in NIMCIX columns 1 and 2. This represented a 55% and 96% increase respectively from the
September 2024 quarter production.
NIMCIX 1 continues to operate at nameplate capacity, NIMCIX 2 achieved nameplate capacity in
November 2024 and NIMCIX 3 recently commenced operations and is expected to achieve nameplate
capacity in February 2025. The remaining columns 4, 5 and 6 will be commissioned during CY2025 as part
of Boss’ strategy to ramp-up to Feasibility Study forecasts of 2.45Mlbs/annum U3O8.
Table 2: Operational physicals for the December 2024 Quarter as compared to the September Quarter 2024
Key Metric Quarter ended
Unit
December Q2 FY25
September Q1 FY25
2
1
2
1
861,204
729,299
(U3O8 mg/l)
116
71
(%)
97.8
97.2
(lbs)
215,319
110,050
(lbs)
137,084
89,516
Wellfields online
IX Columns operational
IX Flow (total)
1
3
(m )
PLS to IX tenor (weighted average)2
IX Recovery (weighted average)
IX Production (total)
1
U3O8 Drummed (total)
Notes: (1) Conversions: There are 1,000 litres per m 3 and 0.00000220462 lbs per mg (2) the tenors being achieved
from initial wellfields exceed the average LOM tenors forecast in the Feasibility Study should not be extrapolated
across the LOM.
Significantly, during the December quarter and extending into mid-January, a number of key milestones
were achieved to derisk delivery of FY25 guided production along with positioning the operation towards
the next step-change in ramp-up profile to 1.6Mlbs U3O8 annualised throughput rate. This includes:
•
Commissioning of Kiln 2, the final kiln required to achieve nameplate capacity
•
Final installation and commissioning of NIMIX Column 3
•
Preparation and readiness of Wellfield 3
As disclosed in the September 2024 Quarterly Report, production was impacted in October, with the
northern part of South Australia and far west New South Wales experiencing an abnormal weather event
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
Page 3
that affected power supply to these regions. The power supply to the Honeymoon project was also
impacted, with limited power restrictions imposed. These impacts were effectively managed and despite
slightly reduced production during that time, there is no change to forecast production of 850,000lbs of
U3O8 in 2025. Since acquiring the Honeymoon Uranium Project in December 2015, Boss has not noted any
other instances where power to the site from the grid was interrupted for any longer than a couple of
hours.
Production was also impacted during the quarter by slight time delays in commissioning and tuning the
second horizontal electrical kiln (calciner) in the Drying and Packing area at the back end of the processing
plant associated with the conversion of uranium peroxide to uranium oxide (U3O8). Unlike the front end
of the processing plant with the NIMCIX columns, where installation and commissioning can be performed
independently without any impacts to the operation, this is not the case with the back end of the
processing plant, which is more integrated. This explains the variance in IX production and U3O8 drummed
at the end of December quarter.
The second calciner became operational in mid-January, resulting in consistency (and an increase) in
production. From 14 January until 24 January 2025, the step-change in average daily production to
3,902lbs U3O8 demonstrates Honeymoon is already achieving the required production rate, providing
further confidence that the FY25 forecast of 850,000lbs will be achieved.
Initiatives to optimise plant performance are ongoing as learnings are implemented.
Honeymoon Construction Activities
Construction actives continue to progress on schedule. During the quarter Kiln 2 was integrated into the
plant, construction activities of NIMCIX column 3 and wellfield 3 were completed.
The remaining three NIMCIX columns 4,5 and 6 will be sequentially installed and commissioned over the
coming months until Q3 CY25, when column 4 is planned to come into operation. NIMCIX columns 5 and
6 will become operational in Q4 CY25, aligned with new wellfields being brought into production. This
will conclude the final capital project works.
Figure 1: NIMCIX Column 3 Commissioned and in Operation
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
Page 4
Figure 2: Wellfield 3 Flushed and Primed for Production
Exploration Activities
During the quarter, Boss completed infill drilling at the Gould’s Dam and Jason’s satellite deposits, as
reported on 20 November 2024 (See ASX release 2024 infill drilling on satellite uranium growth deposits
complete, dated 20 November 2024). This release included a number of significant intersections,
including 3.25m @ 3,873ppm pU3O8 (WRM0176).
Gould’s Dam and Jason’s deposits form an important part of Boss’ strategy to increase the production
rate and mine life at the Honeymoon mine and the results of this drilling program will feed into a scoping
study and ISR mining lease proposals. AMC Consultants were engaged to produce the mineral resource
update for these key satellite deposits. It is anticipated that this will be delivered in Q3 FY25.
Exploration activity focussed on mineral prospectivity analysis of an 80 km radius around the Honeymoon
operation, aimed at identifying high-priority targets that could represent additional undiscovered
resources. RSC consultants were engaged to generate a series of input maps and a prospectivity map will
be delivered in Q3 FY25. During the quarter, exploration drilling focussed on the Cummins Dam prospect,
located approximately 2 km north-east of the East Kalkaroo (Honeymoon) deposit which consisted of
twenty-four widely spaced mud rotary holes for approximately 2,880 m. Results from the drilling have
been positive, defining a zone of mineralisation of approximately 1km x 1km, which remains open.
Further drilling at Cummins Dam is planned in Q3FY25.
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
Page 5
Strong Balance Sheet
As at 31 December 2024, Boss has no debt and $252M of liquid assets (being cash, liquid investments and
physical uranium), an increase of $6.7M from 30 September 2024.
Table 3: Cash, inventory and investments
$000’s
December Q2 FY25
September Q1 FY25
65,177
66,551
Investments and other liquid assets
34,382
32,931
1
Inventory on hand
117,279
114,861
Loan receivable
34,808
30,560
Total cash and liquid investments
251,646
244,903
Cash on hand
Notes: (1) Inventory includes strategic inventory and inventory on hand. Excludes inventory ‘in circuit’.
Unrestricted cash and cash equivalents stood at $65.2M (which excludes a fully cash-backed
environmental bond of $13.5M) with a further $186.4M in liquid investments (including inventory).
Existing cash and liquid investments will fully support ramp up with no requirement for any external
capital or debt. The waterfall chart below highlights the December quarter movements in cash.
Figure 3: December Q2 FY25 cash ($000’s)
Boss Sales
During the quarter, Boss sold 200,000lbs U308, at a realised price of US$77.50/lb to receive cash of
US$15.5M ($25.2M).
Table 4: Sales
Key Metric
Unit
December Q2 FY25
September Q1 FY25
Sales
lbs
200,000
200,000
Realised price
US$/lb
77.5
78.0
Revenue
US$
15,500,000
15,608,000
Honeymoon’s first shipment of 57Klbs U308 has arrived at, and 78Klbs are in transit to, the Honeywell
Uranium Hexafluoride Processing Facility in Metropolis, Illinois, USA. Further, an additional 120Klbs are
in containers at Honeymoon which will form a part of the next shipment at the end of February.
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
Page 6
Boss’ contracting strategy is to monitor the markets and layer in contracts, predominantly market-related
for the uncommitted supply from Honeymoon and Alta Mesa, to optimise future pricing and, in the near
term, to ensure profitability and cash flow as production ramps up.
Cost Guidance
Honeymoon commenced commercial production on 1 January 2025, following its successful restart. As
previously noted, Boss committed to providing cost guidance once NIMCIX 3 had been successfully
commissioned, which has now occurred.
On this basis, Boss is pleased to provide 2H FY25 guidance for the Honeymoon Operation.
Table 5: Guidance for 2H FY25
1
Honeymoon Guidance
Production
Cash Cost – Fixed2
Cash Cost – Variable
2
Unit
2H FY25
(AUD)
(USD)4
lbs (000’s)
625
625
$/lb
22-24
14-15
$/lb
15-17
9-10
2
$/lb
37-41
23-25
Capex – Wellfields3
$M
17-20
11-12
Capex – Capital Projects
$M
19-21
12-13
Capex – Other sustaining capital
$M
1-2
1-2
Capex - Total
$M
38-43
24-26
Cash Cost – Total
Notes: (1) Guidance is for Honeymoon only and excludes Alta Mesa with definitions consistent with EFS. (2) Cash Cost
includes all mining costs, onsite processing costs, onsite general and administration costs and logistical costs. Excludes
royalties and capital expenditure. (3) Wellfields capex includes sustaining and deferred capex. (4) AUD/USD exchange
rate of 0.62 assumed
Cash cost update reinforces Honeymoon as a high margin mining operation and competitively positioned
on the cost curve. The cash cost per pound is expected to reduce in future years as fixed costs are
fractionalised by increased production.
Cash cost for 2H25 reflects an increase approximately in-line with CPI since the EFS2 (numbers were real
as at 1Q CY21). The composition of the key drivers of labour, reagents and power remain consistent with
the EFS. This result reinforces the strong technical work conducted during the feasibility study.
Wellfields capex represents cost to bring on wellfields and associated infrastructure, that are expected to
come online through to the end of FY26. Costs have mostly increased in-line with inflation except for ‘first
fill’ costs (~$2M) which are a new cost. Studies are underway to investigate potential recovery and reuse
of the reagents for future wellfields which will reduce this cost for future wellfields.
Project capex represents most of the cost to complete the Project phase which represents the installation
and commissioning of the additional IX columns 4-6. Cost has increased compared to the EFS mainly due
to increased labour cost and general inflation.
2
Refer to ASX: BOE announcement dated 21 June 2021
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
Page 7
Alta Mesa
On 8 October 2024, enCore Energy Corp. announced the grand opening celebration of the Alta Mesa
Uranium Plant with George W. Bush, the 43rd President of the United States.
Shortly thereafter on 25 October, enCore announced that the production ramp-up passed another
important milestone, with the first of three IX circuits nearing flow capacity.
Alta Mesa’s first IX circuit was commissioned in June 2024 with the second IX circuit planned to commence
operation in the first quarter of CY2025 and the third IX circuit planned to be online by year end of CY25.
During the quarter enCore announced more strong grade drilling results. Please refer to enCore’s
announcement dated 15 October 2024, for further information3.
The operation also observed increased wellfield recoveries as the ramp-up continues. Wellfield solution
head grades at Alta Mesa peaked at approximately 140 mg/l U3O8 and averaged approximately 65 mg/l
U3O8. Please refer to enCore’s announcement dated 14 November 2024, for further information4.
Alta Mesa is ramping up to an annualised production rate of 1.5Mlbs U3O8. Boss’ share of this production
is 30 per cent.
Figure 4: Alta Mesa Ramping-up Production
The Alta Mesa Project, which consists of over 200,000 acres plus the central processing plant and
wellfields, is managed by experienced uranium producer, and partner, enCore.
Boss acquired its 30 per cent interest in the Alta Mesa Project in February 2024 from enCore and its wholly
owned subsidiary, enCore Energy U.S. Corp., a highly credentialed United States uranium developer and
operator, for US$60M cash (see ASX release dated 27 February 2024).
3 enCore Energy Corp. announcement titled ‘enCore Energy Continues to Encounter High Grade Drill Results from the Alta Mesa Uranium
Project.’ dated 15 October 2024
https://www.sedarplus.ca/csa-party/records/document.html?id=744fc68bc7324711050b527b28fee210b7280edc50dc28686e95c17c76bb4c2d
4 enCore Energy Corp. announcement titled ‘enCore Energy Provides Q3 2024 Results and Operational Update’ dated 14 November 2024
https://www.sedarplus.ca/csa-party/records/document.html?id=930169abd688d55b1ac5399e71955f2548d544ad5ca9f192eee7a1883592a5a1
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
Page 8
Uranium Market Analysis
During 2024 fundaments improved significantly. On the demand side, International Energy Agency’s (IEA)
2023 World Energy Outlook, Net Zero Emissions by 2050 Scenario, which envisages charting a roadmap
to a 1.5-degree Celsius stabilization in rising global temperatures, projects more than a doubling of global
nuclear capacity from 417 GW, increasing to 916 GW, up from 871 GW in the 2022 edition, by 2050.
In related developments, the industry saw unprecedented interest in developing nuclear capacity to
support data centre growth. In 2024, several prominent companies, including Amazon, Microsoft, Meta,
and Google, announced memorandums of understanding (MOUs) with nuclear utilities to develop nuclear
capacity aimed at supporting data centres. This move highlights a strategic shift towards sustainable and
reliable energy sources to power the growing demands of data infrastructure.
The growing demand for electricity generation has also driven nuclear capacity uprates, life extensions
and re-commissioning of shut down reactors such as Diablo Canyon, Palisades, Three Mile Island, and
Duane Arnold. Nuclear capacity demand and associated uranium demand is expected to more than
double by 2050. In the USA, President Trump announced the Stargate Project, a $500 billion AI
infrastructure venture with an immediate $100 billion investment. The project will build data centres
across the U.S., to meet the growing demand for AI. The implications of this project for growth in
electricity demand are significant and expected to increase and advance demand for nuclear energy and
uranium.
While demand expectations are increasing, the risks on the supply side cannot be ignored. Geopolitical
concerns continue to dominate. These include potential import bans, sanctions, transportation issues,
potential tariffs and counter tariffs, trade restrictions in other goods and services, supporting nuclear
uranium production and fewer available ports, all of which continue to create uncertainty in the market
regarding the availability of supply now and in the future.
Figure 5: Historical U3O8 (Spot Price and Long-Term Price)
US$
160
140
120
100
80
60
40
20
-
U3O8 Spot Price
U3O8 Long-Term Price
Source: UxC, LLC https://www.uxc.com/
During 2024 the month end spot market price fell approximately 28% from January to December 2024.
Term prices however continued to trend upwards.
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
Page 9
Annual General Meeting
Boss Energy held its Annual General Meeting on 20 November 2024 and all resolutions were passed by a
poll.
December 2024 Quarterly Results Conference Call – 29 January 2025
Boss will hold a conference call today, Wednesday 29 January 2025, at 11am AEDT (8am AWST) with
Managing Director Duncan Craib, Chief Financial Officer Justin Laird and Chief Operating Officer Matt
Dusci, to discuss the results. To listen in live, please click on the link below and register your details.
https://loghic.eventsair.com/220328/795123/Site/Register
Appendix 5B disclosures
In line with its obligations under ASX Listing Rule 5.3.5, Boss notes that the only payments to related
parties of the Company, as disclosed in the Appendix 5B (Quarterly Cashflow Report) for the period ended
31 December 2024, consist of executive director and chief financial officer salaries and wages (including
superannuation) and payment of non-executive director fees.
During the quarter ended 31 December 2024, the Company spent approximately $14.2M on project and
exploration activities relating to its Honeymoon and Alta Mesa Projects. These activities included:
•
Technical studies costs
•
Construction equipment
•
Wellfield drilling and development costs
•
Engineering and construction expenses
•
Mineral exploration and evaluation costs
In addition to these activities the Company continued to incur costs relating to the ongoing maintenance
activities required at Honeymoon. The expenditure represents direct costs associated with these
activities as well as capitalised wages which can be directly attributable to Honeymoon.
This ASX announcement was approved and authorised by the Board of Boss Energy Limited.
For further information, contact:
Duncan Craib
Chief Executive Officer
P: +61 (8) 6263 4494
E: boss@bossenergy.com
For media enquiries, contact:
Paul Armstrong
Read Corporate
P: +61 (8) 9388 1474
E: info@readcorporate.com
ASX: BOE
www.bossenergy.com
OTCQX: BQSSF
Page 10
Reference to previous ASX announcements
In relation to the results of the Enhanced Feasibility Study announced on 21 June 2021, the Company
confirms, for the purposes of listing rule 5.19 and for all other purposes, that all material assumptions
underpinning the production target and forecast financial information included in that announcement
continue to apply and have not materially changed.
The mineral resource estimates in this announcement were reported by the Company in accordance with
listing rule 5.8 on 25 February 2019. The Company confirms it is not aware of any new information or data
that materially affects the information included in the previous announcement and that all material
assumptions and technical parameters underpinning the estimates in the previous announcement
continue to apply and have not materially changed.
Forward-Looking Statements
This announcement includes forward-looking statements. These forward-looking statements are based
on the Company’s expectations and beliefs concerning future events. Forward-looking statements are
necessarily subject to risks, uncertainties, and other factors, many of which are outside the control of Boss
Energy, which could cause actual results to differ materially from such statements. Boss Energy makes no
undertaking to subsequently update or revise the forward-looking statements made in this
announcement, to reflect the circumstances or events after the date of this announcement.
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
Page 11
Appendix One:
Schedule of Mining Tenements
The following information is provided pursuant to Listing Rule 5.3.3 for the quarter ended 31 December
2024.
Tenement Name
Location
Licence Number
Interest
Yarramba
South Australia
EL6510
100%
South Eagle
South Australia
EL6081
100%
Gould’s Dam
South Australia
EL6512
100%
Katchiwilleroo
South Australia
EL6511
100%
Ethiudna
South Australia
EL6020
100%
Gould’s Dam
South Australia
RL83-85
100%
Honeymoon Mine
South Australia
ML6109
100%
Prairie Dam
South Australia
EL6962
75%
Chalker Dam
South Australia
EL6963
75%
Oakvale
South Australia
EL6964
75%
Gairloch
South Australia
EL6965
75%
Venus Bay
South Australia
EL6992
100%
Darke Peak
South Australia
EL7013
100%
Rudall
South Australia
EL6999
100%
There were no mining tenement acquisitions or divestments during the quarter.
EL6512, 6511, 6020, 6510 and 6081 are subject to an earn-in agreement with First Quantum Minerals in
respect to the base and precious metal rights. Refer ASX release dated 10 February 2022 for further
information.
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
Page 12
Honeymoon Project Mineral Resource
Honeymoon’s Mineral Resource (lower cut-off of 250 ppm U3O8)
Classification
Tonnage
(Million Tonnes)
Average Grade
(ppm U3O8)
Contained Metal
(Mkg, U3O8)
Contained Metal
(Mlb, U3O8)
Measured
3.1
1,100
3.4
7.6
Indicated
18.4
630
12.0
25.5
Inferred
30.9
570
18.0
38.5
Total
52.4
620
32.5
71.6
The global Honeymoon Mineral Resource stands at 71.6Mlb (52.4Mt) with an average grade of 620ppm
U308, using a cut-off grade of 250ppm.
The current Honeymoon restart feasibility studies utilise only a portion of Honeymoon’s JORC resource,
excluding 36Mlb of JORC resource outside the HRA, which could expand the mine life, and Boss’ defined
exploration target could potentially extend the mine life beyond the initial 11 years and increase the
production profile. Honeymoon’s Federal EPIP Act approvals allow export of more than 3Mlbs/annum
U3O8 equivalent.
In addition to the global Mineral Resource, the Honeymoon Uranium Project also has an Exploration
Target range of 28Mt to 133Mt of mineralisation at a grade of 340ppm to 1,080ppm U308 for a contained
58Mlbs to 190Mlbs U308 (26,300 to 86,160 tonnes of contained U308), using a cut-off of 250ppm5. Note
the potential quantity and grade of the Exploration Target range is conceptual in nature. There has been
insufficient exploration to estimate a Mineral Resource and it is uncertain whether future exploration will
result in the definition of a Mineral Resource.
5
Refer to ASX: BOE announcement dated 25 March 2019
ASX: BOE
OTCQX: BQSSF
www.bossenergy.com
Page 13
Alta Mesa Project Mineral Resource
Alta Mesa & Mesteña Grande Mineral Resource
Summary (0.30 GT cut-off)1,2,3
Tons
Avg. Grade
(% U3O8)
Pounds
Total Measured Mineral Resource1
54,000
0.152
164,000
Alta Mesa Indicated Mineral Resource
1,397,000
0.106
2,959,000
119,000
0.120
287,000
Total Measured & Indicated Resources
1,570,000
0.109
3,410,000
Alta Mesa Inferred Mineral Resource
1,263,000
0.126
3,192,000
Mesteña Grande Inferred Mineral Resource
5,733,000
0.119
13,601,000
Total Inferred Resources
6,996,000
0.120
16,793,000
Mesteña Grande Indicated Mineral Resource
1. Represents that portion of the in-place mineral resource that are estimated to be recoverable within existing wellfields.
Wellfield recovery factors have not been applied to indicated and inferred mineral resources.
2. Technical Report Summary for the Alta Mesa Uranium Project, Brooks and Jim Hogg Counties, Texas, National Instrument
43-101, Technical Report prepared for enCore Energy Corp, Doug Beahm, P.E. 19 January 2023.
3. For the purposes of ASX Listing Rule 5.12, Boss Energy cautions that the mineral resources for the Alta Mesa Project are not
reported in accordance with the Australasian Code for Reporting of Mineral Resources and Ore Reserves 2012 (JORC Code).
The mineral resource estimate at the Alta Mesa Project is a foreign estimate prepared in accordance with Canadian National
Instrument 43-101. A competent person has not done sufficient work to classify the foreign estimate as a mineral resource
in accordance with the JORC Code, and it is uncertain whether further evaluation and exploration will result in an estimate
reportable under the JORC Code.
Foreign Resource Estimate
Please refer to Boss Energy's announcement to the ASX market announcements platform dated 6
December 2023 for additional technical information relating to the foreign resource estimate for the Alta
Mesa Project. Boss Energy confirms it is not in possession of any new information or data